Home / Browse projects / Surat, Gujarat / ZIRCON ARENA

Valid until 1 Dec 2023 Commercial project

ZIRCON ARENA

By ZIRCON ENTERPRISE

RG-GJ-83208 · RERA PR/GJ/SURAT/CHORASI/SUDA/CAA04658/EX2/A1C/210323 · Last updated on GujRERA portal: 16 Mar 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Dec 2023Possession promisedmoved 24 months from the original
8 of 9Construction stages donefurthest along: Stilt Floor, 0%
85 of 181Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

ZIRCON ARENA is a Commercial project by ZIRCON ENTERPRISE in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORASI/SUDA/CAA04658/EX2/A1C/210323 on 11 Jan 2019. Possession is promised by 1 Dec 2023. The completion date has moved by 24 months from the original filing. 96 of the 181 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameZIRCON ARENA
  • TypeCommercial
  • Location
    • BLOCK NO.22
    • OP NO.22
    • FP NO.22
    • TPS NO.50(BHATHA-BET)
    • MOJE-BHATHA
    • TA: CHORYASI
    • DIST-SURAT
    • Chorasi
    • Surat
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORASI/SUDA/CAA04658/EX2/A1C/210323
  • ReraGenie IDRG-GJ-83208

Builder

  • NameZIRCON ENTERPRISE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2019First promiseDec 2021Revised toDec 2023

Key facts

Registration and timeline

  • StatusValid until 1 Dec 2023
  • Registered on11 Jan 2019
  • Promised completion1 Dec 2023
  • Revised completionRevised to 1 Dec 2023 (originally 1 Dec 2021)
  • Buildings1 building record
  • Documents filed40 files

Current status

53%96 of 181 units booked
100.0%Of the estimated cost spent so far

Figures as on 16 Mar 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---0178181

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 16 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

A: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 16 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,584 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 15.00 cr
Cost incurredRs 15.00 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 15.00 crRs 15.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTUSHAR H SUTARIYA
EngineerSMITKUMAR JAWAHARBHAI THAKKAR

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/CHORASI/SUDA/CAA04658/EX1/271221Applied Dec 2021; approved Dec 2021
PR/GJ/SURAT/CHORASI/SUDA/CAA04658/EX2/210323Applied Dec 2022; approved Mar 2023

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORASI/SUDA/CAA04658/EX2/A1C/210323 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)16 Mar 2024
Engineer's certificate (Form 2)16 Mar 2024
Engineer's certificate annexure16 Mar 2024
Site photograph, A16 Mar 2024
RERA registration certificate11 Jan 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

53%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 24 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep ZIRCON ARENA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Surat2,600+ in Surat

2 kmZIRCON ARENAOther 115Dot size: filed unitsN

Filed coordinates, straight-line distance. 115 registered projects within 2 km.

Builder: ZIRCON ENTERPRISE

ZIRCON ENTERPRISE has 1 registration on GujRERA, including ZIRCON ARENA. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if ZIRCON ARENA is delayed beyond 1 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ZIRCON ARENA?

The registered promoter entity is ZIRCON ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ZIRCON ARENA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ZIRCON ARENA?

The professionals named in the filing: Architect: TUSHAR H SUTARIYA; Engineer: SMITKUMAR JAWAHARBHAI THAKKAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ZIRCON ARENA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ZIRCON ARENA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ZIRCON ARENA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.