Home / Browse projects / Ahmedabad, Gujarat / Swagat BaganVille Phase - 1
Swagat BaganVille Phase - 1
By SWAGAT INFRASTRUCTURE P L TD
RG-GJ-64394 · RERA PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA02791/EX2/A1R/130123 · Last updated on GujRERA portal: 30 Jun 2023
Source: official GujRERA filing
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- Separate project account declared
Saved.
Swagat BaganVille Phase - 1 is a Residential/Group Housing project by SWAGAT INFRASTRUCTURE P L TD in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA02791/EX2/A1R/130123 on 1 Jun 2018. Possession is promised by 30 Jun 2023. The completion date has moved by 24 months from the original filing. 16 of the 30 units on this registration are recorded sold or booked, and 40 of 40 construction stages are filed complete.
At a glance
Project
- NameSwagat BaganVille Phase - 1
- TypeResidential/Group Housing
- Location
- Swagat BaganVille
- Nr. Kalhar Bungalows
- Shilaj Rancharada road
- Shilaj
- Ahmedabad
- Daskroi
- Ahmedabad
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA02791/EX2/A1R/130123
- ReraGenie IDRG-GJ-64394
Builder
- NameSWAGAT INFRASTRUCTURE P L TD
- Entity typeCOMPANY
- Other registrations5 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Jun 2023
- Registered on1 Jun 2018
- Promised completion30 Jun 2023
- Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2021)
- Buildings5 building records
- Documents filed42 files
Current status
Figures as on 30 Jun 2023, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TYPE A | - | - | - | 12 | 0 | 12 |
| TYPE B | - | - | - | 2 | 0 | 2 |
| TYPE C | - | - | - | 6 | 0 | 6 |
| TYPE D | - | - | - | 5 | 0 | 5 |
| TYPE E | - | - | - | 5 | 0 | 5 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building5
As on 30 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
40 of 40 construction stages are filed complete across 5 buildings.
TYPE A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TYPE B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TYPE C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TYPE D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
TYPE E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 30 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 100% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TYPE A | NA | Rs 5.62 cr | Rs 5.62 cr |
| TYPE B | NA | Rs 5.62 cr | Rs 5.62 cr |
| TYPE C | NA | Rs 5.62 cr | Rs 5.62 cr |
| TYPE D | NA | Rs 5.62 cr | Rs 5.62 cr |
| TYPE E | NA | Rs 5.62 cr | Rs 5.62 cr |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed42
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA02791/EX2/A1R/130123 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 30 Jun 2023 |
| Engineer's certificate (Form 2) | 30 Jun 2023 |
| Engineer's certificate annexure | 30 Jun 2023 |
| Accountant's certificate (Form 3) | 30 Jun 2023 |
| Site photograph, TYPE A | 30 Jun 2023 |
| Site photograph, TYPE B | 30 Jun 2023 |
| Site photograph, TYPE C | 30 Jun 2023 |
| Site photograph, TYPE D | 30 Jun 2023 |
| Site photograph, TYPE E | 30 Jun 2023 |
| RERA registration certificate | 1 Jun 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ahmedabad
Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.
Keep Swagat BaganVille Phase - 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ahmedabad5,400+ in Ahmedabad
Filed coordinates, straight-line distance. 162 registered projects within 2 km.
CELESTE
SHREE SIDDHI INFRABUILDCON LLP
EWS 76
AHMEDABAD MUNICIPAL CORPORATION
Sumel-8
HN SAFAL REALTECH LLP
SWAMINARAYAN PARK NARODA
DHARMADEV INFRASTRUCTURE LIMITED
EWS-51
AHMEDABAD MUNICIPAL CORPORATION
68 SHOPS + 1228 LIG-2 + 432 MIG-1 AT GOTA
GUJARAT HOUSING BOARD
See every Ahmedabad project, with the district possession charts
Builder: SWAGAT INFRASTRUCTURE P L TD
SWAGAT INFRASTRUCTURE P L TD has 6 registrations on GujRERA, including Swagat Pelican and Swagat Agacia. Read the full track record. See more projects on the Ahmedabad district page.
Frequently asked questions
What are my rights if Swagat BaganVille Phase - 1 is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Swagat BaganVille Phase - 1?
The registered promoter entity is SWAGAT INFRASTRUCTURE P L TD, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Swagat BaganVille Phase - 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Swagat BaganVille Phase - 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback