Home / Browse projects / Surat, Gujarat / THE CAPITAL

Valid until 30 Dec 2026 Residential/Group Housing project

THE CAPITAL

By SHREE NILKANTH INFRA

RG-GJ-43720 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/RAA08043/A1R/EX1/140726/301226 · Last updated on GujRERA portal: 30 Apr 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 12 months from the original
41 of 63Construction stages doneacross 7 buildings; furthest along: Plinth, 65%
203 of 252Units unsoldnot recorded sold or booked
Jump to the 53 documents Report an error

THE CAPITAL is a Residential/Group Housing project by SHREE NILKANTH INFRA in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/RAA08043/A1R/EX1/140726/301226 on 10 Feb 2021. Possession is promised by 30 Dec 2026. The completion date has moved by 12 months from the original filing. 49 of the 252 units on this registration are recorded sold or booked, and 41 of 63 construction stages are filed complete.

At a glance

Project

  • NameTHE CAPITAL
  • TypeResidential/Group Housing
  • Location
    • T.P NO.-50
    • F.P. NO-50/2
    • 50/3 VED- KARATGAM
    • RAM KATHA ROAD
    • VED
    • VED
    • Surat City
    • Surat
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/RAA08043/A1R/EX1/140726/301226
  • ReraGenie IDRG-GJ-43720

Builder

  • NameSHREE NILKANTH INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2021First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 30 Dec 2026
  • Registered on10 Feb 2021
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 31 Dec 2025)
  • Buildings7 building records
  • Documents filed53 files

Current status

19%49 of 252 units booked
53.2%Of the estimated cost spent so far

Figures as on 30 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D---28028
E---56056
F---56056
G---28028
A---28028
B---28028
C---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

41 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is Plinth, at 65%.

D33%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F18%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth65%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
G18%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth65%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes50%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes15%
Storm water drainsYes30%
Landscaping and tree plantingYes50%
Street lightingYes40%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes15%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes55%
Fire fightingYes50%
Drinking water facilitiesYes40%
Emergency evacuationYes55%
Use of renewable energyYes20%
SecurityYes50%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,774 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 110.70 cr
Cost incurredRs 58.90 cr
Spent of the estimate53.21%
BuildingWingEstimatedIncurred
ENARs 21.00 crRs 17.00 cr
FNARs 21.00 crRs 50.00 lakh
ANARs 14.10 crRs 13.50 cr
GNARs 14.10 crRs 50.00 lakh
BNARs 13.50 crRs 13.00 cr
CNARs 13.50 crRs 12.00 cr
DNARs 13.50 crRs 2.40 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/SURAT CITY/SUDA/RAA08043/A1R/EX1/140726/301226Applied Nov 2025; approved Jul 2026

Documents filed53

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/RAA08043/A1R/EX1/140726/301226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)30 Apr 2026
Engineer's certificate (Form 2)30 Apr 2026
Engineer's certificate annexure30 Apr 2026
Accountant's certificate (Form 3)30 Apr 2026
Site photograph, D30 Apr 2026
Site photograph, E30 Apr 2026
Site photograph, F30 Apr 2026
Site photograph, G30 Apr 2026
Site photograph, A30 Apr 2026
Site photograph, B30 Apr 2026
Site photograph, C30 Apr 2026
RERA registration certificate10 Feb 2021
Extension certificate-
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Proforma sale deed-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

19%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep THE CAPITAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near VED2,600+ in Surat

2 kmTHE CAPITALOther 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 103 registered projects within 2 km.

Builder: SHREE NILKANTH INFRA

SHREE NILKANTH INFRA has 1 registration on GujRERA, including THE CAPITAL. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if THE CAPITAL is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE CAPITAL?

The registered promoter entity is SHREE NILKANTH INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE CAPITAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in THE CAPITAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE CAPITAL. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE CAPITAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.