Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- Recorded completed on RERA Rajasthan
Saved.
THE CROWN is a Group Housing project by GORBANDH FORT AND PALACE LLP in Jaipur, Rajasthan, registered with RERA Rajasthan as RAJ/P/2017/001 on 3 Jul 2017. The registration is recorded completed; possession was promised by 16 Jan 2022. The completion date has moved by 24 months from the original filing.
At a glance
Project
- TypeGroup Housing
- Location
- Khasra No./ Plot No.A-6
- Village- Jaipur
- AIRPORT ENCLAVE SCHEME
- TONK ROAD
- DURGAPURA
- JAIPUR
- Jaipur - 302018 (Rajasthan)
- Jaipur
- PincodeNot stated
- RERA no.RAJ/P/2017/001
- ReraGenie IDRG-RJ-83273
Builder
- NameGORBANDH FORT AND PALACE LLP
- Entity typePartnership Firm
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed or revoked
Registration and timeline
- StatusCompleted
- Registered on3 Jul 2017
- Promised completion16 Jan 2022
- Revised completionRevised to 16 Jan 2022 (originally 16 Jan 2020)
- Documents filed10 on the register's page, not listed here
Key dates
The full filing
Everything below is from the project's own RERA Rajasthan filing, free to read.
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
No reason recorded in the filing
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Jaipur
Computed across the 2,400+ Jaipur projects on ReraGenie, from their own filings.
Keep THE CROWN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects in Jaipur2,400+ in Jaipur
"GOVERDHAN VATIKA"
Bordiya Balaji Builders And Developers Pri
"LANDMARK"
BADRINATH INFRAPROJECTS PVT LTD
"ROYAL AANGAN BLOCK-A EXT."
GOKUL KRIPA COLONIZERS AND DEVELOPERS PVT.
"THE ELEGANCE"
NEW PATH DEVELOPERS LLP
''PLATINUM GREENS''
RIYASAT INFRA DEVELOPERS PRIVATE LIMITED
14 WOODLAND PARK
WOODLAND PARK BUILDCON LLP
See every Jaipur project, with the district possession charts
Builder: GORBANDH FORT AND PALACE LLP
GORBANDH FORT AND PALACE LLP has 2 registrations on RERA Rajasthan, including THE CROWN and SUVAAS AGAM. Read the full track record. See more projects on the Jaipur district page.
Frequently asked questions
What are my rights if THE CROWN is delayed beyond 16 Jan 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Rajasthan.
How do I verify and contact the developer of THE CROWN?
The registered promoter entity is GORBANDH FORT AND PALACE LLP, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Rajasthan listing and in its filed documents.
Is my payment protected in THE CROWN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in THE CROWN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Rajasthan, and we read every report.
Report an error Share feedback