Home / Browse projects / Vadodara, Gujarat / SHUKAN ANANTA

Valid until 30 Dec 2019 Mixed Development project

SHUKAN ANANTA

By SHREE JAY AMBE INFRA

RG-GJ-45754 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA03407/120918 · Last updated on GujRERA portal: 21 Aug 2019

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2019Possession promisedno revision filed
43 of 56Construction stages doneacross 7 buildings; furthest along: Sanitary fittings within the flats, 90%
90 of 203Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

SHUKAN ANANTA is a Mixed Development project by SHREE JAY AMBE INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA03407/120918 on 12 Sep 2018. Possession is promised by 30 Dec 2019. 113 of the 203 units on this registration are recorded sold or booked, and 43 of 56 construction stages are filed complete.

At a glance

Project

  • NameSHUKAN ANANTA
  • TypeMixed Development
  • Location
    • SHUKAN ANANTA MUKNAND GROUND
    • KARELIBAUG
    • Nagarwada
    • Vadodara
    • 390018
  • Pincode390018
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA03407/120918
  • ReraGenie IDRG-GJ-45754

Builder

  • NameSHREE JAY AMBE INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2018PromisedDec 2019

Key facts

Registration and timeline

  • StatusValid until 30 Dec 2019
  • Registered on12 Sep 2018
  • Promised completion30 Dec 2019
  • Revised completionNone
  • Buildings7 building records
  • Documents filed42 files

Current status

56%113 of 203 units booked
89.5%Of the estimated cost spent so far

Figures as on 21 Aug 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower D---20020
Tower E---20020
Tower F---20020
Commercial---09393
Tower A---10010
Tower B---20020
Tower C---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 21 Aug 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

43 of 56 construction stages are filed complete across 7 buildings. The stage furthest along is Sanitary fittings within the flats, at 90%.

Tower D94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
Tower E96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%
Tower F96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
Commercial86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing35%
Tower A82%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%
Tower B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower C94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%

Progress on shared amenities19

As on 21 Aug 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes90%
Landscaping and tree plantingYes100%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes55%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes52%
Electrical meter room, sub-station, receiving stationYes55%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,881 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 28.55 cr
Cost incurredRs 25.54 cr
Spent of the estimate89.45%
BuildingWingEstimatedIncurred
Tower ANARs 4.08 crRs 3.65 cr
Tower BNARs 4.08 crRs 3.65 cr
Tower CNARs 4.08 crRs 3.65 cr
Tower DNARs 4.08 crRs 3.65 cr
Tower ENARs 4.08 crRs 3.65 cr
Tower FNARs 4.08 crRs 3.65 cr
CommercialNARs 4.08 crRs 3.65 cr

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA03407/120918 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)21 Aug 2019
Engineer's certificate (Form 2)21 Aug 2019
Accountant's certificate (Form 3)21 Aug 2019
Site photograph, Tower D21 Aug 2019
Site photograph, Tower E21 Aug 2019
Site photograph, Tower F21 Aug 2019
Site photograph, Commercial21 Aug 2019
Site photograph, Tower A21 Aug 2019
Site photograph, Tower B21 Aug 2019
Site photograph, Tower C21 Aug 2019
RERA registration certificate12 Sep 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

56%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHUKAN ANANTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Nagarwada2,900+ in Vadodara

2 kmSHUKAN ANANTAOther 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 42 registered projects within 2 km.

Builder: SHREE JAY AMBE INFRA

SHREE JAY AMBE INFRA has 1 registration on GujRERA, including SHUKAN ANANTA. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHUKAN ANANTA is delayed beyond 30 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHUKAN ANANTA?

The registered promoter entity is SHREE JAY AMBE INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHUKAN ANANTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in SHUKAN ANANTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHUKAN ANANTA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHUKAN ANANTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.