Home / Browse projects / Dharwad, Karnataka / ZINNIA

Registration approved No litigation declared Mixed Development project

ZINNIA

By Manthan Groups builders and developers

RG-KA-60506 · RERA PRM/KA/RERA/1259/410/PR/180519/001749 · Last updated on RERA Karnataka portal: 15 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 39 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Mar 2026Possession promisedmoved 39 months from the original
4 of 17Construction stages donefurthest along: RCC or MS Framed structure, 89%
54 of 95Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 73 documents Report an error

ZINNIA is a Mixed Development project by Manthan Groups builders and developers in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/410/PR/180519/001749 on 19 May 2018. Possession is promised by 31 Mar 2026. The completion date has moved by 39 months from the original filing. 41 of the 95 units on this registration are recorded sold or booked, and 4 of 17 construction stages are filed complete.

At a glance

Project

  • NameZINNIA
  • TypeMixed Development
  • Location
    • Dharwad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1259/410/PR/180519/001749
  • ReraGenie IDRG-KA-60506

Builder

  • NameManthan Groups builders and developers
  • Entity typePartnership Firm
  • Authorized SignatoryManoj shantaram Raykar

Key dates

this monthRegisteredMay 2018First promiseDec 2022Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 May 2018
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 31 Dec 2022)
  • Buildings1 building record
  • Documents filed73 files

Current status

43%41 of 95 units booked
32.1%Of the estimated cost spent so far

Figures as on 15 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ZINNIA-----95

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 17 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 89%.

Building: 58% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure89%
Masonry construction: Bricks, Concrete blocks etc72%
Plastering inside , outside & Ceiling65%
Joinery: Doors, Windows, Ventilators etc45%
Basic work of Water supply, Sanitary and Electrification40%
Dadoing, Skirting, Flooring, Tiles work (All types)38%
Railing and Grill fixing40%
Electrification, Water supply and Sanitary Finishing52%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network6%
Weather Proof work(tile,concrete)20%
Painting30%
Elevation work40%
Internal and External work including landscapes as per santioned drawings42%

Progress on shared amenities41

As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes30%
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes42%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes0%
Fire protection and fire safety requirementsYes8%
Education/Health/Other public amenitiesYes30%
Electricity supply transformer and substationYes24%
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes20%
ElectricityYes30%
Smart Home AutomationYes8%
CCTV SurveillanceYes25%
Club HouseYes50%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes15%
Swimming PoolYes60%
GymYes40%
ParksNoNot applicable
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes10%
Air Conditioning And incerntionNoNot applicable
StaircasesYes90%
LiftsYes68%
Staircases and Lift lobbies, corridor,lobbies, corridorYes70%
Fire escapesYes14%
Common entrance and exit for the building / common portico/foyer/verandahYes62%
BasementYes100%
TerraceNoNot applicable
Outer WallYes78%
Open parking areas and common storage spacesYes78%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,977 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.00 cr
Cost incurredRs 9.63 cr
Spent of the estimate32.1%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 25.32 crRs 8.63 cr
On-site expenditure-Site OverheadRs 3.86 crRs 95.12 lakh
Payment of chargesRs 69.47 lakh-
Payment of feesRs 4.25 lakh-
On-site expenditure-Consultants FeesRs 4.09 lakh-
On-site expenditure-Salaries of workersRs 3.26 lakhRs 3.96 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.28 lakhRs 53,000
Payment of Premiums-Rs 9,320

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShemayal Faiz
EngineerSTERLING ENGINEERING CONSULTANCY SERVICES PRIVATE LIMITED

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2022 → Sep 2023

No reason recorded in the filing

EX/PRM/KA/RERA/1259/410/PR/230912/001749Sep 2023 → Sep 2024

Reason as filed by the promoterDelay in getting loan

ExtensionSep 2024 → Mar 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed73

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/410/PR/180519/001749 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE-Q4 JAN-MARCH 26-A.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate-Q4 Jan-March26 (1).pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate -Q4 Jan-March26.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: C A Certificate Q3.pdf10 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect's Certificates Q 3.pdf10 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer's Certificate Q 3.pdf10 Feb 2026
Q3 2025-26 Water supply and sewage board10 Feb 2026
Q3 2025-26 KPTCL- BESCOM10 Feb 2026
Q3 2025-26 Fire and Safety10 Feb 2026
Q3 2025-26 Airport Authority of India10 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department10 Feb 2026
CertificateFile: certificate of registration of firm.jpg-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Architect's Certificate Form EX1 Till Date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer certificate work done till date.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate Fund Utilization Form Ex3_.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect's Certificate FX2Pending work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer certificate Pending work From EX6.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate for funds require Form Ex4_.pdf-
AffidavitFile: Affidavit_.pdf-
Latest Encumbrance CertificateFile: ec from 2004to 2023 manthan.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letters__compressed (2).pdf-
Details Of Sold/ Un-sold UnitsFile: Sold and unsold Flats.pdf-
Document 1File: Affidavit cum Declaration_.pdf-
Building PERMISSION COMMENCEMENT-
merged site plans compressed-
PLAN-
sale deed of zinnia-
Agreement of sale as per RERA (1)-
Sale deed RTC-
SECTION PLAN 7-7-
Area Development Plan-
ALLOTMENT LETTER (PDF)-
broucher-
Project Specifications merged-
Encumrance-
RTC sale deed plan-
Joint Development-
RERA Letter-
Conversion land doc merged-
mergerd All Fire (1)-
NOC Airport Authority-
NOC Hescom-
NOC BSNL-
Aproved layout plan-
SECTION PLAN 7-7-
Advocate search report 1-
Balance Sheet 2016 - 2017File: Balance Sheet.jpg-
Balance Sheet 2015 - 2016File: Balance sheet 15-16.jpg-
Balance Sheet 2014 - 2015File: BALANCE SHEET.pdf-
Audited Profit and Loss Statement 2016 - 2017File: PL.pdf-
Audited Profit and Loss Statement 2015 - 2016File: pl.jpg-
Audited Profit and Loss Statement 2014 - 2015File: PL.pdf-
Director's Report 2016 - 2017File: Directors report.pdf-
Director's Report 2015 - 2016File: Directors report.pdf-
Director's Report 2014 - 2015File: Directors report.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow.pdf-
Auditor's Report 2016 - 2017File: AUDITORS REPORT.pdf-
Auditor's Report 2015 - 2016File: Auditors Report.pdf-
Auditor's Report 2014 - 2015File: Auditors report 14-15.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: 16-17 ITR.jpg-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 15-16.jpg-
Income Tax Return Acknowledgement 2014 - 2015File: ITR.pdf-
Affidavit Cum Declaration-
Prospectus/BrochureFile: Zinnia Brochure compressed.pdf-
Advertisement Copy 1File: Rera Advertisement.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1259_410_PR_180519_001749 (2).xlsx-

How this compares with Dharwad

43%of this project is bookeddistrict median 38%
29%of Dharwad projects moved their completion datethis one moved by 39 months
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep ZINNIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

2 kmZINNIAOther 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: Manthan Groups builders and developers

Manthan Groups builders and developers has 1 registration on RERA Karnataka, including ZINNIA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if ZINNIA is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ZINNIA?

The registered promoter entity is Manthan Groups builders and developers, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ZINNIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ZINNIA?

The professionals named in the filing: Architect: Shemayal Faiz; Engineer: STERLING ENGINEERING CONSULTANCY SERVICES PRIVATE LIMITED. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ZINNIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ZINNIA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ZINNIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.