Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Nov 2026Possession promisedmoved 11 months from the original
320 of 360Construction stages doneacross 40 buildings; furthest along: Stilt Floor, 0%
6 of 40Units unsoldnot recorded sold or booked
Jump to the 64 documents Report an error

SUHRAD GREENS is a Residential/Group Housing project by SUHRAD GREENS in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RN82AA09982/EX1/240326/301126 on 18 Jun 2022. Possession is promised by 30 Nov 2026. The completion date has moved by 11 months from the original filing. 34 of the 40 units on this registration are recorded sold or booked, and 320 of 360 construction stages are filed complete.

At a glance

Project

  • NameSUHRAD GREENS
  • TypeResidential/Group Housing
  • Location
    • TP 1
    • Behind Radha Bungalows
    • Karamsad Vidyanagar Road
    • Karamsad
    • KARAMSAD
    • Anand
    • 388325
  • Pincode388325
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RN82AA09982/EX1/240326/301126
  • ReraGenie IDRG-GJ-19954

Builder

  • NameSUHRAD GREENS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJun 2022First promiseDec 2025Revised toNov 2026

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2026
  • Registered on18 Jun 2022
  • Promised completion30 Nov 2026
  • Revised completionRevised to 30 Nov 2026 (originally 31 Dec 2025)
  • Buildings40 building records
  • Documents filed64 files

Current status

85%34 of 40 units booked
100.0%Of the estimated cost spent so far

Figures as on 17 Mar 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bungalow 1---101
Bungalow 2---101
Bungalow 3---101
Bungalow 4---101
Bungalow 5---101
Bungalow 6---101
Bungalow 7---101
Bungalow 8---101
Bungalow 9---101
Bungalow 10---101
Bungalow 11---101
Bungalow 12---101
Bungalow 13---101
Bungalow 14---101
Bungalow 15---101
Bungalow 16---101
Bungalow 17---101
Bungalow 18---101
Bungalow 19---101
Bungalow 20---101
Bungalow 21---101
Bungalow 22---101
Bungalow 23---101
Bungalow 24---101
Bungalow 25---101
Bungalow 26---101
Bungalow 27---101
Bungalow 28---101
Bungalow 29---101
Bungalow 30---101
Bungalow 31---101
Bungalow 32---101
Bungalow 33---101
Bungalow 34---101
Bungalow 35---101
Bungalow 36---101
Bungalow 37---101
Bungalow 38---101
Bungalow 39---101
Bungalow 40---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 17 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 40 buildings; the table lists the first 20.

320 of 360 construction stages are filed complete across 40 buildings. The stage furthest along is Stilt Floor, at 0%.

Bungalow 189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 489%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 589%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 689%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 889%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 989%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1089%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1489%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1589%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1689%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1889%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 1989%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Bungalow 2089%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 17 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,016 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 8.22 cr
Cost incurredRs 8.22 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Bungalow 12NARs 21.40 lakhRs 21.40 lakh
Bungalow 13NARs 21.40 lakhRs 21.40 lakh
Bungalow 14NARs 21.40 lakhRs 21.40 lakh
Bungalow 15NARs 21.40 lakhRs 21.40 lakh
Bungalow 16NARs 21.40 lakhRs 21.40 lakh
Bungalow 17NARs 21.40 lakhRs 21.40 lakh
Bungalow 18NARs 21.40 lakhRs 21.40 lakh
Bungalow 19NARs 21.40 lakhRs 21.40 lakh
Bungalow 20NARs 21.40 lakhRs 21.40 lakh
Bungalow 21NARs 21.40 lakhRs 21.40 lakh
Bungalow 22NARs 21.40 lakhRs 21.40 lakh
Bungalow 23NARs 21.40 lakhRs 21.40 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPriyanka Bhadreshkumar Gajjar
EngineerMITESH HARSHADRAY DAVE

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RN82AA09982/EX1/240326/301126Applied Jan 2026; approved Mar 2026

Documents filed64

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/Anand VallabhVidhyanagar Karmsad Urban Development Authority/RN82AA09982/EX1/240326/301126 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)17 Mar 2026
Architect's certificate (Form 1)31 Jan 2026
Engineer's certificate (Form 2)31 Jan 2026
Engineer's certificate annexure31 Jan 2026
Site photograph, Bungalow 130 Jan 2026
Site photograph, Bungalow 230 Jan 2026
Site photograph, Bungalow 330 Jan 2026
Site photograph, Bungalow 430 Jan 2026
Site photograph, Bungalow 530 Jan 2026
Site photograph, Bungalow 630 Jan 2026
Site photograph, Bungalow 730 Jan 2026
Site photograph, Bungalow 830 Jan 2026
Site photograph, Bungalow 930 Jan 2026
Site photograph, Bungalow 1030 Jan 2026
Site photograph, Bungalow 1130 Jan 2026
Site photograph, Bungalow 1230 Jan 2026
Site photograph, Bungalow 1330 Jan 2026
Site photograph, Bungalow 1430 Jan 2026
Site photograph, Bungalow 1530 Jan 2026
Site photograph, Bungalow 1630 Jan 2026
Site photograph, Bungalow 1730 Jan 2026
Site photograph, Bungalow 1830 Jan 2026
Site photograph, Bungalow 1930 Jan 2026
Site photograph, Bungalow 2030 Jan 2026
Site photograph, Bungalow 2130 Jan 2026
Site photograph, Bungalow 2230 Jan 2026
Site photograph, Bungalow 2330 Jan 2026
Site photograph, Bungalow 2430 Jan 2026
Site photograph, Bungalow 2530 Jan 2026
Site photograph, Bungalow 2630 Jan 2026
Site photograph, Bungalow 2730 Jan 2026
Site photograph, Bungalow 2830 Jan 2026
Site photograph, Bungalow 2930 Jan 2026
Site photograph, Bungalow 3030 Jan 2026
Site photograph, Bungalow 3130 Jan 2026
Site photograph, Bungalow 3230 Jan 2026
Site photograph, Bungalow 3330 Jan 2026
Site photograph, Bungalow 3430 Jan 2026
Site photograph, Bungalow 3530 Jan 2026
Site photograph, Bungalow 3630 Jan 2026
Site photograph, Bungalow 3730 Jan 2026
Site photograph, Bungalow 3830 Jan 2026
Site photograph, Bungalow 3930 Jan 2026
Site photograph, Bungalow 4030 Jan 2026
RERA registration certificate18 Jun 2022
Extension certificate-
Proforma agreement for sale-
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-

How this compares with Anand

85%of this project is bookeddistrict median 57%
17%of Anand projects moved their completion datethis one moved by 11 months

Computed across the 310+ Anand projects on ReraGenie, from their own filings.

Keep SUHRAD GREENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KARAMSAD310+ in Anand

2 kmSUHRAD GREENSOther 100Dot size: filed unitsN

Filed coordinates, straight-line distance. 100 registered projects within 2 km.

Builder: SUHRAD GREENS

SUHRAD GREENS has 1 registration on GujRERA, including SUHRAD GREENS. Read the full track record. See more projects on the Anand district page.

Frequently asked questions

What are my rights if SUHRAD GREENS is delayed beyond 30 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SUHRAD GREENS?

The registered promoter entity is SUHRAD GREENS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SUHRAD GREENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUHRAD GREENS?

The professionals named in the filing: Architect: Priyanka Bhadreshkumar Gajjar; Engineer: MITESH HARSHADRAY DAVE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUHRAD GREENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUHRAD GREENS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUHRAD GREENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.