Home / Browse projects / Surat, Gujarat / SURAT TEXTILE BOURSE PHASE-I (PART-A)

Valid until 28 Feb 2029 Commercial project

SURAT TEXTILE BOURSE PHASE-I (PART-A)

By THE BARODA RAYON CORPORATION LIMITED

RG-GJ-46273 · RERA PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/CN283AA10183/261222 · Last updated on GujRERA portal: 13 Aug 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Feb 2029Possession promisedno revision filed
10 of 45Construction stages doneacross 5 buildings; furthest along: Sanitary fittings within the flats, 97%
135 of 323Units unsoldnot recorded sold or booked
Jump to the 46 documents Report an error

SURAT TEXTILE BOURSE PHASE-I (PART-A) is a Commercial project by THE BARODA RAYON CORPORATION LIMITED in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/CN283AA10183/261222 on 26 Dec 2022. Possession is promised by 28 Feb 2029. 188 of the 323 units on this registration are recorded sold or booked, and 10 of 45 construction stages are filed complete.

At a glance

Project

  • NameSURAT TEXTILE BOURSE PHASE-I (PART-A)
  • TypeCommercial
  • Location
    • Plot No. A/P-1
    • R.S.No. 151/P
    • Moje -Udhna
    • R.S. No. 1
    • Moje- Bhedwad
    • R.S. No. :346 To 349
    • Moje -Dindoli
    • Village : Udhna
    • Bhedwad
    • Dindoli
    • Udhna
    • ...
  • Pincode394220
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/CN283AA10183/261222
  • ReraGenie IDRG-GJ-46273

Builder

  • NameTHE BARODA RAYON CORPORATION LIMITED
  • Entity typeCOMPANY
  • Other registrations2 more →

Key dates

this monthRegisteredDec 2022PromisedFeb 2029

Key facts

Registration and timeline

  • StatusValid until 28 Feb 2029
  • Registered on26 Dec 2022
  • Promised completion28 Feb 2029
  • Revised completionNone
  • Buildings5 building records
  • Documents filed46 files

Current status

58%188 of 323 units booked
41.2%Of the estimated cost spent so far

Figures as on 13 Aug 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1---0069
B1---0052
C1---0052
D1---00103
E1---0047

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 13 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary fittings within the flats, at 97%.

A166%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats97%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing97%
B169%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
C144%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats45%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%
D144%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats45%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%
E147%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor85%
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats45%
Sanitary fittings within the flats35%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%

Progress on shared amenities19

As on 13 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes50%
Water supplyNoNot applicable
Sewerage (chamber, lines, septic tank, STP)Yes45%
Storm water drainsYes45%
Landscaping and tree plantingYes35%
Street lightingYes35%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes20%
Fire fightingYes20%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area325,338 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 210.27 cr
Cost incurredRs 86.65 cr
Spent of the estimate41.21%
BuildingWingEstimatedIncurred
B1NARs 63.60 crRs 40.25 cr
C1NARs 45.19 crRs 28.70 cr
D1NARs 43.55 crRs 2.30 cr
E1NARs 41.42 crRs 3.20 cr
A1NARs 16.51 crRs 12.20 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHARAT GOPALBHAI PATEL
EngineerBHARATKUMAR BHUKHANDAS DODHIAWALA

Documents filed46

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/CN283AA10183/261222 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)13 Aug 2025
Architect's certificate (Form 1)12 Aug 2025
Site photograph, A111 Aug 2025
Site photograph, B111 Aug 2025
Site photograph, C111 Aug 2025
Site photograph, D111 Aug 2025
Site photograph, E111 Aug 2025
Engineer's certificate (Form 2)30 Sep 2024
Engineer's certificate annexure30 Sep 2024
RERA registration certificate26 Dec 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

58%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep SURAT TEXTILE BOURSE PHASE-I (PART-A) on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Udhna, Bhedwad, Dindoli2,600+ in Surat

2 kmSURAT TEXTILE BOURSE PHAOther 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: THE BARODA RAYON CORPORATION LIMITED

THE BARODA RAYON CORPORATION LIMITED has 3 registrations on GujRERA, including Shree Laxminarayan Industrial Park-Z Row and SURAT TEXTILE BOURSE PHASE-I (PART-A). Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if SURAT TEXTILE BOURSE PHASE-I (PART-A) is delayed beyond 28 Feb 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SURAT TEXTILE BOURSE PHASE-I (PART-A)?

The registered promoter entity is THE BARODA RAYON CORPORATION LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SURAT TEXTILE BOURSE PHASE-I (PART-A)?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SURAT TEXTILE BOURSE PHASE-I (PART-A)?

The professionals named in the filing: Architect: BHARAT GOPALBHAI PATEL; Engineer: BHARATKUMAR BHUKHANDAS DODHIAWALA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SURAT TEXTILE BOURSE PHASE-I (PART-A)?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SURAT TEXTILE BOURSE PHASE-I (PART-A). Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SURAT TEXTILE BOURSE PHASE-I (PART-A) to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.