Valid until 27 Oct 2026 Mixed Development project

SWASTIK PALAZZO PINNACLE

By DLH DEVELOPERS

RG-GJ-24773 · RERA PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA00977/121217 · Last updated on GujRERA portal: 13 Jul 2019

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Oct 2026Possession promisedno revision filed
18 of 115Construction stages doneacross 13 buildings; furthest along: Plinth, 90%
248 of 267Units unsoldnot recorded sold or booked
Jump to the 49 documents Report an error

SWASTIK PALAZZO PINNACLE is a Mixed Development project by DLH DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA00977/121217 on 12 Dec 2017. Possession is promised by 27 Oct 2026. 19 of the 267 units on this registration are recorded sold or booked, and 18 of 115 construction stages are filed complete.

At a glance

Project

  • NameSWASTIK PALAZZO PINNACLE
  • TypeMixed Development
  • Location
    • F.P.NO.40+44
    • OPP.HANSPURA RESIDENCY
    • HANSPURA-MUTHIYA.
    • Hanspur
    • Daskroi
    • Ahmedabad
    • 382330
  • Pincode382330
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA00977/121217
  • ReraGenie IDRG-GJ-24773

Builder

  • NameDLH DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2017PromisedOct 2026

Key facts

Registration and timeline

  • StatusValid until 27 Oct 2026
  • Registered on12 Dec 2017
  • Promised completion27 Oct 2026
  • Revised completionNone
  • Buildings13 building records
  • Documents filed49 files

Current status

7%19 of 267 units booked
25.6%Of the estimated cost spent so far

Figures as on 13 Jul 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1---0121121
A2---06161
A10---10010
A311---11011
B10---10010
B11---101
B22---202
B312---12012
C8---808
C12---202
C28---808
D20---20020
E---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building13

As on 13 Jul 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 115 construction stages are filed complete across 13 buildings. The stage furthest along is Plinth, at 90%.

A132%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure40%
Internal walls, internal plaster, floorings, doors and windows within flats10%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A226%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure22%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A1024%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, internal plaster, floorings, doors and windows within flats3%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A31125%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure25%
Internal walls, internal plaster, floorings, doors and windows within flats3%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B1021%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth90%
Stilt Floor0%
Slabs of Super Structure3%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B110%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B2225%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, internal plaster, floorings, doors and windows within flats5%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B31231%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats5%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing15%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C819%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C1224%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C2828%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure40%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing10%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D200%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 13 Jul 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes65%
Street lightingYes45%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,438 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 60.56 cr
Cost incurredRs 15.48 cr
Spent of the estimate25.56%
BuildingWingEstimatedIncurred
A1NARs 4.66 crRs 1.19 cr
A2NARs 4.66 crRs 1.19 cr
A10NARs 4.66 crRs 1.19 cr
A311NARs 4.66 crRs 1.19 cr
B10NARs 4.66 crRs 1.19 cr
B11NARs 4.66 crRs 1.19 cr
B22NARs 4.66 crRs 1.19 cr
B312NARs 4.66 crRs 1.19 cr
C8NARs 4.66 crRs 1.19 cr
C12NARs 4.66 crRs 1.19 cr
C28NARs 4.66 crRs 1.19 cr
D20NARs 4.66 crRs 1.19 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMORPHALLAXIS
EngineerN P PARMAR

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA00977/121217 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)13 Jul 2019
Architect's certificate (Form 1)8 Jul 2019
Engineer's certificate (Form 2)8 Jul 2019
Site photograph, A18 Jul 2019
Site photograph, A28 Jul 2019
Site photograph, A108 Jul 2019
Site photograph, A3118 Jul 2019
Site photograph, B108 Jul 2019
Site photograph, B118 Jul 2019
Site photograph, B228 Jul 2019
Site photograph, B3128 Jul 2019
Site photograph, C88 Jul 2019
Site photograph, C128 Jul 2019
Site photograph, C288 Jul 2019
Site photograph, D208 Jul 2019
Site photograph, E8 Jul 2019
RERA registration certificate12 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

7%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep SWASTIK PALAZZO PINNACLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Hanspur5,400+ in Ahmedabad

2 kmSWASTIK PALAZZO PINNACLEOther 280Dot size: filed unitsN

Filed coordinates, straight-line distance. 280 registered projects within 2 km.

Builder: DLH DEVELOPERS

DLH DEVELOPERS has 1 registration on GujRERA, including SWASTIK PALAZZO PINNACLE. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if SWASTIK PALAZZO PINNACLE is delayed beyond 27 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SWASTIK PALAZZO PINNACLE?

The registered promoter entity is DLH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SWASTIK PALAZZO PINNACLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SWASTIK PALAZZO PINNACLE?

The professionals named in the filing: Architect: MORPHALLAXIS; Engineer: N P PARMAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWASTIK PALAZZO PINNACLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWASTIK PALAZZO PINNACLE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWASTIK PALAZZO PINNACLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.