Home / Browse projects / Vadodara, Gujarat / VRAJ VILLA

Valid until 28 Aug 2018 Residential/Group Housing project

VRAJ VILLA

By SHREE BHAKTI CORPORATION PVT LTD

RG-GJ-57564 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA03049/020718 · Last updated on GujRERA portal: 10 May 2019

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Aug 2018Possession promisedno revision filed
608 of 608Construction stages doneacross 101 buildings; every applicable stage filed complete
Jump to the 136 documents Report an error

VRAJ VILLA is a Residential/Group Housing project by SHREE BHAKTI CORPORATION PVT LTD in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA03049/020718 on 2 Jul 2018. Possession is promised by 28 Aug 2018.

At a glance

Project

  • NameVRAJ VILLA
  • TypeResidential/Group Housing
  • Location
    • OPP. NALANDA COLLEGE
    • NEAR PARIWAR CHAR RASTA
    • WAGHODIA DABHOI RING ROAD
    • Bapod
    • Vadodara
    • 390025
  • Pincode390025
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA03049/020718
  • ReraGenie IDRG-GJ-57564

Builder

  • NameSHREE BHAKTI CORPORATION PVT LTD
  • Entity typeCOMPANY

Key dates

this monthRegisteredJul 2018PromisedAug 2018

Key facts

Registration and timeline

  • StatusValid until 28 Aug 2018
  • Registered on2 Jul 2018
  • Promised completion28 Aug 2018
  • Revised completionNone
  • Buildings101 building records
  • Documents filed136 files

Current status

100.0%Of the estimated cost spent so far

Figures as on 10 May 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101
DUPLEX-----101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 10 May 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 101 buildings; the table lists the first 20.

608 of 608 construction stages are filed complete across 101 buildings.

DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
DUPLEX100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 10 May 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area25,394 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 22.44 cr
Cost incurredRs 22.44 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh
DUPLEXNARs 22.22 lakhRs 22.22 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEV ARCHITECTS
EngineerASHOK SHAH & ASSCOCIATES

Documents filed136

As listed on the registration, under the names the promoter filed them with; the newest 80 of 136 are shown. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA03049/020718 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)10 May 2019
Engineer's certificate (Form 2)10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019
Site photograph, DUPLEX10 May 2019

How this compares with Vadodara

23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep VRAJ VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bapod2,900+ in Vadodara

2 kmVRAJ VILLAOther 208Dot size: filed unitsN

Filed coordinates, straight-line distance. 208 registered projects within 2 km.

Builder: SHREE BHAKTI CORPORATION PVT LTD

SHREE BHAKTI CORPORATION PVT LTD has 1 registration on GujRERA, including VRAJ VILLA. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if VRAJ VILLA is delayed beyond 28 Aug 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VRAJ VILLA?

The registered promoter entity is SHREE BHAKTI CORPORATION PVT LTD, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VRAJ VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VRAJ VILLA?

The professionals named in the filing: Architect: DEV ARCHITECTS; Engineer: ASHOK SHAH & ASSCOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRAJ VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRAJ VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRAJ VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.