Home / Browse projects / Vadodara, Gujarat / SHUKUN DUPLEX

Valid until 30 Jun 2022 Residential/Group Housing project

SHUKUN DUPLEX

By VIR DEVELOPERS

RG-GJ-42870 · RERA PR/GJ/VADODARA/PADRA/Others/RAA05034/EX1/260422 · Last updated on GujRERA portal: 26 Dec 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2022Possession promisedmoved 12 months from the original
11 of 29Construction stages doneacross 6 buildings; furthest along: Sanitary fittings within the flats, 95%
22 of 48Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

SHUKUN DUPLEX is a Residential/Group Housing project by VIR DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/PADRA/Others/RAA05034/EX1/260422 on 12 Mar 2019. Possession is promised by 30 Jun 2022. The completion date has moved by 12 months from the original filing. 26 of the 48 units on this registration are recorded sold or booked, and 11 of 29 construction stages are filed complete.

At a glance

Project

  • NameSHUKUN DUPLEX
  • TypeResidential/Group Housing
  • Location
    • BESIDE MEERA RESIDANCY
    • BEHIND WESTERN CERAMIC
    • NR. KHOKHAR TALAV
    • PADRA ROAD
    • SANGMA
    • Sangama
    • Padra
    • Vadodara
    • 391440
  • Pincode391440
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/PADRA/Others/RAA05034/EX1/260422
  • ReraGenie IDRG-GJ-42870

Builder

  • NameVIR DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2019First promiseJun 2021Revised toJun 2022

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2022
  • Registered on12 Mar 2019
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 30 Jun 2021)
  • Buildings6 building records
  • Documents filed43 files

Current status

54%26 of 48 units booked
41.1%Of the estimated cost spent so far

Figures as on 26 Dec 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C---808
D---808
E---808
F---808
A---808
B---808

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 26 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 29 construction stages are filed complete across 6 buildings. The stage furthest along is Sanitary fittings within the flats, at 95%.

C97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
D96%
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
E97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
F97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
A97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
B97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 26 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes75%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes90%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes85%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,880 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.28 cr
Cost incurredRs 1.35 cr
Spent of the estimate41.15%
BuildingWingEstimatedIncurred
ANARs 54.67 lakhRs 22.50 lakh
BNARs 54.67 lakhRs 22.50 lakh
CNARs 54.67 lakhRs 22.50 lakh
DNARs 54.67 lakhRs 22.50 lakh
ENARs 54.67 lakhRs 22.50 lakh
FNARs 54.67 lakhRs 22.50 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANSUYA A DHAIBAR
EngineerCHIRAG G BHATT

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/PADRA/Others/RAA05034/EX1/260422Applied Dec 2021; approved Apr 2022

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/PADRA/Others/RAA05034/EX1/260422 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)26 Dec 2021
Site photograph, C15 Dec 2021
Site photograph, D15 Dec 2021
Site photograph, E15 Dec 2021
Site photograph, F15 Dec 2021
Site photograph, A15 Dec 2021
Site photograph, B15 Dec 2021
Accountant's certificate (Form 3)6 May 2021
Engineer's certificate (Form 2)7 Apr 2021
Engineer's certificate annexure7 Apr 2021
RERA registration certificate12 Mar 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

54%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHUKUN DUPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sangama2,900+ in Vadodara

2 kmSHUKUN DUPLEXOther 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: VIR DEVELOPERS

VIR DEVELOPERS has 1 registration on GujRERA, including SHUKUN DUPLEX. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHUKUN DUPLEX is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHUKUN DUPLEX?

The registered promoter entity is VIR DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHUKUN DUPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHUKUN DUPLEX?

The professionals named in the filing: Architect: ANSUYA A DHAIBAR; Engineer: CHIRAG G BHATT. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHUKUN DUPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHUKUN DUPLEX. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHUKUN DUPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.