Home / Browse projects / Surat, Gujarat / SHREE SHILPRAJ RESIDENCY

Valid until 31 Mar 2022 Plotted Development project

SHREE SHILPRAJ RESIDENCY

By PRATIKSHA CONSTRUCTION

RG-GJ-40440 · RERA PR/GJ/SURAT/SURAT CITY/SUDA/PAA07881/070121 · Last updated on GujRERA portal: 22 Mar 2022

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Mar 2022Possession promisedno revision filed
148 of 162Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

SHREE SHILPRAJ RESIDENCY is a Plotted Development project by PRATIKSHA CONSTRUCTION in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/SUDA/PAA07881/070121 on 7 Jan 2021. Possession is promised by 31 Mar 2022. 14 of the 162 units on this registration are recorded sold or booked.

At a glance

Project

  • NameSHREE SHILPRAJ RESIDENCY
  • TypePlotted Development
  • Location
    • BLOCK NO. 240 AND 242 PAIKEE SUB DIVISION 1
    • RS NO.35/2/B AND 35/2/A
    • OPPOSITE
    • SHREEJI NAGRI SOCIETY
    • UGAT ROAD
    • MOJE-JAHANGIRABAD
    • Jahangirabad
    • Surat...
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/SUDA/PAA07881/070121
  • ReraGenie IDRG-GJ-40440

Builder

  • NamePRATIKSHA CONSTRUCTION
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2021PromisedMar 2022

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2022
  • Registered on7 Jan 2021
  • Promised completion31 Mar 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

9%14 of 162 units booked
100.0%Of the estimated cost spent so far

Figures as on 22 Mar 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PLOT---1620162

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 22 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

PLOT:

ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 22 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,116 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.10 cr
Cost incurredRs 2.10 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
PLOTNARs 2.10 crRs 2.10 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHASMUKH A. PATEL
EngineerDHAVAL M. BADARUKHIYA

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/SUDA/PAA07881/070121 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)22 Mar 2022
Architect's certificate (Form 1)21 Mar 2022
Engineer's certificate (Form 2)21 Mar 2022
Engineer's certificate annexure21 Mar 2022
Site photograph, PLOT21 Mar 2022
RERA registration certificate7 Jan 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

9%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep SHREE SHILPRAJ RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Jahangirabad2,600+ in Surat

2 kmSHREE SHILPRAJ RESIDENCYOther 160Dot size: filed unitsN

Filed coordinates, straight-line distance. 160 registered projects within 2 km.

Builder: PRATIKSHA CONSTRUCTION

PRATIKSHA CONSTRUCTION has 1 registration on GujRERA, including SHREE SHILPRAJ RESIDENCY. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if SHREE SHILPRAJ RESIDENCY is delayed beyond 31 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREE SHILPRAJ RESIDENCY?

The registered promoter entity is PRATIKSHA CONSTRUCTION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREE SHILPRAJ RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE SHILPRAJ RESIDENCY?

The professionals named in the filing: Architect: HASMUKH A. PATEL; Engineer: DHAVAL M. BADARUKHIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SHILPRAJ RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SHILPRAJ RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SHILPRAJ RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.