ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / VANILLA SKY

Valid until 30 Sep 2025 Residential/Group Housing project

VANILLA SKY

By RAJGREEN INFRALINK LLP

RG-GJ-90888 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA05333/A1R/EX2/080925/300925 · Last updated on GujRERA portal: 14 Dec 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Sep 2025Possession promisedmoved 24 months from the original
27 of 36Construction stages doneacross 4 buildings; furthest along: Internal walls, 95%
10 of 106Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

VANILLA SKY is a Residential/Group Housing project by RAJGREEN INFRALINK LLP in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA05333/A1R/EX2/080925/300925 on 26 Apr 2019. Possession is promised by 30 Sep 2025. The completion date has moved by 24 months from the original filing. 96 of the 106 units on this registration are recorded sold or booked, and 27 of 36 construction stages are filed complete.

At a glance

Project

  • NameVANILLA SKY
  • TypeResidential/Group Housing
  • Location
    • T.P. NO.5 ( VESU -BHIMRAD) VIP ROAD
    • VESU
    • VESU
    • Surat City
    • Surat
    • 395007
  • Pincode395007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA05333/A1R/EX2/080925/300925
  • ReraGenie IDRG-GJ-90888

Builder

  • NameRAJGREEN INFRALINK LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2019First promiseSep 2023Revised toSep 2025

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2025
  • Registered on26 Apr 2019
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 Sep 2023)
  • Buildings4 building records
  • Documents filed44 files

Current status

91%96 of 106 units booked
99.6%Of the estimated cost spent so far

Figures as on 14 Dec 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---26026
B---26026
C---28028
D---26026

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 14 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 95%.

A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
C87%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 14 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes70%
Street lightingYes70%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes70%
Water conservation, rain water harvestingYes100%
Energy managementYes0%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes70%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes50%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,347 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 94.50 cr
Cost incurredRs 94.16 cr
Spent of the estimate99.63%
BuildingWingEstimatedIncurred
ANARs 23.62 crRs 23.62 cr
BNARs 23.62 crRs 23.62 cr
CNARs 23.62 crRs 23.28 cr
DNARs 23.62 crRs 23.62 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMISHKUMAR PATEL
EngineerSANDEEP A PRAJAPATI

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA05333/A1R/EX1/180424/300924Applied Oct 2023; approved Apr 2024
PR/GJ/SURAT/SURAT CITY/SUDA/RAA05333/A1R/EX2/080925/300925Applied Sep 2024; approved Sep 2025

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA05333/A1R/EX2/080925/300925 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)14 Dec 2024
Architect's certificate (Form 1)13 Dec 2024
Engineer's certificate (Form 2)13 Dec 2024
Engineer's certificate annexure13 Dec 2024
Site photograph, A13 Dec 2024
Site photograph, B13 Dec 2024
Site photograph, C13 Dec 2024
Site photograph, D13 Dec 2024
RERA registration certificate26 Apr 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

91%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 24 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep VANILLA SKY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near VESU2,600+ in Surat

2 kmVANILLA SKYOther 222Dot size: filed unitsN

Filed coordinates, straight-line distance. 222 registered projects within 2 km.

Builder: RAJGREEN INFRALINK LLP

RAJGREEN INFRALINK LLP has 2 registrations on GujRERA, including THE BLUEBELL and VANILLA SKY. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if VANILLA SKY is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VANILLA SKY?

The registered promoter entity is RAJGREEN INFRALINK LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VANILLA SKY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VANILLA SKY?

The professionals named in the filing: Architect: AMISHKUMAR PATEL; Engineer: SANDEEP A PRAJAPATI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VANILLA SKY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VANILLA SKY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VANILLA SKY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.