Home / Browse projects / Surat, Gujarat / THE POLARIS AVENUE

Valid until 30 Sep 2026 Residential/Group Housing project

THE POLARIS AVENUE

By BAVCHANDBHAI VASHRAM BHAGAT PROPRIETOR OF THE POLARIS AVENUE

RG-GJ-64044 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA05782/EX1/180326/300926 · Last updated on GujRERA portal: 23 Feb 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Sep 2026Possession promisedmoved 12 months from the original
27 of 54Construction stages doneacross 6 buildings; furthest along: Internal walls, 83%
26 of 57Units unsoldnot recorded sold or booked
Jump to the 47 documents Report an error

THE POLARIS AVENUE is a Residential/Group Housing project by BAVCHANDBHAI VASHRAM BHAGAT PROPRIETOR OF THE POLARIS AVENUE in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA05782/EX1/180326/300926 on 24 Jul 2019. Possession is promised by 30 Sep 2026. The completion date has moved by 12 months from the original filing. 31 of the 57 units on this registration are recorded sold or booked, and 27 of 54 construction stages are filed complete.

At a glance

Project

  • NameTHE POLARIS AVENUE
  • TypeResidential/Group Housing
  • Location
    • T.P.6
    • F.P. 59/B
    • SURVEY NO. 247/1
    • VESU CANAL ROAD
    • NEAR AANGAN RESIDENCY
    • Vesu
    • Surat City
    • Surat
    • 394518
  • Pincode394518
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA05782/EX1/180326/300926
  • ReraGenie IDRG-GJ-64044

Builder

  • NameBAVCHANDBHAI VASHRAM BHAGAT PROPRIETOR OF THE POLARIS AVENUE
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredJul 2019First promiseSep 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2026
  • Registered on24 Jul 2019
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Sep 2025)
  • Buildings6 building records
  • Documents filed47 files

Current status

54%31 of 57 units booked
30.8%Of the estimated cost spent so far

Figures as on 23 Feb 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---10010
B---12012
C---10010
D---505
E---10010
F---10010

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 23 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Internal walls, at 83%.

A64%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B65%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats83%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E67%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
F64%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 23 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes65%
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,735 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 39.00 cr
Cost incurredRs 12.00 cr
Spent of the estimate30.77%
BuildingWingEstimatedIncurred
ANARs 6.50 crRs 2.00 cr
BNARs 6.50 crRs 2.00 cr
CNARs 6.50 crRs 2.00 cr
DNARs 6.50 crRs 2.00 cr
ENARs 6.50 crRs 2.00 cr
FNARs 6.50 crRs 2.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay Josshi
EngineerHiren G. Desai

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA05782/EX1/180326/300926Applied Nov 2025; approved Mar 2026

Documents filed47

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA05782/EX1/180326/300926 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)23 Feb 2026
Architect's certificate (Form 1)17 Feb 2026
Engineer's certificate (Form 2)17 Feb 2026
Engineer's certificate annexure17 Feb 2026
Site photograph, A17 Feb 2026
Site photograph, B17 Feb 2026
Site photograph, C17 Feb 2026
Site photograph, D17 Feb 2026
Site photograph, E17 Feb 2026
Site photograph, F17 Feb 2026
RERA registration certificate24 Jul 2019
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

54%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep THE POLARIS AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vesu2,600+ in Surat

2 kmTHE POLARIS AVENUEOther 163Dot size: filed unitsN

Filed coordinates, straight-line distance. 163 registered projects within 2 km.

Builder: BAVCHANDBHAI VASHRAM BHAGAT PROPRIETOR OF THE POLARIS AVENUE

BAVCHANDBHAI VASHRAM BHAGAT PROPRIETOR OF THE POLARIS AVENUE has 1 registration on GujRERA, including THE POLARIS AVENUE. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if THE POLARIS AVENUE is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE POLARIS AVENUE?

The registered promoter entity is BAVCHANDBHAI VASHRAM BHAGAT PROPRIETOR OF THE POLARIS AVENUE, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE POLARIS AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE POLARIS AVENUE?

The professionals named in the filing: Architect: Sanjay Josshi; Engineer: Hiren G. Desai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE POLARIS AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE POLARIS AVENUE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE POLARIS AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.