SONAMAHOR RADHA

By HINDVA INFRATECH

RG-GJ-19385 · RERA PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA12896/070224/311228 · Last updated on GujRERA portal: 7 Feb 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2029Possession promisedno revision filed
5 of 9Construction stages donefurthest along: Stilt Floor, 75%
7 of 28Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

SONAMAHOR RADHA is a Residential/Group Housing project by HINDVA INFRATECH in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA12896/070224/311228 on 7 Feb 2024. Possession is promised by 30 Apr 2029. 21 of the 28 units on this registration are recorded sold or booked, and 5 of 9 construction stages are filed complete.

At a glance

Project

  • NameSONAMAHOR RADHA
  • TypeResidential/Group Housing
  • Location
    • SONAMAHOR RADHA
    • OPP. PRUSHTI VATIKA
    • ROYAL PARK
    • MAVDI
    • RAJKOT
    • MAVDI
    • Rajkot
    • 360005
  • Pincode360005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA12896/070224/311228
  • ReraGenie IDRG-GJ-19385

Builder

  • NameHINDVA INFRATECH
  • Entity typePARTNERSHIP FIRM
  • Other registrations5 more →

Key dates

this monthRegisteredFeb 2024PromisedApr 2029

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2029
  • Registered on7 Feb 2024
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Current status

75%21 of 28 units booked
39.9%Of the estimated cost spent so far

Figures as on 7 Feb 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 75%.

A: 77% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor75%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats64%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities23

As on 7 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes30%
Water supplyYes75%
Sewerage (chamber, lines, septic tank, STP)Yes75%
Storm water drainsYes55%
Landscaping and tree plantingYes15%
Street lightingYes20%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxNoNot applicable
Compound wallYes50%
Plinth protectionYes35%
Water tankYes60%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area542 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 3.70 cr
Cost incurredRs 1.48 cr
Spent of the estimate39.86%
BuildingWingEstimatedIncurred
ANARs 3.70 crRs 1.48 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPrithvirajsinh Bilkha
EngineerHARESH VIRJIBHAI GHELANI

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA12896/070224/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate7 Feb 2024
Engineer's certificate (Form 2)19 Jan 2024
Engineer's certificate annexure19 Jan 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

75%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep SONAMAHOR RADHA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near MAVDI1,800+ in Rajkot

2 kmSONAMAHOR RADHAOther 285Dot size: filed unitsN

Filed coordinates, straight-line distance. 285 registered projects within 2 km.

Builder: HINDVA INFRATECH

HINDVA INFRATECH has 6 registrations on GujRERA, including RATNAGAR ELITE and SONAMAHOR ELEVATE. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if SONAMAHOR RADHA is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SONAMAHOR RADHA?

The registered promoter entity is HINDVA INFRATECH, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SONAMAHOR RADHA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SONAMAHOR RADHA?

The professionals named in the filing: Architect: Prithvirajsinh Bilkha; Engineer: HARESH VIRJIBHAI GHELANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SONAMAHOR RADHA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SONAMAHOR RADHA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SONAMAHOR RADHA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.