SHYAM YAMUNA

By SIYARAM DEVELOPERS

RG-GJ-65416 · RERA PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA15065/050425/311230 · Last updated on GujRERA portal: 3 Jun 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2031Possession promisedno revision filed
20 of 45Construction stages doneacross 5 buildings; furthest along: Internal walls, 70%
221 of 280Units unsoldnot recorded sold or booked
Jump to the 29 documents Report an error

SHYAM YAMUNA is a Residential/Group Housing project by SIYARAM DEVELOPERS in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA15065/050425/311230 on 5 Apr 2025. Possession is promised by 30 Apr 2031. 59 of the 280 units on this registration are recorded sold or booked, and 20 of 45 construction stages are filed complete.

At a glance

Project

  • NameSHYAM YAMUNA
  • TypeResidential/Group Housing
  • Location
    • BLOCK NO.156
    • SWAMINARAYAN MISSION SCHOOL ROAD
    • OPP. KARUNESH VILLA
    • PASODARA
    • NEAR LASKANA
    • TAL. KAMREJ
    • PASODARA
    • Surat City
    • Surat
    • 395006
  • Pincode395006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA15065/050425/311230
  • ReraGenie IDRG-GJ-65416

Builder

  • NameSIYARAM DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2025PromisedApr 2031

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2031
  • Registered on5 Apr 2025
  • Promised completion30 Apr 2031
  • Revised completionNone
  • Buildings5 building records
  • Documents filed29 files

Current status

21%59 of 280 units booked
49.8%Of the estimated cost spent so far

Figures as on 3 Jun 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D---56056
C---56056
E---56056
B---56056
A---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 70%.

D58%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C58%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
E58%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B52%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A53%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing10%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,464 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 36.13 cr
Cost incurredRs 18.00 cr
Spent of the estimate49.82%
BuildingWingEstimatedIncurred
ANARs 7.26 crRs 3.55 cr
BNARs 7.26 crRs 3.47 cr
DNARs 7.26 crRs 3.80 cr
ENARs 7.17 crRs 3.60 cr
CNARs 7.16 crRs 3.58 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHVINKUMAR R. DOBARIA
EngineerDIVYESHBHAI MANSUKHBHAI SAKARIYA

Documents filed29

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Surat Municipal Corporation/RAA15065/050425/311230 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)3 Jun 2026
Engineer's certificate annexure3 Jun 2026
Accountant's certificate (Form 3)3 Jun 2026
Architect's certificate (Form 1)2 Jun 2026
Site photograph, D1 Jun 2026
Site photograph, C1 Jun 2026
Site photograph, E1 Jun 2026
Site photograph, B1 Jun 2026
Site photograph, A1 Jun 2026
RERA registration certificate5 Apr 2025
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-

How this compares with Surat

21%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep SHYAM YAMUNA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near PASODARA2,600+ in Surat

2 kmSHYAM YAMUNAOther 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: SIYARAM DEVELOPERS

SIYARAM DEVELOPERS has 1 registration on GujRERA, including SHYAM YAMUNA. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if SHYAM YAMUNA is delayed beyond 30 Apr 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHYAM YAMUNA?

The registered promoter entity is SIYARAM DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHYAM YAMUNA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHYAM YAMUNA?

The professionals named in the filing: Architect: ASHVINKUMAR R. DOBARIA; Engineer: DIVYESHBHAI MANSUKHBHAI SAKARIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHYAM YAMUNA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHYAM YAMUNA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHYAM YAMUNA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.