SUREKHA ENCLAVE
RG-KA-36351 · RERA PRM/KA/RERA/1249/369/PR/190424/006812 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SUREKHA ENCLAVE is a Plotted Development project by NAKSHATRA VENTURES in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/369/PR/190424/006812 on 19 Apr 2024. Possession is promised by 31 Dec 2026.
At a glance
Project
- NameSUREKHA ENCLAVE
- TypePlotted Development
- Location
- Hukkeri
- Belagavi
- 591309
- Pincode591309
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1249/369/PR/190424/006812
- ReraGenie IDRG-KA-36351
Builder
- NameNAKSHATRA VENTURES
- Entity typePartnership Firm
- GSTIN29AEVFS7996E1ZU
- Authorized SignatoryMr. Rajashekar Chanabasappa Hosamani
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Apr 2024
- Promised completion31 Dec 2026
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed220 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership16
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Rudragouda Paragouda Patil | - | - |
| Mallikarjun Rudragouda Patil | - | - |
| Rudragouda Paragouda Patil | - | - |
| Mallikarjun Rudragouda Patil | - | - |
| Rudragouda Paragouda Patil | - | - |
| Mallikarjun Rudragouda Patil | - | - |
| Nikil Yallappa Savagonkar | - | - |
| Omkar Vinod Savagonkar | - | - |
| Suraj Maruti Savagonkar | - | - |
| Aakash Maruri Savagonkar | - | - |
| Nikil Yallappa Savagonkar | - | - |
| Omkar Vinod Savagonkar | - | - |
| Suraj Maruti Savagonkar | - | - |
| Aakash Maruri Savagonkar | - | - |
| Basavraj Shivagouda Patil | - | - |
| Basavraj Shivagouda Patil | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 6.22 cr | Rs 39.28 lakh |
| On-site expenditure-Consultants Fees | Rs 5.00 lakh | Rs 16.57 lakh |
| Payment of taxes | - | Rs 11.06 lakh |
| Principal sum and interest payable to financial institutions-Scheduled Banks | - | Rs 16.05 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | Er. Rakesh R Mane |
| Chartered Accountant | CA Shripad V Karoshi |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed220
As listed on the registration, under the names the promoter filed them with; the newest 80 of 220 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/369/PR/190424/006812 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Sep-2026.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: F6 Engineer Sep-2026.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Horticulture department | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Jun-2026.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: F6 Engineer Jun-2026.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Horticulture department | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Mar-2026_compressed.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: F6 Engineer Mar-2026.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q4 2025-26 Horticulture department | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Dec-2025_organized.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Dec-2025.pdf | 15 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 15 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 15 Jan 2026 |
| Q3 2025-26 Horticulture department | 15 Jan 2026 |
| Q3 2025-26 Upload approval documentFile: Revised Estimation.pdf | 15 Jan 2026 |
| AMMENDMENT OF MODIFICATION NAME INTO NAKSHTRA VENTURESFile: Partnership Deed Name Modification Copy.pdf | 18 Apr 2024 |
| GST CERTIFICATE TO MATCH THE FIRM NAME NAKSHATRA VENTURESFile: GST Certificate (1).pdf | 18 Apr 2024 |
| FIRM REGISTRATION COPY OLD & NEW COPY WITH DISTRICT REGISTRAR OF FIRMS SIGN AND SEALFile: Firm Registration Copy Old & New.pdf | 18 Apr 2024 |
| PARTBNERSHIP DEED COPYFile: Partnership Deed Final Copy.pdf | 18 Apr 2024 |
| Firm Registration CertificateFile: Firm Registration Copy Old & New 2.pdf | 15 Apr 2024 |
| Upload partnership registration certificateFile: Firm Registration Copy.pdf | 4 Apr 2024 |
| chartered accountant certificate in prescribed format form -01File: Form-1 CA Revised.pdf | 4 Apr 2024 |
| sources of funds to complete the projectFile: Source of Funds.pdf | 4 Apr 2024 |
| profit and loss account and balance sheet, 2020-21, 2021-22 & 2022-23 with CA UDIN along with scheduFile: Financial Statements.pdf | 4 Apr 2024 |
| bank affidavit in prescribed formatFile: Bank Affidavit.pdf | 4 Apr 2024 |
| sanction planFile: Approved Plan Clear Copy-min.jpg | 4 Apr 2024 |
| partnership firm registration certificateFile: Firm Registration Copy.pdf | 4 Apr 2024 |
| MR in favour of landowner before conversion for all snos in PDF formatFile: All MR (2).pdf | 4 Apr 2024 |
| EC from 1-4-2007 to till dateFile: Encumbrance Clear Copy.pdf | 4 Apr 2024 |
| title deedFile: GIFT DEED.pdf | 4 Apr 2024 |
| title deedFile: Title Deed Copy.pdf | 4 Apr 2024 |
| advocate search reportFile: Advocate Search Report.pdf | 4 Apr 2024 |
| Relinquishment deedFile: Relinquishment Deed .pdf | 4 Apr 2024 |
| Layout Work OrderFile: Layout Order Copy.pdf | 4 Apr 2024 |
| Layout Work OrderFile: Work Order Copy.pdf | 4 Apr 2024 |
| CDP map showing the proposed siteFile: Village Map (1)_merged_compressed.pdf | 4 Apr 2024 |
| village map showing the proposed siteFile: Village Map (1)_merged_compressed.pdf | 4 Apr 2024 |
| KSPCB CFEFile: KSPCB NOC (2).pdf | 4 Apr 2024 |
| KSPCB CFE Fee Paid ReceiptFile: KSPCB Fee Paid Receipt.jpg | 4 Apr 2024 |
| layout planFile: Approved Plan Clear Copy-min.jpg | 4 Apr 2024 |
| latest dated self attested copy of the renewed Engineer license certificateFile: Engineer Licence Revised.pdf | 4 Apr 2024 |
| Engineer certificate in the prescribed formatFile: Form No-3 Surekha Enclave.pdf | 4 Apr 2024 |
| brief estimated cost of construction certified by the EngineerFile: Brief Estimation Cost (1).pdf | 4 Apr 2024 |
| STP design drawing as per the Guidelines of KSPCB NOCFile: STP Skecth (1).pdf | 4 Apr 2024 |
| source of water supply to the projectFile: Water Supply.pdf | 4 Apr 2024 |
| calculation sheet Common area details certified by the EngineerFile: Certified Amenties & Common Area Details PDF.pdf | 4 Apr 2024 |
| Revenue CertificateFile: Revenue Certificate.pdf | 4 Apr 2024 |
| layout plan OrderFile: Layout Order Copy.pdf | 4 Apr 2024 |
| Upload partnership registration certificateFile: Firm Registration Copy.pdf | 30 Mar 2024 |
| FORM-1 CAFile: Form-1 CA Revised.pdf | 30 Mar 2024 |
| sources of funds to complete the projectFile: Source of Funds.pdf | 30 Mar 2024 |
| profit and loss account and balance sheet, 2020-21, 2021-22 & 2022-23 with CA UDIN along with scheduFile: Financial Statements.pdf | 30 Mar 2024 |
| bank affidavit in prescribed formatFile: Bank Affidavit.pdf | 30 Mar 2024 |
| sanction planFile: Approved Plan Clear Copy-min.jpg | 30 Mar 2024 |
| MR in favour of landowner before conversion for all snos in PDF formatFile: All MR (2).pdf | 30 Mar 2024 |
| merged ECs of all snoFile: Encumbrance Clear Copy.pdf | 30 Mar 2024 |
| title deed in favour of land owner for all snos of the projectFile: GIFT DEED.pdf | 30 Mar 2024 |
| title deed in favour of land owner for all snos of the projectFile: Title Deed Copy.pdf | 30 Mar 2024 |
| Relinquishment deed.File: Relinquishment Deed .pdf | 30 Mar 2024 |
| Layout Work OrderFile: Layout Order Copy.pdf | 30 Mar 2024 |
| CDP map showing the proposed site.File: Village Map (1)_merged_compressed.pdf | 30 Mar 2024 |
| village map showing the proposed siteFile: Village Map (1)_merged_compressed.pdf | 30 Mar 2024 |
| KSPCB CFEFile: KSPCB NOC (2).pdf | 30 Mar 2024 |
| KSPCB CFE Fee Paid ReceiptFile: KSPCB Fee Paid Receipt.jpg | 30 Mar 2024 |
| layout plan.File: Approved Plan Clear Copy-min.jpg | 30 Mar 2024 |
| layout plan OrderFile: Layout Order Copy.pdf | 30 Mar 2024 |
| self attested copy of the renewed Engineer license certificateFile: Engineer Licence Revised.pdf | 30 Mar 2024 |
| Engineer certificate in the prescribed formatFile: Form No-3 Surekha Enclave.pdf | 30 Mar 2024 |
| STP design drawing as per the Guidelines of KSPCB NOCFile: STP Skecth (1).pdf | 30 Mar 2024 |
| source of water supply to the projectFile: Undertaking of Water Supply.pdf | 30 Mar 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep SUREKHA ENCLAVE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
DOLLARS COLONY
SANTOSH IRAPPA KHOT
GAJABARWADI PHASE A
ALTAF ABDULHAMID ATTAR
GAJABARWADI PHASE B
IMRAN GAJABARSAB ATTAR
GAJABARWADI PHASE C
ALLAUDDIN YAHYAKHAN NADAF
GALAXY LAYOUT
MANAGULI ANNAPURNA
PADMAMBA NAGAR
ROHIT PADMANABHA CHOUGALA
See every Belagavi project, with the district possession charts
Builder: NAKSHATRA VENTURES
NAKSHATRA VENTURES has 2 registrations on RERA Karnataka, including SUREKHA ENCLAVE and NAKSHATRA-MORGANITE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if SUREKHA ENCLAVE is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SUREKHA ENCLAVE?
The registered promoter entity is NAKSHATRA VENTURES, a partnership firm as per the filing. Its GSTIN 29AEVFS7996E1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SUREKHA ENCLAVE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SUREKHA ENCLAVE?
The professionals named in the filing: Engineer: Er. Rakesh R Mane; Chartered Accountant: CA Shripad V Karoshi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUREKHA ENCLAVE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback