Valid until 31 Aug 2026 Mixed Development project

THE SAHAJANAND GREEN

By SWAMINARAYAN CORPORATION

RG-GJ-73823 · RERA PR/GJ//AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA05718/A2M/EX1/281026/301125 · Last updated on GujRERA portal: 7 Oct 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Aug 2026Possession promisedmoved 9 months from the original
27 of 63Construction stages doneacross 7 buildings; furthest along: Staircases, 95%
284 of 376Units unsoldnot recorded sold or booked
Jump to the 49 documents Report an error

THE SAHAJANAND GREEN is a Mixed Development project by SWAMINARAYAN CORPORATION in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ//AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA05718/A2M/EX1/281026/301125 on 15 Jul 2019. Possession is promised by 31 Aug 2026. The completion date has moved by 9 months from the original filing. 92 of the 376 units on this registration are recorded sold or booked, and 27 of 63 construction stages are filed complete.

At a glance

Project

  • NameTHE SAHAJANAND GREEN
  • TypeMixed Development
  • Location
    • NR. GANGOTRI CIRCLE
    • OPP. PRATISTHA BUNGALOWS
    • M.G. ROAD
    • NIKOL
    • AHMEDABAD
    • NIKOL
    • Ahmedabad City
    • Ahmedabad
    • 380049
  • Pincode380049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ//AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA05718/A2M/EX1/281026/301125
  • ReraGenie IDRG-GJ-73823

Builder

  • NameSWAMINARAYAN CORPORATION
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJul 2019First promiseNov 2025Revised toAug 2026

Key facts

Registration and timeline

  • StatusValid until 31 Aug 2026
  • Registered on15 Jul 2019
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 30 Nov 2025)
  • Buildings7 building records
  • Documents filed49 files

Current status

24%92 of 376 units booked
86.9%Of the estimated cost spent so far

Figures as on 7 Oct 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---52052
B---52052
C---52052
D---52052
E---52052
F---52052
G---06464

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 7 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 63 construction stages are filed complete across 7 buildings. The stage furthest along is Staircases, at 95%.

A78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats25%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing35%
B91%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats65%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
C81%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats40%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing45%
D82%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats40%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing45%
E84%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats45%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing55%
F81%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats35%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing45%
G83%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats65%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%

Progress on shared amenities19

As on 7 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes45%
Sewerage (chamber, lines, septic tank, STP)Yes40%
Storm water drainsYes40%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes40%
Solid waste management and disposalYes35%
Water conservation, rain water harvestingYes30%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,744 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 55.50 cr
Cost incurredRs 48.25 cr
Spent of the estimate86.94%
BuildingWingEstimatedIncurred
ANARs 18.18 crRs 12.75 cr
BNARs 8.70 crRs 8.65 cr
FNARs 7.60 crRs 7.00 cr
ENARs 5.90 crRs 5.60 cr
DNARs 5.83 crRs 5.40 cr
CNARs 4.98 crRs 4.60 cr
GNARs 4.31 crRs 4.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSiddharth Vitthalbhai Patel
EngineerKETAN KANUBHAI PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA05718/A1M/EX1/200126/310826Applied Nov 2025; approved Jan 2026

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ//AHMEDABAD CITY/Ahmedabad Municipal Corporation/MAA05718/A2M/EX1/281026/301125 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)7 Oct 2026
Architect's certificate (Form 1)28 Aug 2025
Engineer's certificate (Form 2)28 Aug 2025
Engineer's certificate annexure28 Aug 2025
Site photograph, A28 Aug 2025
Site photograph, B28 Aug 2025
Site photograph, C28 Aug 2025
Site photograph, D28 Aug 2025
Site photograph, E28 Aug 2025
Site photograph, F28 Aug 2025
Site photograph, G28 Aug 2025
RERA registration certificate15 Jul 2019
Extension certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

24%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 9 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep THE SAHAJANAND GREEN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near NIKOL5,400+ in Ahmedabad

2 kmTHE SAHAJANAND GREENOther 355Dot size: filed unitsN

Filed coordinates, straight-line distance. 355 registered projects within 2 km.

Builder: SWAMINARAYAN CORPORATION

SWAMINARAYAN CORPORATION has 1 registration on GujRERA, including THE SAHAJANAND GREEN. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if THE SAHAJANAND GREEN is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE SAHAJANAND GREEN?

The registered promoter entity is SWAMINARAYAN CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE SAHAJANAND GREEN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE SAHAJANAND GREEN?

The professionals named in the filing: Architect: Siddharth Vitthalbhai Patel; Engineer: KETAN KANUBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE SAHAJANAND GREEN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE SAHAJANAND GREEN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE SAHAJANAND GREEN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.