Valid until 18 Apr 2022 Residential/Group Housing project

Sky City

By KATARIYA PROPERTIES PRIVATE LIMITED

RG-GJ-97409 · RERA PR/GJ/BHARUCH/ANKLESVAR/Others/RAA04804/060219 · Last updated on GujRERA portal: 6 Feb 2019

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Apr 2022Possession promisedno revision filed
0 of 21Construction stages doneacross 3 buildings; furthest along: Excavation, 47%
Jump to the 38 documents Report an error

Sky City is a Residential/Group Housing project by KATARIYA PROPERTIES PRIVATE LIMITED in Bharuch, Gujarat, registered with GujRERA as PR/GJ/BHARUCH/ANKLESVAR/Others/RAA04804/060219 on 6 Feb 2019. Possession is promised by 18 Apr 2022.

At a glance

Project

  • NameSky City
  • TypeResidential/Group Housing
  • Location
    • SKY CITY NO.81
    • OPP
    • PANI PURVATHA TANKI
    • BESIDE MAA RESIDENCY
    • ANKLESHWAR
    • 393001
    • KY CITY NO.81
    • OPP
    • PANI PURVATHA TANKI
    • BESIDE MAA...
  • Pincode393020
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/BHARUCH/ANKLESVAR/Others/RAA04804/060219
  • ReraGenie IDRG-GJ-97409

Builder

  • NameKATARIYA PROPERTIES PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredFeb 2019PromisedApr 2022

Key facts

Registration and timeline

  • StatusValid until 18 Apr 2022
  • Registered on6 Feb 2019
  • Promised completion18 Apr 2022
  • Revised completionNone
  • Buildings3 building records
  • Documents filed38 files

Current status

6.9%Of the estimated cost spent so far

Figures as on 6 Feb 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A-----54
TYPE B-----4
TYPE C-----1

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 6 Feb 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 21 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 47%.

TYPE A34%
ActivityProgress
Excavation47%
Podiums (if any)Not applicable
Plinth47%
Stilt FloorNot applicable
Slabs of Super Structure42%
Internal walls, internal plaster, floorings, doors and windows within flats34%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks34%
External plumbing and external plaster, elevation, completion of terraces with waterproofing34%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE B23%
ActivityProgress
Excavation40%
Podiums (if any)Not applicable
Plinth40%
Stilt FloorNot applicable
Slabs of Super Structure40%
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
TYPE C0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 6 Feb 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,818 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.53 cr
Cost incurredRs 85.98 lakh
Spent of the estimate6.86%
BuildingWingEstimatedIncurred
TYPE ANARs 4.18 crRs 28.66 lakh
TYPE BNARs 4.18 crRs 28.66 lakh
TYPE CNARs 4.18 crRs 28.66 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR. SUHEL BHAJJUWALA
EngineerS.V.N. CONSULTING ENGINEER

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHARUCH/ANKLESVAR/Others/RAA04804/060219 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate6 Feb 2019
Architect's certificate (Form 1)6 Jul 2018
Engineer's certificate (Form 2)6 Jul 2018
Site photograph, TYPE A6 Jul 2018
Site photograph, TYPE B6 Jul 2018
Site photograph, TYPE C6 Jul 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Bharuch

20%of Bharuch projects moved their completion datethis one has not

Computed across the 200+ Bharuch projects on ReraGenie, from their own filings.

Keep Sky City on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Diva200+ in Bharuch

2 kmSky CityOther 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: KATARIYA PROPERTIES PRIVATE LIMITED

KATARIYA PROPERTIES PRIVATE LIMITED has 1 registration on GujRERA, including Sky City. Read the full track record. See more projects on the Bharuch district page.

Frequently asked questions

What are my rights if Sky City is delayed beyond 18 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Sky City?

The registered promoter entity is KATARIYA PROPERTIES PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Sky City?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Sky City?

The professionals named in the filing: Architect: AR. SUHEL BHAJJUWALA; Engineer: S.V.N. CONSULTING ENGINEER. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sky City?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sky City. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sky City to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.