Home / Browse projects / Ahmedabad, Gujarat / TAJ RESIDENCY

Valid until 30 Sep 2019 Residential/Group Housing project

TAJ RESIDENCY

By BALAJI BUILDCON (PROPRIETOR:- PRAVINBHAI MANSUKHBHAI SUKHADIA)

RG-GJ-10032 · RERA PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00276/EX2/230719 · Last updated on GujRERA portal: 26 Sep 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 9 months
  • 2 extensions taken

Clear

  • Separate project account declared
Sep 2019Possession promisedmoved 9 months from the original
29 of 31Construction stages doneacross 4 buildings; furthest along: Stilt Floor, 0%
25 of 70Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

TAJ RESIDENCY is a Residential/Group Housing project by BALAJI BUILDCON (PROPRIETOR:- PRAVINBHAI MANSUKHBHAI SUKHADIA) in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00276/EX2/230719 on 27 Sep 2017. Possession is promised by 30 Sep 2019. The completion date has moved by 9 months from the original filing. 45 of the 70 units on this registration are recorded sold or booked, and 29 of 31 construction stages are filed complete.

At a glance

Project

  • NameTAJ RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • NR GANGOTRI CIRCLE
    • NIKOL
    • Nikol
    • Ahmedabad City
    • Ahmedabad
    • 380049
  • Pincode380049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00276/EX2/230719
  • ReraGenie IDRG-GJ-10032

Builder

  • NameBALAJI BUILDCON (PROPRIETOR:- PRAVINBHAI MANSUKHBHAI SUKHADIA)
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredSep 2017First promiseDec 2018Revised toSep 2019

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2019
  • Registered on27 Sep 2017
  • Promised completion30 Sep 2019
  • Revised completionRevised to 30 Sep 2019 (originally 31 Dec 2018)
  • Buildings4 building records
  • Documents filed41 files

Current status

64%45 of 70 units booked
100.0%Of the estimated cost spent so far

Figures as on 26 Sep 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A+B---28028
BLOCK C---14014
BLOCK D---14014
BLOCK E---14014

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 26 Sep 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 31 construction stages are filed complete across 4 buildings. The stage furthest along is Stilt Floor, at 0%.

BLOCK A+B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK D88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK E88%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 26 Sep 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,885 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.75 cr
Cost incurredRs 12.75 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
BLOCK A+BNARs 3.19 crRs 3.19 cr
BLOCK CNARs 3.19 crRs 3.19 cr
BLOCK DNARs 3.19 crRs 3.19 cr
BLOCK ENARs 3.19 crRs 3.19 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKETAN K PATEL
EngineerVALAY P SHAH

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00276/EX1/040219Applied Dec 2018; approved Feb 2019
PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00276/EX2/230719Applied Jul 2019; approved Jul 2019

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/RAA00276/EX2/230719 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)26 Sep 2019
Architect's certificate (Form 1)25 Sep 2019
Engineer's certificate (Form 2)25 Sep 2019
Engineer's certificate annexure25 Sep 2019
Site photograph, BLOCK A+B25 Sep 2019
Site photograph, BLOCK C25 Sep 2019
Site photograph, BLOCK D25 Sep 2019
Site photograph, BLOCK E25 Sep 2019
RERA registration certificate27 Sep 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

64%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 9 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep TAJ RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Nikol5,400+ in Ahmedabad

2 kmTAJ RESIDENCYOther 327Dot size: filed unitsN

Filed coordinates, straight-line distance. 327 registered projects within 2 km.

Builder: BALAJI BUILDCON (PROPRIETOR:- PRAVINBHAI MANSUKHBHAI SUKHADIA)

BALAJI BUILDCON (PROPRIETOR:- PRAVINBHAI MANSUKHBHAI SUKHADIA) has 1 registration on GujRERA, including TAJ RESIDENCY. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if TAJ RESIDENCY is delayed beyond 30 Sep 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of TAJ RESIDENCY?

The registered promoter entity is BALAJI BUILDCON (PROPRIETOR:- PRAVINBHAI MANSUKHBHAI SUKHADIA), an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in TAJ RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TAJ RESIDENCY?

The professionals named in the filing: Architect: KETAN K PATEL; Engineer: VALAY P SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TAJ RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TAJ RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TAJ RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.