Home / Browse projects / Ahmedabad, Gujarat / VEDKALP

Valid until 30 Apr 2028 Residential/Group Housing project

VEDKALP

By TATVA INFRASTRUCTURE

RG-GJ-67103 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RN300AA10200/130123 · Last updated on GujRERA portal: 5 Jan 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
22 of 36Construction stages doneacross 4 buildings; furthest along: Installation of lifts, 90%
130 of 212Units unsoldnot recorded sold or booked
Jump to the 28 documents Report an error

VEDKALP is a Residential/Group Housing project by TATVA INFRASTRUCTURE in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RN300AA10200/130123 on 13 Jan 2023. Possession is promised by 30 Apr 2028. 82 of the 212 units on this registration are recorded sold or booked, and 22 of 36 construction stages are filed complete.

At a glance

Project

  • NameVEDKALP
  • TypeResidential/Group Housing
  • Location
    • VEDKALP
    • B/S SONA HI SONA
    • OPP. HEALTH ONE HOSPITAL
    • NR. 200 FT. S.P. RING ROAD
    • VASTRAL
    • VASTRAL
    • Ahmedabad City
    • Ahmedabad
    • 382415
  • Pincode382415
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RN300AA10200/130123
  • ReraGenie IDRG-GJ-67103

Builder

  • NameTATVA INFRASTRUCTURE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2023PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on13 Jan 2023
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings4 building records
  • Documents filed28 files

Current status

39%82 of 212 units booked
81.2%Of the estimated cost spent so far

Figures as on 5 Jan 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---56056
B---52052
C---52052
D---52052

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 5 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of lifts, at 90%.

A61%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B69%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats23%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
C77%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats70%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%
D85%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%

Progress on shared amenities19

As on 5 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes50%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,209 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 70.36 cr
Cost incurredRs 57.16 cr
Spent of the estimate81.24%
BuildingWingEstimatedIncurred
ANARs 24.16 crRs 17.75 cr
BNARs 15.40 crRs 12.32 cr
CNARs 15.40 crRs 13.09 cr
DNARs 15.40 crRs 14.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMahendrasinh Madhusinh Khasavat
EngineerACHAL JITENDRAKUMAR PARIKH

Documents filed28

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RN300AA10200/130123 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)5 Jan 2026
Engineer's certificate (Form 2)5 Jan 2026
Engineer's certificate annexure5 Jan 2026
Accountant's certificate (Form 3)5 Jan 2026
Site photograph, A5 Jan 2026
Site photograph, A5 Jan 2026
Site photograph, A5 Jan 2026
Site photograph, B5 Jan 2026
Site photograph, C5 Jan 2026
Site photograph, D5 Jan 2026
RERA registration certificate13 Jan 2023
Proforma agreement for sale-
Project specific document-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Proforma sale deed-
Project photograph-

How this compares with Ahmedabad

39%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep VEDKALP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near VASTRAL5,400+ in Ahmedabad

2 kmVEDKALPOther 188Dot size: filed unitsN

Filed coordinates, straight-line distance. 188 registered projects within 2 km.

Builder: TATVA INFRASTRUCTURE

TATVA INFRASTRUCTURE has 1 registration on GujRERA, including VEDKALP. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if VEDKALP is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VEDKALP?

The registered promoter entity is TATVA INFRASTRUCTURE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VEDKALP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VEDKALP?

The professionals named in the filing: Architect: Mahendrasinh Madhusinh Khasavat; Engineer: ACHAL JITENDRAKUMAR PARIKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VEDKALP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VEDKALP. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VEDKALP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.