Home / Browse projects / Surat, Gujarat / HAPPY ELEGANCE

Valid until 28 Jan 2022 Residential/Group Housing project

HAPPY ELEGANCE

By HAPPY HOME CORPORATION

RG-GJ-62151 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA00879/EX1/160121 · Last updated on GujRERA portal: 27 Jan 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Jan 2022Possession promisedmoved 12 months from the original
72 of 72Construction stages doneacross 9 buildings; every applicable stage filed complete
195 of 468Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

HAPPY ELEGANCE is a Residential/Group Housing project by HAPPY HOME CORPORATION in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA00879/EX1/160121 on 4 Dec 2017. Possession is promised by 28 Jan 2022. The completion date has moved by 12 months from the original filing. 273 of the 468 units on this registration are recorded sold or booked, and 72 of 72 construction stages are filed complete.

At a glance

Project

  • NameHAPPY ELEGANCE
  • TypeResidential/Group Housing
  • Location
    • TP-75 (Vesu)
    • FP-84
    • OPP. STAR GALAXY
    • NR. GREENLAND BUNGALOW
    • VVIP-CANAL ROAD
    • VESU
    • SURAT
    • Vesu
    • Surat City
    • Surat
    • 394518
  • Pincode394518
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA00879/EX1/160121
  • ReraGenie IDRG-GJ-62151

Builder

  • NameHAPPY HOME CORPORATION
  • Entity typePARTNERSHIP FIRM
  • Other registrations8 more →

Key dates

this monthRegisteredDec 2017First promiseJan 2021Revised toJan 2022

Key facts

Registration and timeline

  • StatusValid until 28 Jan 2022
  • Registered on4 Dec 2017
  • Promised completion28 Jan 2022
  • Revised completionRevised to 28 Jan 2022 (originally 28 Jan 2021)
  • Buildings9 building records
  • Documents filed45 files

Current status

58%273 of 468 units booked
62.9%Of the estimated cost spent so far

Figures as on 27 Jan 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B1---52052
B2---52052
B3---52052
A1---52052
A2---52052
A3---52052
A4---52052
A5---52052
A6---52052

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building9

As on 27 Jan 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

72 of 72 construction stages are filed complete across 9 buildings.

B1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A5100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A6100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 27 Jan 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,180 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 78.75 cr
Cost incurredRs 49.54 cr
Spent of the estimate62.9%
BuildingWingEstimatedIncurred
A1NARs 8.75 crRs 5.50 cr
A2NARs 8.75 crRs 5.50 cr
A3NARs 8.75 crRs 5.50 cr
A4NARs 8.75 crRs 5.50 cr
A5NARs 8.75 crRs 5.50 cr
A6NARs 8.75 crRs 5.50 cr
B1NARs 8.75 crRs 5.50 cr
B2NARs 8.75 crRs 5.50 cr
B3NARs 8.75 crRs 5.50 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA00879/EX1/160121Applied Dec 2020; approved Jan 2021

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA00879/EX1/160121 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)27 Jan 2022
Engineer's certificate (Form 2)27 Jan 2022
Engineer's certificate annexure27 Jan 2022
Accountant's certificate (Form 3)27 Jan 2022
Site photograph, B127 Jan 2022
Site photograph, B227 Jan 2022
Site photograph, B327 Jan 2022
Site photograph, A127 Jan 2022
Site photograph, A227 Jan 2022
Site photograph, A327 Jan 2022
Site photograph, A427 Jan 2022
Site photograph, A527 Jan 2022
Site photograph, A627 Jan 2022
RERA registration certificate4 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

58%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep HAPPY ELEGANCE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vesu2,600+ in Surat

2 kmHAPPY ELEGANCEOther 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 133 registered projects within 2 km.

Builder: HAPPY HOME CORPORATION

HAPPY HOME CORPORATION has 9 registrations on GujRERA, including HAPPY GOLDMINES SHOPPERS and HAPPY ELEGANCE. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if HAPPY ELEGANCE is delayed beyond 28 Jan 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of HAPPY ELEGANCE?

The registered promoter entity is HAPPY HOME CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in HAPPY ELEGANCE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in HAPPY ELEGANCE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HAPPY ELEGANCE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HAPPY ELEGANCE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.