Home / Browse projects / Ahmedabad, Gujarat / Sahjanand Business Park

Valid until 30 Jun 2026 Commercial project

Sahjanand Business Park

By Sahjanand Developers

RG-GJ-09590 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA00952/081217 · Last updated on GujRERA portal: 31 Mar 2021

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2026Possession promisedno revision filed
88 of 96Construction stages doneacross 12 buildings; furthest along: Excavation, 0%
284 of 434Units unsoldnot recorded sold or booked
Jump to the 49 documents Report an error

Sahjanand Business Park is a Commercial project by Sahjanand Developers in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA00952/081217 on 8 Dec 2017. Possession is promised by 30 Jun 2026. 150 of the 434 units on this registration are recorded sold or booked, and 88 of 96 construction stages are filed complete.

At a glance

Project

  • NameSahjanand Business Park
  • TypeCommercial
  • Location
    • Sahjanand Business Park
    • Opp. Pam Hotel
    • Odhav-Nikol Ring Road
    • Nikol
    • Ahmedabad - 382350
    • Nikol
    • Ahmedabad City
    • Ahmedabad
    • 382415
  • Pincode382415
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA00952/081217
  • ReraGenie IDRG-GJ-09590

Builder

  • NameSahjanand Developers
  • Entity typePARTNERSHIP FIRM
  • Other registrations8 more →

Key dates

this monthRegisteredDec 2017PromisedJun 2026

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2026
  • Registered on8 Dec 2017
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings12 building records
  • Documents filed49 files

Current status

35%150 of 434 units booked
74.0%Of the estimated cost spent so far

Figures as on 31 Mar 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---0166166
B---0140140
C---088
D---088
E---01616
F---01212
G---01212
H---01717
I---01717
J---01212
L---066
M---02020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building12

As on 31 Mar 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

88 of 96 construction stages are filed complete across 12 buildings. The stage furthest along is Excavation, at 0%.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
H100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
I100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
J100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
L100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
M100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 31 Mar 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,729 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 18.11 cr
Cost incurredRs 13.40 cr
Spent of the estimate74.0%
BuildingWingEstimatedIncurred
ANARs 1.51 crRs 1.12 cr
BNARs 1.51 crRs 1.12 cr
CNARs 1.51 crRs 1.12 cr
DNARs 1.51 crRs 1.12 cr
ENARs 1.51 crRs 1.12 cr
FNARs 1.51 crRs 1.12 cr
GNARs 1.51 crRs 1.12 cr
HNARs 1.51 crRs 1.12 cr
INARs 1.51 crRs 1.12 cr
JNARs 1.51 crRs 1.12 cr
LNARs 1.51 crRs 1.12 cr
MNARs 1.51 crRs 1.12 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKaushal Lehri
EngineerAmee Associates

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA00952/081217 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)31 Mar 2021
Engineer's certificate (Form 2)31 Mar 2021
Engineer's certificate annexure31 Mar 2021
Accountant's certificate (Form 3)31 Mar 2021
Site photograph, A30 Mar 2021
Site photograph, B30 Mar 2021
Site photograph, C30 Mar 2021
Site photograph, D30 Mar 2021
Site photograph, E30 Mar 2021
Site photograph, F30 Mar 2021
Site photograph, G30 Mar 2021
Site photograph, H30 Mar 2021
Site photograph, I30 Mar 2021
Site photograph, J30 Mar 2021
Site photograph, L30 Mar 2021
Site photograph, M30 Mar 2021
RERA registration certificate8 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

35%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Sahjanand Business Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Nikol5,400+ in Ahmedabad

2 kmSahjanand Business ParkOther 296Dot size: filed unitsN

Filed coordinates, straight-line distance. 296 registered projects within 2 km.

Builder: Sahjanand Developers

Sahjanand Developers has 9 registrations on GujRERA, including Sahjanand Business Park and Sahjanand Enclave. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Sahjanand Business Park is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Sahjanand Business Park?

The registered promoter entity is Sahjanand Developers, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Sahjanand Business Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Sahjanand Business Park?

The professionals named in the filing: Architect: Kaushal Lehri; Engineer: Amee Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sahjanand Business Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sahjanand Business Park. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sahjanand Business Park to a free account