Home / Browse projects / Ahmedabad, Gujarat / Vishwanath Sarathya West

Valid until 31 Dec 2026 Mixed Development project

Vishwanath Sarathya West

By Vishwanath Builders through Prop Hitesh R Vyas

RG-GJ-85261 · RERA PR/GJ/AHMEDABAD/SANAND/AUDA/MAA10293/A1M/140323 · Last updated on GujRERA portal: 6 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2026Possession promisedno revision filed
25 of 45Construction stages doneacross 5 buildings; furthest along: Stilt Floor, 86%
269 of 700Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

Vishwanath Sarathya West is a Mixed Development project by Vishwanath Builders through Prop Hitesh R Vyas in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/SANAND/AUDA/MAA10293/A1M/140323 on 8 Jun 2022. Possession is promised by 31 Dec 2026. 431 of the 700 units on this registration are recorded sold or booked, and 25 of 45 construction stages are filed complete.

At a glance

Project

  • NameVishwanath Sarathya West
  • TypeMixed Development
  • Location
    • Plot No.15
    • N. D. Avenue
    • Opp. Vishwanath Sarathya
    • VIP Road
    • Shela
    • Sanand
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/SANAND/AUDA/MAA10293/A1M/140323
  • ReraGenie IDRG-GJ-85261

Builder

  • NameVishwanath Builders through Prop Hitesh R Vyas
  • Entity typeIndividual/Propritorship
  • Other registrations2 more →

Key dates

this monthRegisteredJun 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on8 Jun 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings5 building records
  • Documents filed39 files

Current status

62%431 of 700 units booked
69.4%Of the estimated cost spent so far

Figures as on 6 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
H---7432106
G---82082
A+B---16710177
E+F---1670167
C+D---1680168

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 6 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

25 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is Stilt Floor, at 86%.

H80%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor66%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats66%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing47%
G86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor85%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing61%
A+B88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor85%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing56%
E+F73%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor45%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats45%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing30%
C+D88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor86%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats86%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing48%

Progress on shared amenities23

As on 6 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes40%
Water supplyYes70%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsYes0%
Landscaping and tree plantingYes40%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes20%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes30%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes10%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes90%
Plinth protectionYes40%
Water tankYes100%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,243 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 183.00 cr
Cost incurredRs 126.94 cr
Spent of the estimate69.37%
BuildingWingEstimatedIncurred
A+BNARs 46.70 crRs 34.56 cr
E+FNARs 43.20 crRs 28.08 cr
C+DNARs 42.30 crRs 31.30 cr
HNARs 28.50 crRs 18.50 cr
GNARs 22.30 crRs 14.49 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectADS Architect Pvt. Ltd.
EngineerBhoomi Consultants

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/SANAND/AUDA/MAA10293/A1M/140323 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)6 Oct 2024
Engineer's certificate annexure6 Oct 2024
RERA registration certificate8 Jun 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Proforma sale deed-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

62%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Vishwanath Sarathya West on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmVishwanath Sarathya WestOther 224Dot size: filed unitsN

Filed coordinates, straight-line distance. 224 registered projects within 2 km.

Builder: Vishwanath Builders through Prop Hitesh R Vyas

Vishwanath Builders through Prop Hitesh R Vyas has 3 registrations on GujRERA, including Vishwanath Sarathya and Vishwanath Samam. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Vishwanath Sarathya West is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Vishwanath Sarathya West?

The registered promoter entity is Vishwanath Builders through Prop Hitesh R Vyas, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Vishwanath Sarathya West?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Vishwanath Sarathya West?

The professionals named in the filing: Architect: ADS Architect Pvt. Ltd.; Engineer: Bhoomi Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vishwanath Sarathya West?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vishwanath Sarathya West. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vishwanath Sarathya West to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.