Home / Browse projects / Ahmedabad, Gujarat / THE GOLD SKY VILLA

Valid until 30 Apr 2027 Residential/Group Housing project

THE GOLD SKY VILLA

By SHAH BIRJUKUMAR AJITBHAI

RG-GJ-17657 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10292/A1R/050423 · Last updated on GujRERA portal: 14 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
10 of 27Construction stages doneacross 3 buildings; furthest along: Staircases, 93%
86 of 109Units unsoldnot recorded sold or booked
Jump to the 35 documents Report an error

THE GOLD SKY VILLA is a Residential/Group Housing project by SHAH BIRJUKUMAR AJITBHAI in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10292/A1R/050423 on 8 Jun 2022. Possession is promised by 30 Apr 2027. 23 of the 109 units on this registration are recorded sold or booked, and 10 of 27 construction stages are filed complete.

At a glance

Project

  • NameTHE GOLD SKY VILLA
  • TypeResidential/Group Housing
  • Location
    • THE GOLD SKY VILLE
    • SHILAJ CIRCLE
    • TOWARDS BHADAJ CIRCLE
    • HEBATPUR
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10292/A1R/050423
  • ReraGenie IDRG-GJ-17657

Builder

  • NameSHAH BIRJUKUMAR AJITBHAI
  • Entity typeCOMPANY

Key dates

this monthRegisteredJun 2022PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on8 Jun 2022
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed35 files

Current status

21%23 of 109 units booked
52.0%Of the estimated cost spent so far

Figures as on 14 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK-A---13013
BLOCK-C---48048
BLOCK-B---48048

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 14 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 93%.

BLOCK-A60%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor31%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats43%
Sanitary fittings within the flats31%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing5%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing31%
BLOCK-C53%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor8%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats57%
Sanitary fittings within the flats8%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks93%
External plumbing and external plaster, elevation, completion of terraces with waterproofing5%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing8%
BLOCK-B49%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats43%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks93%
External plumbing and external plaster, elevation, completion of terraces with waterproofing5%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities23

As on 14 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,993 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 83.50 cr
Cost incurredRs 43.42 cr
Spent of the estimate52.0%
BuildingWingEstimatedIncurred
BLOCK-BNARs 34.11 crRs 17.74 cr
BLOCK-CNARs 34.11 crRs 17.74 cr
BLOCK-ANARs 15.28 crRs 7.94 cr

Documents filed35

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA10292/A1R/050423 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)14 Oct 2024
Engineer's certificate annexure14 Oct 2024
RERA registration certificate8 Jun 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Approved building or plotting plan-
Proforma sale deed-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

21%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep THE GOLD SKY VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmTHE GOLD SKY VILLAOther 126Dot size: filed unitsN

Filed coordinates, straight-line distance. 126 registered projects within 2 km.

Builder: SHAH BIRJUKUMAR AJITBHAI

SHAH BIRJUKUMAR AJITBHAI has 1 registration on GujRERA, including THE GOLD SKY VILLA. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if THE GOLD SKY VILLA is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE GOLD SKY VILLA?

The registered promoter entity is SHAH BIRJUKUMAR AJITBHAI, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE GOLD SKY VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in THE GOLD SKY VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE GOLD SKY VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE GOLD SKY VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.