ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / VARDHAMAN ENCLAVE

Valid until 31 Mar 2020 Mixed Development project

VARDHAMAN ENCLAVE

By AADINATH DEVELOPERS

RG-GJ-42052 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA01909/EX1/150719 · Last updated on GujRERA portal: 7 Oct 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2020Possession promisedmoved 12 months from the original
24 of 24Construction stages doneacross 4 buildings; every applicable stage filed complete
Jump to the 36 documents Report an error

VARDHAMAN ENCLAVE is a Mixed Development project by AADINATH DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA01909/EX1/150719 on 7 Mar 2018. Possession is promised by 31 Mar 2020. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameVARDHAMAN ENCLAVE
  • TypeMixed Development
  • Location
    • BLOCK NO 273
    • F P NO 22
    • T P NO 25
    • VARDHAMAN ENCLAVE
    • OPP. GOPINATHJI SHOWROOM
    • ATLADARA PADRA ROAD
    • VADODARA
    • Atladara
    • Vadodara
    • 390012
  • Pincode390012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA01909/EX1/150719
  • ReraGenie IDRG-GJ-42052

Builder

  • NameAADINATH DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations6 more →

Key dates

this monthRegisteredMar 2018First promiseMar 2019Revised toMar 2020

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2020
  • Registered on7 Mar 2018
  • Promised completion31 Mar 2020
  • Revised completionRevised to 31 Mar 2020 (originally 31 Mar 2019)
  • Buildings4 building records
  • Documents filed36 files

Current status

88.4%Of the estimated cost spent so far

Figures as on 7 Oct 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER C-----41
TOWER D-----75
TOWER A-----42
TOWER B-----33

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 7 Oct 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 24 construction stages are filed complete across 4 buildings.

TOWER C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 7 Oct 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,006 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 9.75 cr
Cost incurredRs 8.62 cr
Spent of the estimate88.36%
BuildingWingEstimatedIncurred
TOWER ANARs 2.44 crRs 2.15 cr
TOWER BNARs 2.44 crRs 2.15 cr
TOWER CNARs 2.44 crRs 2.15 cr
TOWER DNARs 2.44 crRs 2.15 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHIRAG B PATEL
EngineerVINUBHAI PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA01909/EX1/150719Applied May 2019; approved Jul 2019

Documents filed36

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA01909/EX1/150719 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Oct 2019
Engineer's certificate (Form 2)7 Oct 2019
Engineer's certificate annexure7 Oct 2019
RERA registration certificate7 Mar 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep VARDHAMAN ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Atladara2,900+ in Vadodara

2 kmVARDHAMAN ENCLAVEOther 288Dot size: filed unitsN

Filed coordinates, straight-line distance. 288 registered projects within 2 km.

Builder: AADINATH DEVELOPERS

AADINATH DEVELOPERS has 7 registrations on GujRERA, including VARDHAMAN ENCLAVE and Kalash. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if VARDHAMAN ENCLAVE is delayed beyond 31 Mar 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VARDHAMAN ENCLAVE?

The registered promoter entity is AADINATH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VARDHAMAN ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VARDHAMAN ENCLAVE?

The professionals named in the filing: Architect: CHIRAG B PATEL; Engineer: VINUBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VARDHAMAN ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VARDHAMAN ENCLAVE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VARDHAMAN ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.