Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jan 2023Possession promisedmoved 6 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 49 documents Report an error

SHRIDATTA RESIDENCY BLOCK F is a Residential/Group Housing project by SHRIDATTA INFRATECH PRIVATE LIMITED in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/479/PR/190921/002904 on 21 Sep 2019. Possession is promised by 31 Jan 2023. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameSHRIDATTA RESIDENCY BLOCK F
  • TypeResidential/Group Housing
  • Location
    • Hubballi
    • Dharwad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1259/479/PR/190921/002904
  • ReraGenie IDRG-KA-21821

Builder

  • NameSHRIDATTA INFRATECH PRIVATE LIMITED
  • Entity typeCompany
  • CINU45203KA2012PTC063474
  • Authorized SignatoryPRAKASH DATTATREYA JOSHI
  • DirectorPRAKASH DATTATREYA JOSHI
  • Other registrations2 more →

Key dates

this monthRegisteredSep 2019First promiseJul 2022Revised toJan 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Sep 2019
  • Promised completion31 Jan 2023
  • Revised completionRevised to 31 Jan 2023 (originally 31 Jul 2022)
  • Buildings1 building record
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRIDATTA RESIDENCY BLOCK F-----16

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area730 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.80 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHANAWAZ M KATHEWADI
EngineerGalagali Associates

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJul 2022 → Jan 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/479/PR/190921/002904 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Incorporation Certificates_compressed.pdf-
Commencement Certificate permission copy block - f-
Approved Building Plan - Drawing-
Approved Layout Plan-
Sale Deed as per RERA-
FINAL AGREEMENT FOR SALE-
Sale Deed of Land Owner-
Approved Section of Building Drawing-
Area Development Plan of Project Area-
Allotment Letter-
Brochure-
NOC Water and Fire Board 2 pages-
SPECIFICATIONS-
E C 15_compressed-
affidavit-
Joint Affidavit cum declaration-
Utar-
Joint Development Agreement Merged OK-
Mutation-
CONVERSION ORDER - NA Order Copy-
NOC Water and Fire Board 2 pages-
Existing Layout Plan-
Existing Section Plan and Specification-
NA for change of Land Use-
Balance Sheet 2017 - 2018File: Balance Sheet.pdf-
Balance Sheet 2016 - 2017File: Balance Sheet.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit & Loss.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit & Loss.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit & Loss.pdf-
Director's Report 2017 - 2018File: Director's Report.pdf-
Director's Report 2016 - 2017File: Director's Report.pdf-
Director's Report 2015 - 2016File: Director's Report.pdf-
Cash Flow Statement 2017 - 2018File: Cash Flow FY 2017-2018.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow FY 2016-2017.pdf-
Auditor's Report 2017 - 2018File: Auditor's Report.pdf-
Auditor's Report 2016 - 2017File: Auditor's Report.pdf-
Auditor's Report 2015 - 2016File: Auditor Report.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: Acknowledgement.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Acknowledgement.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Acknowledgement.pdf-
form B-
Prospectus/BrochureFile: Brochure.jpg-
Advertisement Copy 1File: Typical Floor Plan.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1259_479_PR_190921_002904.xlsx-
Occupancy CertificateFile: Completion Certiifcate.pdf-
Completion certificateFile: Completion Certiifcate.pdf-
Registered Agreement of SaleFile: SALE AGREEMENT F BLOCK.pdf-
Registered conveyance deed for an individual unitFile: SALE AGREEMENT F BLOCK.pdf-

How this compares with Dharwad

29%of Dharwad projects moved their completion datethis one moved by 6 months
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep SHRIDATTA RESIDENCY BLOCK F on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

Builder: SHRIDATTA INFRATECH PRIVATE LIMITED

Shridatta Infratech Private Limited has 3 registrations on RERA Karnataka, including Datt Vihar and SHRIDATTA RESIDENCY BLOCK F. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if SHRIDATTA RESIDENCY BLOCK F is delayed beyond 31 Jan 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRIDATTA RESIDENCY BLOCK F?

The registered promoter entity is SHRIDATTA INFRATECH PRIVATE LIMITED, a company as per the filing. Its CIN U45203KA2012PTC063474 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRIDATTA RESIDENCY BLOCK F?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHRIDATTA RESIDENCY BLOCK F?

The professionals named in the filing: Architect: SHANAWAZ M KATHEWADI; Engineer: Galagali Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRIDATTA RESIDENCY BLOCK F?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRIDATTA RESIDENCY BLOCK F. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRIDATTA RESIDENCY BLOCK F to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.