ReraGenieLog inGet a buyer report

Home / Browse projects / Dharwad, Karnataka / SHRINIVAS RESIDENCY

Registration approved Residential/Group Housing project

SHRINIVAS RESIDENCY

By RAVINDRA and ASSOCIATES

RG-KA-32173 · RERA PRM/KA/RERA/1259/410/PR/210804/004215 · Last updated on RERA Karnataka portal: 5 Jul 2021

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 76 documents Report an error

SHRINIVAS RESIDENCY is a Residential/Group Housing project by RAVINDRA and ASSOCIATES in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/410/PR/210804/004215 on 4 Aug 2021. Possession is promised by 31 Mar 2023.

At a glance

Project

  • NameSHRINIVAS RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • Dharwad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1259/410/PR/210804/004215
  • ReraGenie IDRG-KA-32173

Builder

  • NameRAVINDRA and ASSOCIATES
  • Entity typeProprietorship Firm
  • Authorized SignatoryRAVINDRA DESHPANDE
  • OthersRAVINDRA DESHPANDE
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2021PromisedMar 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Aug 2021
  • Promised completion31 Mar 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed76 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---20020

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 5 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 5 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area789 sq m
Named landowners2
LandownerVillageDistrict
RAVINDRA DESHPANDE--
PADMA SHRINIVAS DESHPANDE--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 1.60 cr

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerErShivanand. S Gopai

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed76

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/410/PR/210804/004215 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Area StatementFile: AREA STATEMENT.pdf5 Jul 2021
DeclarationFile: Declaration.pdf5 Jul 2021
NDCFile: N D C.pdf30 Jun 2021
partition deedFile: Partition Dead.pdf30 Jun 2021
Form -BFile: Form-B.pdf30 Jun 2021
ECFile: E C 08-07-2021 to 13-6-2021.pdf30 Jun 2021
AffidavitFile: Affidavit.pdf30 Jun 2021
JDAFile: JDA.pdf30 Jun 2021
Building drawingFile: Building Drawing.pdf30 Jun 2021
Area statementFile: Area Statement.pdf30 Jun 2021
Property cardFile: Property Card.pdf30 Jun 2021
Tax registerFile: Property Tax Register.pdf30 Jun 2021
CertificateFile: Certificate of registration of firm.pdf-
Building Permit-
Village map-
Sale Deed Bond and RTC-
HUBLI DHARWAD PROP LANDUSE-
SPECIFICATIONS-
Encumbrance Certificate-
Affidavit-
JDA Affidavit-
shrinivas aprtment Khata-
AGREEMENT JOINT DEVELOPMENT-
HESCOM-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Fire NOC-
Unnamed document-
Unnamed document-
Waterboard-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Village map-
SPECIFICATIONS-
Land Use certificate-
Unnamed document-
Balance Sheet 2019 - 2020File: BS 2020.pdf-
Balance Sheet 2018 - 2019File: BS 2019.pdf-
Balance Sheet 2017 - 2018File: BS 2018.pdf-
Audited Profit and Loss Statement 2019 - 2020File: PL 2020.pdf-
Audited Profit and Loss Statement 2018 - 2019File: PL 2019.pdf-
Audited Profit and Loss Statement 2017 - 2018File: PL 2018.pdf-
Director's Report 2019 - 2020File: Declaration.pdf-
Director's Report 2018 - 2019File: Declaration.pdf-
Director's Report 2017 - 2018File: Declaration.pdf-
Cash Flow Statement 2019 - 2020File: Declaration.pdf-
Cash Flow Statement 2018 - 2019File: Declaration.pdf-
Auditor's Report 2019 - 2020File: AR 2020.pdf-
Auditor's Report 2018 - 2019File: AR 2019.pdf-
Auditor's Report 2017 - 2018File: AR 2018.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR V 2020.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR V 2019.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR V 2018.pdf-
Form-B-
Tower Excel SheetFile: PRM_KA_RERA_1259_410_PR_210804_004215 (2).xlsx-
Occupancy CertificateFile: Occupancy certificate 29 07 2022.pdf-
Architect certificate for having completed the work(in format no 5)File: ARC Completion.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: C A completion.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf-
Eng Certificate completionFile: ENG Completion.pdf-
Agreement saleFile: Agreement sale 10 11 2020.pdf-
sale deedFile: Sale deed 21 06 2022.pdf-

How this compares with Dharwad

29%of Dharwad projects moved their completion datethis one has not
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep SHRINIVAS RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

2 kmSHRINIVAS RESIDENCYOther 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 32 registered projects within 2 km.

Builder: RAVINDRA and ASSOCIATES

RAVINDRA and ASSOCIATES has 2 registrations on RERA Karnataka, including SHRINIVAS RESIDENCY and SHAKAMBARI RESIDENCY. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if SHRINIVAS RESIDENCY is delayed beyond 31 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRINIVAS RESIDENCY?

The registered promoter entity is RAVINDRA and ASSOCIATES, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRINIVAS RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHRINIVAS RESIDENCY?

The professionals named in the filing: Engineer: ErShivanand. S Gopai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRINIVAS RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRINIVAS RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRINIVAS RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.