ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / SUN SHANTAM

Valid until 30 Oct 2029 Mixed Development project

SUN SHANTAM

By SALASAR REALTY

RG-GJ-23734 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/MAA11742/090523 · Last updated on GujRERA portal: 2 Sep 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Oct 2029Possession promisedno revision filed
27 of 45Construction stages doneacross 5 buildings; furthest along: Stilt Floor, 95%
162 of 349Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

SUN SHANTAM is a Mixed Development project by SALASAR REALTY in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/MAA11742/090523 on 9 May 2023. Possession is promised by 30 Oct 2029. 187 of the 349 units on this registration are recorded sold or booked, and 27 of 45 construction stages are filed complete.

At a glance

Project

  • NameSUN SHANTAM
  • TypeMixed Development
  • Location
    • BLOCK NO.1030
    • F.P. NO.17
    • O.P. NO.12
    • T.P.S. NO. 37 (VARIYAV)
    • AT MOJE: - VARIYAV
    • TA: - ADAJAN
    • DIST: - SURAT
    • Surat City
    • Surat
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/MAA11742/090523
  • ReraGenie IDRG-GJ-23734

Builder

  • NameSALASAR REALTY
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2023PromisedOct 2029

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2029
  • Registered on9 May 2023
  • Promised completion30 Oct 2029
  • Revised completionNone
  • Buildings5 building records
  • Documents filed43 files

Current status

54%187 of 349 units booked
23.2%Of the estimated cost spent so far

Figures as on 2 Sep 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
I---56056
H---56056
K---56056
J---56056
L+M---10813125

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 2 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is Stilt Floor, at 95%.

I89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats55%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
H91%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats60%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
K74%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats12%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing10%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing55%
J72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing15%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing15%
L+M84%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing45%

Progress on shared amenities19

As on 2 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,313 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 63.50 cr
Cost incurredRs 14.75 cr
Spent of the estimate23.23%
BuildingWingEstimatedIncurred
L+MNARs 20.00 crRs 2.50 cr
JNARs 11.85 crRs 2.50 cr
KNARs 11.85 crRs 2.25 cr
HNARs 9.90 crRs 4.00 cr
INARs 9.90 crRs 3.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMIRAL ASHOKKUMAR HADAKIA
EngineerHemant A. Shukla

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/MAA11742/090523 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)2 Sep 2025
Accountant's certificate (Form 3)2 Sep 2025
Site photograph, I2 Sep 2025
Site photograph, H2 Sep 2025
Site photograph, K2 Sep 2025
Site photograph, J2 Sep 2025
Site photograph, L+M2 Sep 2025
Engineer's certificate (Form 2)22 Jun 2024
Engineer's certificate annexure22 Jun 2024
RERA registration certificate9 May 2023
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

54%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep SUN SHANTAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Surat2,600+ in Surat

2 kmSUN SHANTAMOther 54Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: SALASAR REALTY

SALASAR REALTY has 1 registration on GujRERA, including SUN SHANTAM. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if SUN SHANTAM is delayed beyond 30 Oct 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SUN SHANTAM?

The registered promoter entity is SALASAR REALTY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SUN SHANTAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUN SHANTAM?

The professionals named in the filing: Architect: MIRAL ASHOKKUMAR HADAKIA; Engineer: Hemant A. Shukla. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUN SHANTAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUN SHANTAM. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUN SHANTAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.