Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2025Possession promisedmoved 12 months from the original
16 of 18Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 0%
11 of 107Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

SKYWAY ELEGANCE is a Mixed Development project by LOTUS DEVELOPERS in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA09264/EX1/050225/281225 on 30 Oct 2021. Possession is promised by 28 Dec 2025. The completion date has moved by 12 months from the original filing. 96 of the 107 units on this registration are recorded sold or booked, and 16 of 18 construction stages are filed complete.

At a glance

Project

  • NameSKYWAY ELEGANCE
  • TypeMixed Development
  • Location
    • Skyway Elegance
    • Nr Shivdhara campus
    • Naroda Dehgam Ring Road Circle
    • Ahmedabad
    • Daskroi
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA09264/EX1/050225/281225
  • ReraGenie IDRG-GJ-83080

Builder

  • NameLOTUS DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredOct 2021First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusValid until 28 Dec 2025
  • Registered on30 Oct 2021
  • Promised completion28 Dec 2025
  • Revised completionRevised to 28 Dec 2025 (originally 31 Dec 2024)
  • Buildings2 building records
  • Documents filed42 files

Current status

90%96 of 107 units booked
100.0%Of the estimated cost spent so far

Figures as on 15 Jul 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---42951
B+C---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 15 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 0%.

A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B+C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 15 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,809 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 14.00 cr
Cost incurredRs 14.00 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 7.00 crRs 7.00 cr
B+CNARs 7.00 crRs 7.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANKET VORA
EngineerCHIRAGKUMAR P NAKRANI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA09264/EX1/050225/281225Applied Dec 2024; approved Feb 2025

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA09264/EX1/050225/281225 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)15 Jul 2025
Architect's certificate (Form 1)10 Jul 2025
Site photograph, A3 Jul 2025
Site photograph, B+C3 Jul 2025
Engineer's certificate (Form 2)27 Dec 2024
Engineer's certificate annexure27 Dec 2024
RERA registration certificate30 Oct 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

90%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep SKYWAY ELEGANCE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmSKYWAY ELEGANCEOther 132Dot size: filed unitsN

Filed coordinates, straight-line distance. 132 registered projects within 2 km.

Builder: LOTUS DEVELOPERS

LOTUS DEVELOPERS has 3 registrations on GujRERA, including SKYWAY ELEGANCE and 24 KARAT. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if SKYWAY ELEGANCE is delayed beyond 28 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SKYWAY ELEGANCE?

The registered promoter entity is LOTUS DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SKYWAY ELEGANCE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SKYWAY ELEGANCE?

The professionals named in the filing: Architect: SANKET VORA; Engineer: CHIRAGKUMAR P NAKRANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SKYWAY ELEGANCE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SKYWAY ELEGANCE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SKYWAY ELEGANCE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.