Home / Browse projects / Surat, Gujarat / Construction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY

Valid until 30 Dec 2021 Residential/Group Housing project

Construction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY

By SURAT MUNICIPAL CORPORATION

RG-GJ-65836 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA03348/EX2/100221 · Last updated on GujRERA portal: 28 Dec 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • Separate project account declared
Dec 2021Possession promisedmoved 30 months from the original
40 of 40Construction stages doneacross 5 buildings; every applicable stage filed complete
0 of 660Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

Construction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY is a Residential/Group Housing project by SURAT MUNICIPAL CORPORATION in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA03348/EX2/100221 on 4 Sep 2018. Possession is promised by 30 Dec 2021. The completion date has moved by 30 months from the original filing. 660 of the 660 units on this registration are recorded sold or booked, and 40 of 40 construction stages are filed complete.

At a glance

Project

  • NameConstruction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY
  • TypeResidential/Group Housing
  • Location
    • T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2
    • Behind Rahul Raj Mall
    • Surat
    • Rundh
    • Surat City
    • Surat
    • 395007
  • Pincode395007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA03348/EX2/100221
  • ReraGenie IDRG-GJ-65836

Builder

  • NameSURAT MUNICIPAL CORPORATION
  • Entity typeCOMPETENT AUTHORITY/ GOVERNMENT
  • Other registrations49 more →

Key dates

this monthRegisteredSep 2018First promiseJun 2019Revised toDec 2021

Key facts

Registration and timeline

  • StatusValid until 30 Dec 2021
  • Registered on4 Sep 2018
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 30 Jun 2019)
  • Buildings5 building records
  • Documents filed42 files

Current status

100%660 of 660 units booked
100.0%Of the estimated cost spent so far

Figures as on 28 Dec 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---1300130
B---1300130
C---1300130
D---1260126
E---1440144

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 28 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 40 construction stages are filed complete across 5 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 28 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,470 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 31.99 cr
Cost incurredRs 31.99 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 6.40 crRs 6.40 cr
BNARs 6.40 crRs 6.40 cr
CNARs 6.40 crRs 6.40 cr
DNARs 6.40 crRs 6.40 cr
ENARs 6.40 crRs 6.40 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay Umarigar
EngineerJayesh Dalal

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA03348/EX1/030919Applied Aug 2019; approved Sep 2019
PR/GJ/SURAT/SURAT CITY/SUDA/RAA03348/EX2/100221Applied Dec 2020; approved Feb 2021

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA03348/EX2/100221 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)28 Dec 2021
Engineer's certificate (Form 2)28 Dec 2021
Engineer's certificate annexure28 Dec 2021
Accountant's certificate (Form 3)28 Dec 2021
Site photograph, A28 Dec 2021
Site photograph, B28 Dec 2021
Site photograph, C28 Dec 2021
Site photograph, D28 Dec 2021
Site photograph, E28 Dec 2021
RERA registration certificate4 Sep 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

100%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 30 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep Construction Of 660 DUs Of EWS-II Type at T. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rundh2,600+ in Surat

2 kmConstruction Of 660 DUs Other 140Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: SURAT MUNICIPAL CORPORATION

SURAT MUNICIPAL CORPORATION has 50 registrations on GujRERA, including Construction Of 1088 DUs Of EWS-II Type at T.P.53(Magob-Dumbhal),F.P.No.82 under PMAY and Construction Of 160 DUs Of EWS-I Type at T.P.41(Dindoli),F.P.No.29 under PMAY. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if Construction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Construction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY?

The registered promoter entity is SURAT MUNICIPAL CORPORATION, a competent authority/ government as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Construction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Construction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY?

The professionals named in the filing: Architect: Sanjay Umarigar; Engineer: Jayesh Dalal. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Construction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Construction Of 660 DUs Of EWS-II Type at T.P.28(RUNDH-VESU) F.P.32/P-SUB PLOT NO-2 under PMAY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Construction Of 660 DUs Of EWS-II Type at T. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.