Swayam West

By SWAYAM ENTERPRISE

RG-GJ-88889 · RERA PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA13186/EX1/290526/310327 · Last updated on GujRERA portal: 6 May 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Mar 2027Possession promisedmoved 12 months from the original
18 of 18Construction stages doneacross 2 buildings; every applicable stage filed complete
1 of 56Units unsoldnot recorded sold or booked
Jump to the 31 documents Report an error

Swayam West is a Residential/Group Housing project by SWAYAM ENTERPRISE in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA13186/EX1/290526/310327 on 27 Mar 2024. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 55 of the 56 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameSwayam West
  • TypeResidential/Group Housing
  • Location
    • Patidar Chowk
    • Opp. Nand Empire
    • Near Icon Trade
    • Rajkot
    • Raiya
    • Rajkot
    • 360005
  • Pincode360005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA13186/EX1/290526/310327
  • ReraGenie IDRG-GJ-88889

Builder

  • NameSWAYAM ENTERPRISE
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredMar 2024First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2027
  • Registered on27 Mar 2024
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings2 building records
  • Documents filed31 files

Current status

98%55 of 56 units booked
100.0%Of the estimated cost spent so far

Figures as on 6 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---28028
Tower B---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete across 2 buildings.

Tower A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,198 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 14.90 cr
Cost incurredRs 14.90 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Tower ANARs 7.45 crRs 7.45 cr
Tower BNARs 7.45 crRs 7.45 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHUTOSH KARSANBHAI PARSANA
EngineerMANISH VINAYKANT DOSHI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA13186/EX1/290526/310327Applied Apr 2026; approved May 2026

Documents filed31

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA13186/EX1/290526/310327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 May 2026
Architect's certificate (Form 1)8 Apr 2026
Engineer's certificate (Form 2)8 Apr 2026
Engineer's certificate annexure8 Apr 2026
Site photograph, Tower A8 Apr 2026
Site photograph, Tower B8 Apr 2026
RERA registration certificate27 Mar 2024
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

98%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one moved by 12 months

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep Swayam West on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Raiya1,800+ in Rajkot

2 kmSwayam WestOther 239Dot size: filed unitsN

Filed coordinates, straight-line distance. 239 registered projects within 2 km.

Builder: SWAYAM ENTERPRISE

SWAYAM ENTERPRISE has 3 registrations on GujRERA, including Swayam West and SWAYAM GEM. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if Swayam West is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Swayam West?

The registered promoter entity is SWAYAM ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Swayam West?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Swayam West?

The professionals named in the filing: Architect: ASHUTOSH KARSANBHAI PARSANA; Engineer: MANISH VINAYKANT DOSHI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Swayam West?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Swayam West. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Swayam West to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.