Valid until 31 Dec 2026 Commercial project

SHREENATHJI HEIGHTS

By SHREE HARIOM CO OPERATIVE COMMERCIAL SERVICE SOCIETY LIMITED

RG-GJ-73827 · RERA PR/GJ/KUTCH/GANDHIDHAM/Others/CAA11458/150323 · Last updated on GujRERA portal: 2 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2026Possession promisedno revision filed
8 of 9Construction stages donefurthest along: External plumbing and external plaster, 75%
13 of 69Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SHREENATHJI HEIGHTS is a Commercial project by SHREE HARIOM CO OPERATIVE COMMERCIAL SERVICE SOCIETY LIMITED in Kutch, Gujarat, registered with GujRERA as PR/GJ/KUTCH/GANDHIDHAM/Others/CAA11458/150323 on 15 Mar 2023. Possession is promised by 31 Dec 2026. 56 of the 69 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHREENATHJI HEIGHTS
  • TypeCommercial
  • Location
    • PLOT NO. 2
    • SECTOR 8
    • GANDHIDHAM
    • Gandhidham
    • Kutch
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/KUTCH/GANDHIDHAM/Others/CAA11458/150323
  • ReraGenie IDRG-GJ-73827

Builder

  • NameSHREE HARIOM CO OPERATIVE COMMERCIAL SERVICE SOCIETY LIMITED
  • Entity typeOther

Key dates

this monthRegisteredMar 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on15 Mar 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed38 files

Current status

81%56 of 69 units booked
75.0%Of the estimated cost spent so far

Figures as on 2 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block 1---06969

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 2 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 75%.

Block 1: 97% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 2 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes20%
Drinking water facilitiesYes20%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes100%
Plinth protectionYes100%
Water tankYes100%
Other requirementsYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,569 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 3.00 cr
Cost incurredRs 2.25 cr
Spent of the estimate75.0%
BuildingWingEstimatedIncurred
Block 1NARs 3.00 crRs 2.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHAUMIKKUMAR C. DONGA
EngineerSUNIL GUPTA

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/KUTCH/GANDHIDHAM/Others/CAA11458/150323 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)2 Oct 2024
Engineer's certificate annexure2 Oct 2024
RERA registration certificate15 Mar 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Kutch

81%of this project is bookeddistrict median 42%
6%of Kutch projects moved their completion datethis one has not

Computed across the 80 Kutch projects on ReraGenie, from their own filings.

Keep SHREENATHJI HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kutch80 in Kutch

2 kmSHREENATHJI HEIGHTSOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: SHREE HARIOM CO OPERATIVE COMMERCIAL SERVICE SOCIETY LIMITED

SHREE HARIOM CO OPERATIVE COMMERCIAL SERVICE SOCIETY LIMITED has 1 registration on GujRERA, including SHREENATHJI HEIGHTS. Read the full track record. See more projects on the Kutch district page.

Frequently asked questions

What are my rights if SHREENATHJI HEIGHTS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREENATHJI HEIGHTS?

The registered promoter entity is SHREE HARIOM CO OPERATIVE COMMERCIAL SERVICE SOCIETY LIMITED. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREENATHJI HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREENATHJI HEIGHTS?

The professionals named in the filing: Architect: BHAUMIKKUMAR C. DONGA; Engineer: SUNIL GUPTA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREENATHJI HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREENATHJI HEIGHTS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREENATHJI HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.