ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmedabad, Gujarat / Silver Brook 2

Valid until 30 Apr 2027 Mixed Development project

Silver Brook 2

By AVIRAT SHILAJ PROJECT

RG-GJ-37897 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA11094/A1M/171023 · Last updated on GujRERA portal: 30 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
8 of 9Construction stages donefurthest along: Sanitary fittings within the flats, 30%
72 of 192Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

Silver Brook 2 is a Mixed Development project by AVIRAT SHILAJ PROJECT in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA11094/A1M/171023 on 29 Dec 2022. Possession is promised by 30 Apr 2027. 120 of the 192 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameSilver Brook 2
  • TypeMixed Development
  • Location
    • Silver Brook 2
    • Near S P Ring Road
    • Near Shilaj Circle
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA11094/A1M/171023
  • ReraGenie IDRG-GJ-37897

Builder

  • NameAVIRAT SHILAJ PROJECT
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredDec 2022PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on29 Dec 2022
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Current status

62%120 of 192 units booked
98.9%Of the estimated cost spent so far

Figures as on 30 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B+C---16824192

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Sanitary fittings within the flats, at 30%.

A+B+C: 92% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes40%
Street lightingYes80%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes90%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementYes90%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes90%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes60%
Letter boxYes80%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,463 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 45.00 cr
Cost incurredRs 44.50 cr
Spent of the estimate98.89%
BuildingWingEstimatedIncurred
A+B+CNARs 45.00 crRs 44.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPlacekinesis Asociates
EngineerBhavik Patel

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA11094/A1M/171023 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)30 Jul 2026
Engineer's certificate annexure30 Jul 2026
Accountant's certificate (Form 3)30 Jul 2026
Architect's certificate (Form 1)29 Jul 2026
Site photograph, A+B+C29 Jul 2026
RERA registration certificate29 Dec 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

62%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Silver Brook 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ahmedabad5,400+ in Ahmedabad

2 kmSilver Brook 2Other 156Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: AVIRAT SHILAJ PROJECT

AVIRAT SHILAJ PROJECT has 2 registrations on GujRERA, including SILVER BROOK and Silver Brook 2. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Silver Brook 2 is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Silver Brook 2?

The registered promoter entity is AVIRAT SHILAJ PROJECT, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Silver Brook 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Silver Brook 2?

The professionals named in the filing: Architect: Placekinesis Asociates; Engineer: Bhavik Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Silver Brook 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Silver Brook 2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Silver Brook 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.