Home / Browse projects / Rajkot, Gujarat / SHUBHJIVAN PARK
SHUBHJIVAN PARK
RG-GJ-39593 · RERA PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA17279/180826/311228 · Last updated on GujRERA portal: 18 Aug 2026
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
SHUBHJIVAN PARK is a Residential/Group Housing project by SHUBHJIVAN BUILDCON in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA17279/180826/311228 on 18 Aug 2026. Possession is promised by 31 Dec 2028. 0 of the 23 units on this registration are recorded sold or booked, and 2 of 9 construction stages are filed complete.
At a glance
Project
- NameSHUBHJIVAN PARK
- TypeResidential/Group Housing
- Location
- SHUBHJIVAN PARK
- BEHIND SERENITY GARDEN
- BHAGIRATH GRANITE CORNER
- KALAWAD ROAD
- RAJKOT
- MUNJKA
- Rajkot
- 360005
- Pincode360005
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA17279/180826/311228
- ReraGenie IDRG-GJ-39593
Builder
- NameSHUBHJIVAN BUILDCON
- Entity typePARTNERSHIP FIRM
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Dec 2028
- Registered on18 Aug 2026
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed35 files
Current status
Figures as on 18 Aug 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RESIDENTIAL 23 UNIT | - | - | - | 23 | 0 | 23 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building1
As on 18 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 55%.
RESIDENTIAL 23 UNIT: 39% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 55% |
| Slabs of Super Structure | 50% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 20% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Progress on shared amenities19
As on 18 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 0% |
| Water supply | Yes | 15% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 10% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | Yes | 0% |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| RESIDENTIAL 23 UNIT | NA | Rs 4.00 cr | Rs 1.32 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prithvirajsinh Bilkha |
| Engineer | SHAH NIRALI KAMLESHBHAI |
Documents filed35
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA17279/180826/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| RERA registration certificate | 18 Aug 2026 |
| Architect's certificate (Form 1) | 12 Aug 2026 |
| Engineer's certificate (Form 2) | 12 Aug 2026 |
| Engineer's certificate annexure | 12 Aug 2026 |
| Accountant's certificate (Form 3) | 12 Aug 2026 |
| Site photograph, RESIDENTIAL 23 UNIT | 12 Aug 2026 |
| Site photograph, RESIDENTIAL 23 UNIT | 12 Aug 2026 |
| Proforma agreement for sale | - |
| Auditor's report (3 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Declaration in Form B | - |
| Declaration in Form B1 | - |
| Declaration in Form B2 | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Statutory document | - |
| Other document | - |
| Proforma sale deed | - |
| Project photograph | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Rajkot
Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.
Keep SHUBHJIVAN PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MUNJKA1,800+ in Rajkot
Filed coordinates, straight-line distance. 104 registered projects within 2 km.
Smart Ghar 3
RAJKOT MUNICIPAL CORPORATION
SANATAN
SANATAN INFRACON LLP
PMAY EWS- I
RAJKOT URBAN DEVELOPMENT AUTHORITY
PMAY EWS- II
RAJKOT URBAN DEVELOPMENT AUTHORITY
Titanium One
NDK BUILDCON INDIA PRIVATE LIMITED
Smart Ghar 2
RAJKOT MUNICIPAL CORPORATION
See every Rajkot project, with the district possession charts
Builder: SHUBHJIVAN BUILDCON
SHUBHJIVAN BUILDCON has 1 registration on GujRERA, including SHUBHJIVAN PARK. Read the full track record. See more projects on the Rajkot district page.
Frequently asked questions
What are my rights if SHUBHJIVAN PARK is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SHUBHJIVAN PARK?
The registered promoter entity is SHUBHJIVAN BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SHUBHJIVAN PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SHUBHJIVAN PARK?
The professionals named in the filing: Architect: Prithvirajsinh Bilkha; Engineer: SHAH NIRALI KAMLESHBHAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHUBHJIVAN PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.