Sumel-10
RG-GJ-05551 · RERA PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/CAA00085/060917 · Last updated on GujRERA portal: 17 Feb 2018
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
- Separate project account declared
Saved.
Sumel-10 is a Commercial project by SAFAL GOYAL DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/CAA00085/060917 on 6 Sep 2017. Possession is promised by 30 Sep 2018.
At a glance
Project
- NameSumel-10
- TypeCommercial
- Location
- MH Mill
- B/s Kalupur Railway Station
- Nr. Ambedkar Hall
- Saraspur
- Shaher Kotda
- Ahmedabad City
- Ahmedabad
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/CAA00085/060917
- ReraGenie IDRG-GJ-05551
Builder
- NameSAFAL GOYAL DEVELOPERS
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Sep 2018
- Registered on6 Sep 2017
- Promised completion30 Sep 2018
- Revised completionNone
- Buildings7 building records
- Documents filed48 files
Current status
Figures as on 17 Feb 2018, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| G+H | - | - | - | - | - | 18 |
| I+J | - | - | - | - | - | 18 |
| K+L | - | - | - | - | - | 18 |
| M | - | - | - | - | - | 7 |
| A+B+C | - | - | - | - | - | 20 |
| D+E | - | - | - | - | - | 18 |
| F | - | - | - | - | - | 7 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building7
As on 17 Feb 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
56 of 56 construction stages are filed complete across 7 buildings.
G+H100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
I+J100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
K+L100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
M100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
A+B+C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D+E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
F100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 17 Feb 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | Yes | 100% |
| Drinking water facilities | Yes | 100% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | Yes | 100% |
| Security | Yes | 100% |
| Letter box | Yes | 100% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A+B+C | NA | Rs 5.57 cr | Rs 5.57 cr |
| D+E | NA | Rs 5.57 cr | Rs 5.57 cr |
| F | NA | Rs 5.57 cr | Rs 5.57 cr |
| G+H | NA | Rs 5.57 cr | Rs 5.57 cr |
| I+J | NA | Rs 5.57 cr | Rs 5.57 cr |
| K+L | NA | Rs 5.57 cr | Rs 5.57 cr |
| M | NA | Rs 5.57 cr | Rs 5.57 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Dipikaben Chavda, ADS ARCHITECT PVT. LTD. |
| Engineer | Naresh K. Shah |
Documents filed48
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/CAA00085/060917 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 17 Feb 2018 |
| Engineer's certificate (Form 2) | 17 Feb 2018 |
| Site photograph, G+H | 16 Feb 2018 |
| Site photograph, G+H | 16 Feb 2018 |
| Site photograph, I+J | 16 Feb 2018 |
| Site photograph, I+J | 16 Feb 2018 |
| Site photograph, K+L | 16 Feb 2018 |
| Site photograph, K+L | 16 Feb 2018 |
| Site photograph, M | 16 Feb 2018 |
| Site photograph, A+B+C | 16 Feb 2018 |
| Site photograph, A+B+C | 16 Feb 2018 |
| Site photograph, A+B+C | 16 Feb 2018 |
| Site photograph, D+E | 16 Feb 2018 |
| Site photograph, D+E | 16 Feb 2018 |
| Site photograph, F | 16 Feb 2018 |
| RERA registration certificate | 6 Sep 2017 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ahmedabad
Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.
Keep Sumel-10 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shaher Kotda5,400+ in Ahmedabad
Filed coordinates, straight-line distance. 23 registered projects within 2 km.
CELESTE
SHREE SIDDHI INFRABUILDCON LLP
EWS 76
AHMEDABAD MUNICIPAL CORPORATION
Sumel-8
HN SAFAL REALTECH LLP
SWAMINARAYAN PARK NARODA
DHARMADEV INFRASTRUCTURE LIMITED
EWS-51
AHMEDABAD MUNICIPAL CORPORATION
68 SHOPS + 1228 LIG-2 + 432 MIG-1 AT GOTA
GUJARAT HOUSING BOARD
See every Ahmedabad project, with the district possession charts
Builder: SAFAL GOYAL DEVELOPERS
SAFAL GOYAL DEVELOPERS has 2 registrations on GujRERA, including Sumel-10 and Sumel 10 (Phase-II). Read the full track record. See more projects on the Ahmedabad district page.
Frequently asked questions
What are my rights if Sumel-10 is delayed beyond 30 Sep 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Sumel-10?
The registered promoter entity is SAFAL GOYAL DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Sumel-10?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Sumel-10?
The professionals named in the filing: Architect: Dipikaben Chavda, ADS ARCHITECT PVT. LTD.; Engineer: Naresh K. Shah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sumel-10?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.