A.M.PATEL INFRA PVT LTD: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

A.M.PATEL INFRA PVT LTD has 2 registrations in this build, including 180 and 51 Greens and 36 Greens. Its filings disclose 5 earlier MahaRERA projects: 0 of 4 past projects completed on time.

2Registrations in this build
5Past projects disclosed
+14 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
180 and 51 GreensAurangabad, Maharashtra2370%Registration lapsed
36 GreensAurangabad, Maharashtra3526%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
30 Greens
31 Oct 201231 Dec 2012+2 months
108 Green Heights and 50 Greens
31 Jan 201431 Jan 2015+12 months
180 and 51 greens
31 Jan 202419 May 2025+16 months
180 and 51 Greens
P51500004770
31 Jan 202419 May 2025+16 months
36 Greens
P51500050638
30 Nov 2027Not completed yetCertificate Signed

Frequently asked questions

How do I verify A.M.PATEL INFRA PVT LTD as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with A.M.PATEL INFRA PVT LTD?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.