ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / WESTLANDS

Valid until 30 Jan 2028 Residential/Group Housing project

WESTLANDS

By GOOD VALUE PROPERTIES INDIA LLP

RG-GJ-55162 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA12618/A2R/210726/300927 · Last updated on GujRERA portal: 10 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jan 2028Possession promisedno revision filed
5 of 9Construction stages donefurthest along: Internal walls, 90%
11 of 59Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

WESTLANDS is a Residential/Group Housing project by GOOD VALUE PROPERTIES INDIA LLP in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA12618/A2R/210726/300927 on 10 Nov 2023. Possession is promised by 30 Jan 2028. 48 of the 59 units on this registration are recorded sold or booked, and 5 of 9 construction stages are filed complete.

At a glance

Project

  • NameWESTLANDS
  • TypeResidential/Group Housing
  • Location
    • Westlands
    • Near Sukrut Repose
    • Ambli
    • Ambli
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA12618/A2R/210726/300927
  • ReraGenie IDRG-GJ-55162

Builder

  • NameGOOD VALUE PROPERTIES INDIA LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredNov 2023PromisedJan 2028

Key facts

Registration and timeline

  • StatusValid until 30 Jan 2028
  • Registered on10 Nov 2023
  • Promised completion30 Jan 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed43 files

Current status

81%48 of 59 units booked
74.4%Of the estimated cost spent so far

Figures as on 10 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B+C+D---59059

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

A+B+C+D: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%

Progress on shared amenities19

As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes20%
Water supplyYes40%
Sewerage (chamber, lines, septic tank, STP)Yes30%
Storm water drainsYes40%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes40%
Treatment and disposal of sewage and sullage waterYes30%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes30%
Energy managementYes20%
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes30%
Fire fightingYes40%
Drinking water facilitiesYes40%
Emergency evacuationYes10%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,467 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 82.00 cr
Cost incurredRs 61.02 cr
Spent of the estimate74.41%
BuildingWingEstimatedIncurred
A+B+C+DNARs 82.00 crRs 61.02 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUPESH M. BHATT
EngineerGAURAV BABULAL PRAJAPATI

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA12618/A2R/210726/300927 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)10 Jul 2026
Engineer's certificate (Form 2)1 May 2026
Engineer's certificate annexure1 May 2026
Architect's certificate (Form 1)25 Apr 2026
Site photograph, A+B+C+D25 Apr 2026
RERA registration certificate10 Nov 2023
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

81%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep WESTLANDS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ambli5,400+ in Ahmedabad

2 kmWESTLANDSOther 154Dot size: filed unitsN

Filed coordinates, straight-line distance. 154 registered projects within 2 km.

Builder: GOOD VALUE PROPERTIES INDIA LLP

GOOD VALUE PROPERTIES INDIA LLP has 1 registration on GujRERA, including WESTLANDS. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if WESTLANDS is delayed beyond 30 Jan 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of WESTLANDS?

The registered promoter entity is GOOD VALUE PROPERTIES INDIA LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in WESTLANDS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at WESTLANDS?

The professionals named in the filing: Architect: RUPESH M. BHATT; Engineer: GAURAV BABULAL PRAJAPATI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WESTLANDS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WESTLANDS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WESTLANDS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.