Home / Browse projects / Ahmedabad, Gujarat / Divyajivan City

Valid until 30 Jun 2020 Mixed Development project

Divyajivan City

By DIVYAJIVAN INFRASTRUCTURE PRIVATE LIMITED

RG-GJ-32382 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA02241/EX2/030120 · Last updated on GujRERA portal: 17 Jun 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jun 2020Possession promisedmoved 18 months from the original
97 of 97Construction stages doneacross 14 buildings; every applicable stage filed complete
146 of 627Units unsoldnot recorded sold or booked
Jump to the 51 documents Report an error

Divyajivan City is a Mixed Development project by DIVYAJIVAN INFRASTRUCTURE PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA02241/EX2/030120 on 3 Apr 2018. Possession is promised by 30 Jun 2020. The completion date has moved by 18 months from the original filing. 481 of the 627 units on this registration are recorded sold or booked, and 97 of 97 construction stages are filed complete.

At a glance

Project

  • NameDivyajivan City
  • TypeMixed Development
  • Location
    • Nr. Haridarshan Cross road
    • Nava Naroda
    • Ahmedbad
    • Naroda
    • Ahmedabad City
    • Ahmedabad
    • 382330
  • Pincode382330
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA02241/EX2/030120
  • ReraGenie IDRG-GJ-32382

Builder

  • NameDIVYAJIVAN INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredApr 2018First promiseDec 2018Revised toJun 2020

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2020
  • Registered on3 Apr 2018
  • Promised completion30 Jun 2020
  • Revised completionRevised to 30 Jun 2020 (originally 31 Dec 2018)
  • Buildings14 building records
  • Documents filed51 files

Current status

77%481 of 627 units booked
98.0%Of the estimated cost spent so far

Figures as on 17 Jun 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---28432
Block B---561167
Block C---28432
Block D---28028
Block E---28028
Block F---30030
Block G---30030
Block H---30030
Block I---1020102
Block J---1000100
Block K---60060
Block L---60060
Block M---28028
Society Office------

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building14

As on 17 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

97 of 97 construction stages are filed complete across 14 buildings.

Block A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block H100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block I100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block J100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block K100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block L100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block M100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Society Office100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 17 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,770 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 27.34 cr
Cost incurredRs 26.79 cr
Spent of the estimate98.0%
BuildingWingEstimatedIncurred
Block ANARs 1.95 crRs 1.91 cr
Block BNARs 1.95 crRs 1.91 cr
Block CNARs 1.95 crRs 1.91 cr
Block DNARs 1.95 crRs 1.91 cr
Block ENARs 1.95 crRs 1.91 cr
Block FNARs 1.95 crRs 1.91 cr
Block GNARs 1.95 crRs 1.91 cr
Block HNARs 1.95 crRs 1.91 cr
Block INARs 1.95 crRs 1.91 cr
Block JNARs 1.95 crRs 1.91 cr
Block KNARs 1.95 crRs 1.91 cr
Block LNARs 1.95 crRs 1.91 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay B. Parekh
EngineerA Y CHIPPA

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA02241/EX1/050219Applied Dec 2018; approved Feb 2019
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA02241/EX2/030120Applied Oct 2019; approved Jan 2020

Documents filed51

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA02241/EX2/030120 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)17 Jun 2022
Engineer's certificate (Form 2)17 Jun 2022
Engineer's certificate annexure17 Jun 2022
Accountant's certificate (Form 3)17 Jun 2022
Site photograph, Block A17 Jun 2022
Site photograph, Block B17 Jun 2022
Site photograph, Block C17 Jun 2022
Site photograph, Block D17 Jun 2022
Site photograph, Block E17 Jun 2022
Site photograph, Block F17 Jun 2022
Site photograph, Block G17 Jun 2022
Site photograph, Block H17 Jun 2022
Site photograph, Block I17 Jun 2022
Site photograph, Block J17 Jun 2022
Site photograph, Block K17 Jun 2022
Site photograph, Block L17 Jun 2022
Site photograph, Block M17 Jun 2022
Site photograph, Society Office17 Jun 2022
RERA registration certificate3 Apr 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

77%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 18 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Divyajivan City on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Naroda5,400+ in Ahmedabad

2 kmDivyajivan CityOther 294Dot size: filed unitsN

Filed coordinates, straight-line distance. 294 registered projects within 2 km.

Builder: DIVYAJIVAN INFRASTRUCTURE PRIVATE LIMITED

DIVYAJIVAN INFRASTRUCTURE PRIVATE LIMITED has 1 registration on GujRERA, including Divyajivan City. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Divyajivan City is delayed beyond 30 Jun 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Divyajivan City?

The registered promoter entity is DIVYAJIVAN INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Divyajivan City?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Divyajivan City?

The professionals named in the filing: Architect: Sanjay B. Parekh; Engineer: A Y CHIPPA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Divyajivan City?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Divyajivan City. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Divyajivan City to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.