ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / TP 16 FP 144 LIG

Valid until 30 Jun 2019 Residential/Group Housing project

TP 16 FP 144 LIG

By VADODARA MUNICIPAL CORPORATION

RG-GJ-73612 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA04831/120219 · Last updated on GujRERA portal: 5 Feb 2021

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jun 2019Possession promisedno revision filed
8 of 8Construction stages doneevery applicable stage filed complete
0 of 32Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

TP 16 FP 144 LIG is a Residential/Group Housing project by VADODARA MUNICIPAL CORPORATION in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA04831/120219 on 12 Feb 2019. Possession is promised by 30 Jun 2019. 32 of the 32 units on this registration are recorded sold or booked, and 8 of 8 construction stages are filed complete.

At a glance

Project

  • NameTP 16 FP 144 LIG
  • TypeResidential/Group Housing
  • Location
    • Vadodara
    • Vadodara
    • Saiyad Vasna
    • Vadodara
    • 390007
  • Pincode390007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA04831/120219
  • ReraGenie IDRG-GJ-73612

Builder

  • NameVADODARA MUNICIPAL CORPORATION
  • Entity typeCOMPETENT AUTHORITY/ GOVERNMENT
  • Other registrations22 more →

Key dates

this monthRegisteredFeb 2019PromisedJun 2019

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2019
  • Registered on12 Feb 2019
  • Promised completion30 Jun 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed39 files

Current status

100%32 of 32 units booked
100.0%Of the estimated cost spent so far

Figures as on 5 Feb 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---32032

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 5 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 8 construction stages are filed complete.

Tower A: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 5 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyYes100%
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,380 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 2.54 cr
Cost incurredRs 2.54 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Tower ANARs 2.54 crRs 2.54 cr

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA04831/120219 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)5 Feb 2021
Architect's certificate (Form 1)3 Feb 2021
Engineer's certificate (Form 2)3 Feb 2021
Engineer's certificate annexure3 Feb 2021
Site photograph, Tower A3 Feb 2021
RERA registration certificate12 Feb 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

100%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep TP 16 FP 144 LIG on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Saiyad Vasna2,900+ in Vadodara

2 kmTP 16 FP 144 LIGOther 301Dot size: filed unitsN

Filed coordinates, straight-line distance. 301 registered projects within 2 km.

Builder: VADODARA MUNICIPAL CORPORATION

VADODARA MUNICIPAL CORPORATION has 23 registrations on GujRERA, including MIG SCHEME TP 1 FP 68 and MIG SCHEME TP 15 FP 103. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if TP 16 FP 144 LIG is delayed beyond 30 Jun 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of TP 16 FP 144 LIG?

The registered promoter entity is VADODARA MUNICIPAL CORPORATION, a competent authority/ government as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in TP 16 FP 144 LIG?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in TP 16 FP 144 LIG?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TP 16 FP 144 LIG. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TP 16 FP 144 LIG to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.