Home / Browse projects / Rajkot, Gujarat / PMAY EWS- I

Valid until 31 Mar 2022 Mixed Development project

PMAY EWS- I

By RAJKOT URBAN DEVELOPMENT AUTHORITY

RG-GJ-67802 · RERA PR/GJ/RAJKOT/RAJKOT/Others/MAA00449/EX1/241121 · Last updated on GujRERA portal: 7 Feb 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 8 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2022Possession promisedmoved 8 months from the original
14 of 65Construction stages doneacross 14 buildings; furthest along: Staircases, 85%
38 of 784Units unsoldnot recorded sold or booked
Jump to the 51 documents Report an error

PMAY EWS- I is a Mixed Development project by RAJKOT URBAN DEVELOPMENT AUTHORITY in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/MAA00449/EX1/241121 on 14 Oct 2017. Possession is promised by 31 Mar 2022. The completion date has moved by 8 months from the original filing. 746 of the 784 units on this registration are recorded sold or booked, and 14 of 65 construction stages are filed complete.

At a glance

Project

  • NamePMAY EWS- I
  • TypeMixed Development
  • Location
    • MUNJKA
    • TP - 17
    • FP- 73
    • RAJKOT
    • Munjka
    • Rajkot
    • 360005
  • Pincode360005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/MAA00449/EX1/241121
  • ReraGenie IDRG-GJ-67802

Builder

  • NameRAJKOT URBAN DEVELOPMENT AUTHORITY
  • Entity typeCOMPETENT AUTHORITY/ GOVERNMENT
  • Other registrations9 more →

Key dates

this monthRegisteredOct 2017First promiseJul 2021Revised toMar 2022

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2022
  • Registered on14 Oct 2017
  • Promised completion31 Mar 2022
  • Revised completionRevised to 31 Mar 2022 (originally 15 Jul 2021)
  • Buildings14 building records
  • Documents filed51 files

Current status

95%746 of 784 units booked
65.2%Of the estimated cost spent so far

Figures as on 7 Feb 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---56056
B---56056
C---56056
D---56056
E---56056
F---56056
G---56056
H---56056
I---56056
J---56056
K---56056
L---56056
M---56056
N---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building14

As on 7 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 65 construction stages are filed complete across 14 buildings. The stage furthest along is Staircases, at 85%.

A78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing55%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
B69%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing45%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
C68%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
D64%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing45%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
E78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
F63%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
G66%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
H72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
I66%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
J64%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
K66%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
L64%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
M72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
N72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 7 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,197 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 39.11 cr
Cost incurredRs 25.49 cr
Spent of the estimate65.19%
BuildingWingEstimatedIncurred
ANARs 2.79 crRs 1.82 cr
BNARs 2.79 crRs 1.82 cr
CNARs 2.79 crRs 1.82 cr
DNARs 2.79 crRs 1.82 cr
ENARs 2.79 crRs 1.82 cr
FNARs 2.79 crRs 1.82 cr
GNARs 2.79 crRs 1.82 cr
HNARs 2.79 crRs 1.82 cr
INARs 2.79 crRs 1.82 cr
JNARs 2.79 crRs 1.82 cr
KNARs 2.79 crRs 1.82 cr
LNARs 2.79 crRs 1.82 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKAMLESH PAREKH
EngineerVARUN SUCHAK
EngineerMARS PLANNING & ENGINEERING SERVICES PVT. LTD.

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/RAJKOT/RAJKOT/Others/MAA00449/EX1/241121Applied Jul 2021; approved Nov 2021

Documents filed51

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/MAA00449/EX1/241121 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)7 Feb 2022
Architect's certificate (Form 1)6 Feb 2022
Engineer's certificate (Form 2)6 Feb 2022
Engineer's certificate annexure6 Feb 2022
Site photograph, A6 Feb 2022
Site photograph, B6 Feb 2022
Site photograph, C6 Feb 2022
Site photograph, D6 Feb 2022
Site photograph, E6 Feb 2022
Site photograph, F6 Feb 2022
Site photograph, G6 Feb 2022
Site photograph, H6 Feb 2022
Site photograph, I6 Feb 2022
Site photograph, J6 Feb 2022
Site photograph, K6 Feb 2022
Site photograph, L6 Feb 2022
Site photograph, M6 Feb 2022
Site photograph, N6 Feb 2022
RERA registration certificate14 Oct 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

95%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one moved by 8 months

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep PMAY EWS- I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Munjka1,800+ in Rajkot

2 kmPMAY EWS- IOther 60Dot size: filed unitsN

Filed coordinates, straight-line distance. 60 registered projects within 2 km.

Builder: RAJKOT URBAN DEVELOPMENT AUTHORITY

RAJKOT URBAN DEVELOPMENT AUTHORITY has 10 registrations on GujRERA, including PMAY EWS- I and PMAY EWS- II. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if PMAY EWS- I is delayed beyond 31 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PMAY EWS- I?

The registered promoter entity is RAJKOT URBAN DEVELOPMENT AUTHORITY, a competent authority/ government as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PMAY EWS- I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PMAY EWS- I?

The professionals named in the filing: Architect: KAMLESH PAREKH; Engineer: VARUN SUCHAK; Engineer: MARS PLANNING & ENGINEERING SERVICES PVT. LTD.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PMAY EWS- I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PMAY EWS- I. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PMAY EWS- I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.