New projects and RERA data in Aravalli district, Gujarat
17 projects are registered in Aravalli district: 2,839 units across them, 3 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 17 covered registrations, 5 have revised their promised completion date. Of the 16 that file a booking figure, the median is 30% booked as of the current data. Every figure comes from the projects' own GujRERA filings.
How far Aravalli possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 5 of 17 projects (29%) have moved at least once; the median move is 12 months and the longest is 48 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Projects in Aravalli
Showing all 17 projects.
Largest first, by the unit count in the filing.
| Project | Developer | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| VANDEMATARAM CITY CENTERModasa, 383315 | VYAPNILA TERMINALS (MODASA) PRIVATE LIMITED | 1060 | 20% | 20 Aug 2019 | Valid until 29 Jan 2028 |
| Zalak Township | Anvarhusen Abdulsattar Mansuri | 333 | 9% | 3 Sep 2021 | Valid until 31 Dec 2023 |
| APSARA BUSINESS CENTREMODASA, 383315 | C K PROPERTY | 256 | 0% | 7 Sep 2026 | Valid until 31 Dec 2028 |
| paavancity phase 3Modasa, 383315 | SHREE RAJ GROUP | 192 | 58% | 30 Apr 2019 | Valid until 30 Jun 2023 |
| Nandan Parisar | Nandan Developers | 152 | 20% | 15 Apr 2023 | Valid until 31 Mar 2027 |
| SIDDHI VINAYAK BUNGLOWS & ARCADEkhalikpur, 383315 | BROOKLAND SIDDHIVINAYAK PROJECTS | 140 | 0% | 25 May 2026 | Valid until 30 Sep 2028 |
| CITY CENTER | New suzan developers | 121 | 60% | 20 Dec 2018 | Valid until 30 Sep 2023 |
| BANDHAN ARCADEModasa, 383315 | BANDHAN DEVELOPERS | 110 | 40% | 15 Nov 2018 | Valid until 15 Apr 2021 |
| PAAVANCITY PHASE 2Modasa, 383315 | SHREE RAJ GROUP | 96 | 75% | 7 Mar 2018 | Valid until 31 Dec 2019 |
| THE SKYLINE CITYMODASA, 383315 | THE SKYLINE CITY | 93 | 0% | 27 Jan 2026 | Valid until 31 Jul 2029 |
| SHAMIANA HEIGHTSModasa, 383315 | IMPERIAL SPACE | 69 | - | 5 Jan 2018 | Valid until 30 Jun 2019 |
| SHUBH DIVINEModasa, 383315 | SHRI GOKUL ENTERPRISE | 61 | 77% | 13 Jul 2018 | Valid until 30 Jun 2021 |
| SG PARKMODASA, 383315 | ANKITKUMAR DINESHBHAI PATEL AND OTHERS | 35 | 0% | 12 Nov 2024 | Valid until 30 Apr 2028 |
| SHUBH HEIGHT | GIRIRAJ ENTERPRISE | 35 | 54% | 12 Jan 2021 | Valid until 31 Mar 2023 |
| RAJ ARCADE | ARVALLI ENTERPRISES | 33 | 100% | 18 Mar 2021 | Valid until 31 Dec 2023 |
| FORAM SWARNIM RESIDENCY(PHASE 1) PLOT NO -B8 TO B11,B14,B15,B21 TO B37,B43 TO B45,B48 TO B51Modasa, 383315 | SWARNIM CORPORATION | 30 | 53% | 26 Apr 2018 | Valid until 30 Sep 2020 |
| Vrundavan VillaModasa, 383315 | SAMAY BUILDCON | 23 | 0% | 10 Jun 2024 | Valid until 30 Jun 2026 |
Developers active in Aravalli
SHREE RAJ GROUP (2), VYAPNILA TERMINALS (MODASA) PRIVATE LIMITED (1), Anvarhusen Abdulsattar Mansuri (1), C K PROPERTY (1), Nandan Developers (1), BROOKLAND SIDDHIVINAYAK PROJECTS (1). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Aravalli projects listed above?
Compare each project against its neighbours, not against the brochure. Of the 16 projects on this page that file a booking figure, the median is 30% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Aravalli project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What if a Aravalli project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own GujRERA filings, and we read every report.