TIRUPATI AAKRUTI INDUSTRIAL ESTATE

By TIRUPATI AKRUTI DEVELOPERS

RG-GJ-72053 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA11794/A1C/150724/300926 · Last updated on GujRERA portal: 23 Mar 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jan 2027Possession promisedno revision filed
70 of 81Construction stages doneacross 9 buildings; furthest along: Stilt Floor, 84%
119 of 253Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

TIRUPATI AAKRUTI INDUSTRIAL ESTATE is a Commercial project by TIRUPATI AKRUTI DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA11794/A1C/150724/300926 on 22 May 2023. Possession is promised by 30 Jan 2027. 134 of the 253 units on this registration are recorded sold or booked, and 70 of 81 construction stages are filed complete.

At a glance

Project

  • NameTIRUPATI AAKRUTI INDUSTRIAL ESTATE
  • TypeCommercial
  • Location
    • TIRUPATI AAKRUTI INDUSTRIAL ESTATE
    • OPP. ABHISHREE ESTATE
    • B/H VEPARI MAHAMANDAL
    • NEAR S P RING ROAD
    • ODHAV
    • AHMEDABAD
    • ODHAV
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA11794/A1C/150724/300926
  • ReraGenie IDRG-GJ-72053

Builder

  • NameTIRUPATI AKRUTI DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2023PromisedJan 2027

Key facts

Registration and timeline

  • StatusValid until 30 Jan 2027
  • Registered on22 May 2023
  • Promised completion30 Jan 2027
  • Revised completionNone
  • Buildings9 building records
  • Documents filed40 files

Current status

53%134 of 253 units booked
89.3%Of the estimated cost spent so far

Figures as on 23 Mar 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK B---0026
BLOCK C---0022
BLOCK D---0022
BLOCK E---0024
BLOCK F---0024
BLOCK G---0024
BLOCK H---0021
BLOCK I---02525
BLOCK A---05465

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building9

As on 23 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

70 of 81 construction stages are filed complete across 9 buildings. The stage furthest along is Stilt Floor, at 84%.

BLOCK B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK C97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK D97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK E97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK F97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK G97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK H97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK I89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor84%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats84%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing64%
BLOCK A97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 23 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes95%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes85%
Landscaping and tree plantingYes95%
Street lightingYes90%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes95%
Plinth protectionYes90%
Water tankYes90%
Other requirementsYes85%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,328 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 23.03 cr
Cost incurredRs 20.56 cr
Spent of the estimate89.27%
BuildingWingEstimatedIncurred
BLOCK ANARs 10.48 crRs 9.18 cr
BLOCK BNARs 1.57 crRs 1.57 cr
BLOCK CNARs 1.57 crRs 1.40 cr
BLOCK DNARs 1.57 crRs 1.40 cr
BLOCK ENARs 1.57 crRs 1.40 cr
BLOCK FNARs 1.57 crRs 1.40 cr
BLOCK GNARs 1.57 crRs 1.40 cr
BLOCK HNARs 1.57 crRs 1.40 cr
BLOCK INARs 1.57 crRs 1.40 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHAILENDRASINH PARBATSINH CHAUHAN
EngineerKRUNAL KIRITKUMAR MISTRY

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/CAA11794/A1C/150724/300926 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)23 Mar 2024
Engineer's certificate annexure23 Mar 2024
RERA registration certificate22 May 2023
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

53%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep TIRUPATI AAKRUTI INDUSTRIAL ESTATE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near ODHAV5,400+ in Ahmedabad

2 kmTIRUPATI AAKRUTI INDUSTROther 269Dot size: filed unitsN

Filed coordinates, straight-line distance. 269 registered projects within 2 km.

Builder: TIRUPATI AKRUTI DEVELOPERS

TIRUPATI AKRUTI DEVELOPERS has 1 registration on GujRERA, including TIRUPATI AAKRUTI INDUSTRIAL ESTATE. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if TIRUPATI AAKRUTI INDUSTRIAL ESTATE is delayed beyond 30 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of TIRUPATI AAKRUTI INDUSTRIAL ESTATE?

The registered promoter entity is TIRUPATI AKRUTI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in TIRUPATI AAKRUTI INDUSTRIAL ESTATE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TIRUPATI AAKRUTI INDUSTRIAL ESTATE?

The professionals named in the filing: Architect: SHAILENDRASINH PARBATSINH CHAUHAN; Engineer: KRUNAL KIRITKUMAR MISTRY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TIRUPATI AAKRUTI INDUSTRIAL ESTATE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TIRUPATI AAKRUTI INDUSTRIAL ESTATE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TIRUPATI AAKRUTI INDUSTRIAL ESTATE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.