Home / Browse projects / Belagavi, Karnataka / DOLLARS COLONY
DOLLARS COLONY
RG-KA-30349 · RERA PRM/KA/RERA/1249/369/PR/300923/006295 · Last updated on RERA Karnataka portal: 2 Sep 2023
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
DOLLARS COLONY is a Plotted Development project by SANTOSH IRAPPA KHOT in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/369/PR/300923/006295 on 30 Sep 2023. Possession is promised by 31 Dec 2024.
At a glance
Project
- NameDOLLARS COLONY
- TypePlotted Development
- Location
- Hukkeri
- Belagavi
- 591309
- Pincode591309
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1249/369/PR/300923/006295
- ReraGenie IDRG-KA-30349
Builder
- NameSANTOSH IRAPPA KHOT
- Entity typeOther ( INDIVIDUAL )
- Authorized SignatorySANTOSH IRAPPA KHOT
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on30 Sep 2023
- Promised completion31 Dec 2024
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed98 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SANTOSH IRPPA KHOT | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 1.59 cr | - |
| Interest on borrowings | Rs 12.00 lakh | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | AKSHAY K KUGATOLI |
| Chartered Accountant | GANGADHARMAGENNAVAR |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed98
As listed on the registration, under the names the promoter filed them with; the newest 80 of 98 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/369/PR/300923/006295 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| the sources of funds to complete the project with supporting documentsFile: Source of Fund with supporting documents.pdf | 2 Sep 2023 |
| Declaration of source of fund for completion of projectFile: Final Notice Reply.pdf | 2 Sep 2023 |
| source of fundFile: Source of fund.pdf | 23 Aug 2023 |
| sewer line drawingFile: Certified sewer line drawing by project engineer.pdf | 23 Aug 2023 |
| NOC FROM LAXMI URBAN CO OP CREDIT SOCIETY HUKKERIFile: Khot_Bank NOC (1).pdf | 30 Jul 2023 |
| ABOUT COST OF LANDFile: ABOUT COST OF LAND.pdf | 30 Jul 2023 |
| PROJECT SPECIFICATION SIGNED BY THE ENGINEERFile: specification khot.pdf | 30 Jul 2023 |
| KJP PLAN (NO. OF PARK AND CA)File: KJP PLAN.pdf | 30 Jul 2023 |
| VILLAGE MAPFile: Khot_village map.pdf | 30 Jul 2023 |
| ABOUT BREAK UP OF PLOTSFile: ABOUT BREAK UP OF PLOTS.pdf | 30 Jul 2023 |
| ABOUT LAYOUT WORK ORDERFile: ABOUT LAYOUT WORK ORDER.pdf | 30 Jul 2023 |
| SEWER LINE DRAWINGFile: Sewer line drawing.jpeg | 30 Jul 2023 |
| PROFIT AND LOSS AND BALANCE SHEET 2020-21 WITH CA UDIN REFER PAGE 2File: Balance sheet, P and L with CA UDIN and scheule with IT ACK for financial year 2020-21.pdf | 13 Jun 2023 |
| PROFIT AND LOSS AND BALANCE SHEET 2021-22 WITH CA UDIN REFER PAGE 2File: Balance sheet, P and L with CA UDIN and scheduel with IT Ack for financial year 2021-22.pd | 13 Jun 2023 |
| BANK LETTER FOR DESIGNATED ACCOUNTFile: Bank letter for designated account.jpeg | 13 Jun 2023 |
| MUTATION COPY IN THE NAME OF SANTOSH IRAPPA KHOTFile: MR in the name of Santosh.pdf | 13 Jun 2023 |
| TITLE DOCUMENT SINCE ANCESTRAL PROPERTYFile: mutation copy.pdf | 13 Jun 2023 |
| EC FROM 01/04/2007 TO 05/06/2023File: EC from 01042007 to 05062023.pdf | 13 Jun 2023 |
| ABOUT INDIVIDUAL PLOT SIZE, DIMENSION AND AREAFile: ABOUT PLOT DIMENSION, AREA (1).pdf | 13 Jun 2023 |
| ABOUT WORK ORDERFile: about work order (1).pdf | 13 Jun 2023 |
| VILLAGE MAP/PT SHEETFile: Khot PT seat.pdf | 13 Jun 2023 |
| ABOUT ARCHITECT CERTIFICATEFile: Arch Certificate.pdf | 13 Jun 2023 |
| RENEWED ENGINEER LICENSEFile: Eng license.jpeg | 13 Jun 2023 |
| SIGNED COPY OF ENGINEER CERTIFICATE-FORM 3File: sign Engineer form 3.jpeg | 13 Jun 2023 |
| BRIEF ESTIMATED COST OF DEVELOPMENT FOR CIVIL WORKS CERTIFIED BY ENGINEERFile: Brief estimation of development.pdf | 13 Jun 2023 |
| SEWER LINE DEMARCATIONFile: Sewer line drawing.jpeg | 13 Jun 2023 |
| FEE RECEIPT FOR POWER SUPPLY NOCFile: Electricity NOC-receipt.jpeg | 13 Jun 2023 |
| FEE RECEIPT FOR WATER SUPPLY NOCFile: Water NOC receipt.jpeg | 13 Jun 2023 |
| SIGNED PROJECT SPECIFICATIONFile: sign project specification.jpeg | 13 Jun 2023 |
| Reply to noticeFile: reply to notice.pdf | 13 Jun 2023 |
| RTC, survey 113/*/1 | - |
| Mutation, survey 113/*/1 | - |
| Encumbrance Certificate, survey 113/*/1 | - |
| Conversion/Alienation Order, survey 113/*/1 | - |
| Khatha, survey 113/*/1 | - |
| Certificate issued by CA Form 1File: FORM 1- CA.pdf | - |
| Certificate issued by Engineer Form 3File: FORM 3- ENG.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: NO LITIGATION AFFIDAVIT.pdf | - |
| Certificate from Chartered AccountFile: FORM 1- CA.pdf | - |
| Certificate issued by Architect | - |
| Balance Sheet 2021 - 2022File: NOT YET Finalized.pdf | - |
| Balance Sheet 2020 - 2021File: IT ack, Balance sheet, P and L with CA UDIN and schedule.pdf | - |
| Balance Sheet 2019 - 2020File: IT ack, Balance sheet, P and L with CA UDIN and schedule.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: NOT YET Finalized.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: IT ack, Balance sheet, P and L with CA UDIN and schedule.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: IT ack, Balance sheet, P and L with CA UDIN and schedule.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: IT ack, Balance sheet, P and L with CA UDIN and schedule.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: IT ack, Balance sheet, P and L with CA UDIN and schedule.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: IT ack, Balance sheet, P and L with CA UDIN and schedule.pdf | - |
| layout order khot | - |
| electricity NOC khot | - |
| electricity NOC khot | - |
| layout plan khot | - |
| layout plan khot | - |
| KJP KHOT | - |
| Specification | - |
| KJP KHOT | - |
| layout plan khot | - |
| Khot_Legal Opinion | - |
| Agreement of Sale Proforma (2) (1) | - |
| Allotment Letter_compressed | - |
| NOT YET Finalized | - |
| KHOT_DECLARATION_compressed | - |
| SECTION 3 AFFIDAVIT | - |
| Electricity NOC | - |
| electricity NOC khot | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep DOLLARS COLONY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
GAJABARWADI PHASE A
ALTAF ABDULHAMID ATTAR
GAJABARWADI PHASE B
IMRAN GAJABARSAB ATTAR
GAJABARWADI PHASE C
ALLAUDDIN YAHYAKHAN NADAF
GALAXY LAYOUT
MANAGULI ANNAPURNA
PADMAMBA NAGAR
ROHIT PADMANABHA CHOUGALA
SAI COLONY
Mr. JAFARKHAN GULABSAB NADAF
See every Belagavi project, with the district possession charts
Builder: SANTOSH IRAPPA KHOT
SANTOSH IRAPPA KHOT has 1 registration on RERA Karnataka, including DOLLARS COLONY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if DOLLARS COLONY is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of DOLLARS COLONY?
The registered promoter entity is SANTOSH IRAPPA KHOT, an other ( individual ) as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in DOLLARS COLONY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at DOLLARS COLONY?
The professionals named in the filing: Engineer: AKSHAY K KUGATOLI; Chartered Accountant: GANGADHARMAGENNAVAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DOLLARS COLONY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback