Home / Browse projects / Surat, Gujarat / SURAT DIAMOND BOURSE

Valid until 30 Jun 2023 Commercial project

SURAT DIAMOND BOURSE

By SDB DIAMOND BOURSE

RG-GJ-36379 · RERA PR/GJ/SURAT/SURAT CITY/Others/CAA05247/A1C/EX1/260722 · Last updated on GujRERA portal: 9 Jun 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2023Possession promisedmoved 12 months from the original
106 of 106Construction stages doneacross 12 buildings; every applicable stage filed complete
457 of 4,798Units unsoldnot recorded sold or booked
Jump to the 52 documents Report an error

SURAT DIAMOND BOURSE is a Commercial project by SDB DIAMOND BOURSE in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Others/CAA05247/A1C/EX1/260722 on 10 Apr 2019. Possession is promised by 30 Jun 2023. The completion date has moved by 12 months from the original filing. 4,341 of the 4,798 units on this registration are recorded sold or booked, and 106 of 106 construction stages are filed complete.

At a glance

Project

  • NameSURAT DIAMOND BOURSE
  • TypeCommercial
  • Location
    • BLOCK NO.177
    • VILLAGE KHAJOD
    • TALUKA MAJURA
    • SURAT
    • KHAJOD
    • Surat City
    • Surat
    • 394550
  • Pincode394550
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/Others/CAA05247/A1C/EX1/260722
  • ReraGenie IDRG-GJ-36379

Builder

  • NameSDB DIAMOND BOURSE
  • Entity typeCOMPANY

Key dates

this monthRegisteredApr 2019First promiseJun 2022Revised toJun 2023

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2023
  • Registered on10 Apr 2019
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2022)
  • Buildings12 building records
  • Documents filed52 files

Current status

90%4341 of 4,798 units booked
100.5%Of the estimated cost spent so far

Figures as on 9 Jun 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 2 (A)---0105108
TOWER 3 (H)---0300303
TOWER 4 (B)---0593605
TOWER 5 (G)---0540542
TOWER 6 (C)---0600603
TOWER 7 (F)---0540542
TOWER 8 (D)---0540542
TOWER 9 (E)---0540541
SPINE---0780805
DIAMOND CLUB---0027
UTILITY BUILDING------
TOWER 1 (J)---0179180

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building12

As on 9 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

106 of 106 construction stages are filed complete across 12 buildings.

TOWER 2 (A)100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER 3 (H)100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER 4 (B)100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER 5 (G)100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER 6 (C)100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER 7 (F)100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER 8 (D)100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER 9 (E)100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
SPINE100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
DIAMOND CLUB100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
UTILITY BUILDING100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER 1 (J)100%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 9 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyYes100%
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area143,825 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 1,440.02 cr
Cost incurredRs 1,447.50 cr
Spent of the estimate100.52%
BuildingWingEstimatedIncurred
TOWER 1 (J)NARs 120.00 crRs 120.62 cr
TOWER 2 (A)NARs 120.00 crRs 120.62 cr
TOWER 3 (H)NARs 120.00 crRs 120.62 cr
TOWER 4 (B)NARs 120.00 crRs 120.62 cr
TOWER 5 (G)NARs 120.00 crRs 120.62 cr
TOWER 6 (C)NARs 120.00 crRs 120.62 cr
TOWER 7 (F)NARs 120.00 crRs 120.62 cr
TOWER 8 (D)NARs 120.00 crRs 120.62 cr
TOWER 9 (E)NARs 120.00 crRs 120.62 cr
SPINENARs 120.00 crRs 120.62 cr
DIAMOND CLUBNARs 120.00 crRs 120.62 cr
UTILITY BUILDINGNARs 120.00 crRs 120.62 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMORPHOGENESIS
EngineerJW CONSULTANTS LLP

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/Others/CAA05247/A1C/EX1/260722Applied Jun 2022; approved Jul 2022

Documents filed52

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Others/CAA05247/A1C/EX1/260722 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)9 Jun 2023
Engineer's certificate (Form 2)9 Jun 2023
Engineer's certificate annexure9 Jun 2023
Accountant's certificate (Form 3)9 Jun 2023
Site photograph, TOWER 2 (A)9 Jun 2023
Site photograph, TOWER 3 (H)9 Jun 2023
Site photograph, TOWER 4 (B)9 Jun 2023
Site photograph, TOWER 5 (G)9 Jun 2023
Site photograph, TOWER 6 (C)9 Jun 2023
Site photograph, TOWER 7 (F)9 Jun 2023
Site photograph, TOWER 8 (D)9 Jun 2023
Site photograph, TOWER 9 (E)9 Jun 2023
Site photograph, SPINE9 Jun 2023
Site photograph, DIAMOND CLUB9 Jun 2023
Site photograph, UTILITY BUILDING9 Jun 2023
Site photograph, TOWER 1 (J)9 Jun 2023
RERA registration certificate10 Apr 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

90%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep SURAT DIAMOND BOURSE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KHAJOD2,600+ in Surat

2 kmSURAT DIAMOND BOURSEOther 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: SDB DIAMOND BOURSE

SDB DIAMOND BOURSE has 1 registration on GujRERA, including SURAT DIAMOND BOURSE. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if SURAT DIAMOND BOURSE is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SURAT DIAMOND BOURSE?

The registered promoter entity is SDB DIAMOND BOURSE, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SURAT DIAMOND BOURSE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SURAT DIAMOND BOURSE?

The professionals named in the filing: Architect: MORPHOGENESIS; Engineer: JW CONSULTANTS LLP. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SURAT DIAMOND BOURSE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SURAT DIAMOND BOURSE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SURAT DIAMOND BOURSE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.