Registration approved No litigation declared Mixed Development project

SHRIYA LAKE VIEW

By SHRIYA ANURAJ PROPERTIES

RG-KA-91420 · RERA PRM/KA/RERA/1259/479/PR/060324/006680 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
0 of 15Construction stages donefurthest along: Earth work and other leveling..., 98%
137 of 174Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 162 documents Report an error

SHRIYA LAKE VIEW is a Mixed Development project by SHRIYA ANURAJ PROPERTIES in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/479/PR/060324/006680 on 6 Mar 2024. Possession is promised by 20 Dec 2029. 37 of the 174 units on this registration are recorded sold or booked, and 0 of 15 construction stages are filed complete.

At a glance

Project

  • NameSHRIYA LAKE VIEW
  • TypeMixed Development
  • Location
    • Hubballi
    • Dharwad
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1259/479/PR/060324/006680
  • ReraGenie IDRG-KA-91420

Builder

  • NameSHRIYA ANURAJ PROPERTIES
  • Entity typePartnership Firm
  • GSTIN29AECPV0017L2ZB
  • Authorized SignatoryVENKAT RAGHUNANDAN BUDUGUMPI

Key dates

this monthRegisteredMar 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Mar 2024
  • Promised completion20 Dec 2029
  • Revised completionNone
  • Buildings6 building records
  • Documents filed162 files

Current status

21%37 of 174 units booked
3.4%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---36036
BLOCK B---36036
BLOCK C---36036
BLOCK D---36036
BLOCK E---24024
CLUB HOUSE---066

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 15 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 98%.

Building: 34% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work98%
Foundation footing work95%
Upto Plinth Level80%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)60%
Retaining wall (All types)70%
RCC or MS Framed structure40%
Masonry Construction35%
Plastering inside , outside & Ceiling20%
Joinery: Doors, Windows, Ventilators etc5%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing10%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable
Common storage spacesYes0%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
Raghuveer Narayan Nayak--
Samarth Bhat--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 66.68 cr
Cost incurredRs 2.29 cr
Spent of the estimate3.43%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 62.80 crRs 2.27 cr
Payment of taxesRs 2.38 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 50.00 lakh-
On-site expenditure-Site OverheadRs 45.00 lakh-
On-site expenditure-Consultants FeesRs 40.00 lakh-
On-site expenditure-Salaries of workersRs 15.00 lakhRs 1.93 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVENUGOPAL B
EngineerPrakash Chavan
Chartered AccountantSANTHOSHAKUMAR PATIL

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed162

As listed on the registration, under the names the promoter filed them with; the newest 80 of 162 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/479/PR/060324/006680 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA certificate- Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: 26-27 Q2 SLV Architect Certificate (QU).pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: 2026-27 Q2 SLV Engineer Certificate (QU).pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 -CA Certificate.pdf12 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: 26-27 Q1 SLV Architect Certificate (QU).pdf12 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: 2026-27 Q1 SLV Engineer Certificate (QU).pdf12 Jul 2026
Q1 2026-27 Water supply and sewage board12 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)12 Jul 2026
Q1 2026-27 KPTCL- BESCOM12 Jul 2026
Q1 2026-27 Fire and Safety12 Jul 2026
Q1 2026-27 Airport Authority of India12 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department12 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA -Q-3 CA Certificate-N.pdf21 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: 25-26 Q4 SLV Architect Certificate (QU).pdf21 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: 2025-26 Q4 SLV Engineer Certificate (QU).pdf21 Apr 2026
Q4 2025-26 Water supply and sewage board21 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)21 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)21 Apr 2026
Q4 2025-26 KPTCL- BESCOM21 Apr 2026
Q4 2025-26 Fire and Safety21 Apr 2026
Q4 2025-26 Airport Authority of India21 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department21 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA -Q-3 CA Certificate_compressed.pdf20 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: 25-26 Q3 SLV Architect Certificate (QU).pdf20 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: 2025-26 Q3 SLV Engineer Certificate (QU).pdf20 Jan 2026
Q3 2025-26 Water supply and sewage board20 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)20 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)20 Jan 2026
Q3 2025-26 KPTCL- BESCOM20 Jan 2026
Q3 2025-26 Fire and Safety20 Jan 2026
Q3 2025-26 Airport Authority of India20 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department20 Jan 2026
Source of fundFile: 1 Source of fund.pdf22 Feb 2024
Suraj Alwandi ITRFile: 1 Suraj Alwandi ITR.pdf22 Feb 2024
Suraj Alwandi Bank Statement April 23 to 05-02-24File: 1 Suraj Alwandi Bank Statement April 23 to 05-02-24.pdf22 Feb 2024
Venkat Raghunandan ITRFile: 1 Venkat Raghunandan ITR.pdf22 Feb 2024
Venkat Bank Statement 01-04-23 to 21-02-24File: 1 Venkat Bank Statement 01-04-23 to 21-02-24.pdf22 Feb 2024
Balance Sheet FY 22-23File: 1 Balance Sheet FY 22-23.pdf22 Feb 2024
Loan Sanction LetterFile: 1 Loan Sanction Letter.pdf22 Feb 2024
Profit and Loss FY 22-23File: 1 Profit and Loss FY 22-23.pdf22 Feb 2024
Bank Confirmation LetterFile: 1 Bank Confirmation Letter.pdf6 Feb 2024
FY 20 -21File: 2 FY 20 -21.pdf6 Feb 2024
Balance Sheet FY 2021-22File: 2 Balance Sheet FY 2021-22.pdf6 Feb 2024
Profit and Loss FY 2021-22File: 2 Profit and Loss FY 2021-22.pdf6 Feb 2024
Balance Sheet FY 22-23File: 2 Balance Sheet FY 22-23.pdf6 Feb 2024
Profit and Loss FY 22-23File: 2 Profit and Loss FY 22-23.pdf6 Feb 2024
Source of fundFile: 3 Source of fund.pdf6 Feb 2024
EC from 01-04-2007File: 4 EC from 01-04-2007.pdf6 Feb 2024
CDP Map of Proposed SiteFile: 6 CDP Map of Proposed Site.pdf6 Feb 2024
Ground Floor Plan, Section and ElevationFile: 7 Ground Floor Plan, Section and Elevation.pdf6 Feb 2024
Typical 1st to 6th Floor Plan (Block A to E)File: 7 Typical 1st to 6th Floor Plan (Block A to E).pdf6 Feb 2024
Village MapFile: 8 Village Map.pdf6 Feb 2024
KSPCB NOCFile: 9 KSPCB NOC.pdf6 Feb 2024
SEIAA NOCFile: 10 SEIAA NOC.pdf6 Feb 2024
Self Attested Engineer LicenceFile: 12 Self Attested Engineer Licence.pdf6 Feb 2024
Common Area detailsFile: 13 Common Area details.pdf6 Feb 2024
Form 6 Engineer CertificateFile: 14 Form 6 Engineer Certificate.pdf6 Feb 2024
Source of Water SupplyFile: 15 Source of Water Supply.pdf6 Feb 2024
AAI NOCFile: 16 AAI NOC.pdf6 Feb 2024
BSNL NOCFile: 16 BSNL NOC.pdf6 Feb 2024
ESCOM NOCFile: 16 ESCOM NOC.pdf6 Feb 2024
Fire NOCFile: 16 Fire NOC.pdf6 Feb 2024
KSPCB NOCFile: 16 KSPCB NOC.pdf6 Feb 2024
KUIDFC NOCFile: 16 KUIDFC NOC.pdf6 Feb 2024
SEIAA NOCFile: 16 SEIAA NOC.pdf6 Feb 2024
STP DrawingFile: 17 STP Drawing.pdf6 Feb 2024
Land Cost CalculationFile: 18 Land Cost Calculation.pdf6 Feb 2024
Abstract EstimationFile: 19 Abstract Estimation.pdf6 Feb 2024
Form - 5 Architect CertificateFile: Form - 5 Architect Certificate.pdf6 Feb 2024
Gift deed of nayakFile: Gift deed of nayak.pdf6 Feb 2024
Gift Deed of BhatFile: Gift Deed of Bhat.pdf6 Feb 2024
RTC, survey Block NO.459/1+469/18A+469/20+461/1B/3/2+459/2+3/1/1+2-
Mutation, survey Block NO.459/1+469/18A+469/20+461/1B/3/2+459/2+3/1/1+2-

How this compares with Dharwad

21%of this project is bookeddistrict median 38%
29%of Dharwad projects moved their completion datethis one has not
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep SHRIYA LAKE VIEW on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

Builder: SHRIYA ANURAJ PROPERTIES

SHRIYA ANURAJ PROPERTIES has 1 registration on RERA Karnataka, including SHRIYA LAKE VIEW. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if SHRIYA LAKE VIEW is delayed beyond 20 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRIYA LAKE VIEW?

The registered promoter entity is SHRIYA ANURAJ PROPERTIES, a partnership firm as per the filing. Its GSTIN 29AECPV0017L2ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRIYA LAKE VIEW?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHRIYA LAKE VIEW?

The professionals named in the filing: Architect: VENUGOPAL B; Engineer: Prakash Chavan; Chartered Accountant: SANTHOSHAKUMAR PATIL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRIYA LAKE VIEW?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRIYA LAKE VIEW. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRIYA LAKE VIEW to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.