ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / SHREE RANG VATIKA

Valid until 30 Apr 2027 Residential/Group Housing project

SHREE RANG VATIKA

By SHREE RANG DEVELOPERS

RG-GJ-28314 · RERA PR/GJ/VADODARA/KARJAN/Others/RAA12805/240124/311226 · Last updated on GujRERA portal: 23 Feb 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
28 of 126Construction stages doneacross 14 buildings; furthest along: Slabs of Super Structure, 95%
10 of 49Units unsoldnot recorded sold or booked
Jump to the 57 documents Report an error

SHREE RANG VATIKA is a Residential/Group Housing project by SHREE RANG DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/KARJAN/Others/RAA12805/240124/311226 on 24 Jan 2024. Possession is promised by 30 Apr 2027. 39 of the 49 units on this registration are recorded sold or booked, and 28 of 126 construction stages are filed complete.

At a glance

Project

  • NameSHREE RANG VATIKA
  • TypeResidential/Group Housing
  • Location
    • LAND BEARING KHATA NO 3328 BLOCK NO 650
    • MOJE: KARJAN TALUKA: KARJAN
    • KARJAN
    • Vadodara
    • 391240
  • Pincode391240
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/KARJAN/Others/RAA12805/240124/311226
  • ReraGenie IDRG-GJ-28314

Builder

  • NameSHREE RANG DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredJan 2024PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on24 Jan 2024
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings14 building records
  • Documents filed57 files

Current status

80%39 of 49 units booked
57.1%Of the estimated cost spent so far

Figures as on 23 Feb 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE C---202
TYPE B---303
TYPE E---12012
TYPE D---101
TYPE G---303
TYPE F---303
TYPE I---404
TYPE H---101
TYPE K---303
TYPE J---101
TYPE M---202
TYPE L---101
TYPE N---101
TYPE A---12012

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building14

As on 23 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 126 construction stages are filed complete across 14 buildings. The stage furthest along is Slabs of Super Structure, at 95%.

TYPE C52%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing40%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE B46%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE E48%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE D44%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats45%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE G43%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing10%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE F48%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats55%
Sanitary fittings within the flats25%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE I51%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE H43%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats40%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE K46%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE J51%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE M47%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE L38%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure75%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE N45%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats30%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE A48%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats55%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing35%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 23 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityNoNot applicable
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,171 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 8.50 cr
Cost incurredRs 4.85 cr
Spent of the estimate57.06%
BuildingWingEstimatedIncurred
TYPE ANARs 2.08 crRs 1.15 cr
TYPE ENARs 2.08 crRs 1.25 cr
TYPE INARs 68.04 lakhRs 42.00 lakh
TYPE GNARs 57.66 lakhRs 25.00 lakh
TYPE KNARs 51.03 lakhRs 27.50 lakh
TYPE BNARs 50.70 lakhRs 25.00 lakh
TYPE FNARs 50.70 lakhRs 35.00 lakh
TYPE CNARs 38.40 lakhRs 25.00 lakh
TYPE MNARs 33.44 lakhRs 19.50 lakh
TYPE LNARs 16.84 lakhRs 7.00 lakh
TYPE NNARs 16.70 lakhRs 9.50 lakh
TYPE JNARs 16.65 lakhRs 11.50 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARESH B GANDHI
EngineerDIYA STRUCTURAL CONSULTANTS

Documents filed57

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/KARJAN/Others/RAA12805/240124/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)23 Feb 2026
Engineer's certificate annexure23 Feb 2026
Accountant's certificate (Form 3)23 Feb 2026
Architect's certificate (Form 1)21 Feb 2026
Site photograph, TYPE C21 Feb 2026
Site photograph, TYPE B21 Feb 2026
Site photograph, TYPE E21 Feb 2026
Site photograph, TYPE D21 Feb 2026
Site photograph, TYPE G21 Feb 2026
Site photograph, TYPE F21 Feb 2026
Site photograph, TYPE I21 Feb 2026
Site photograph, TYPE H21 Feb 2026
Site photograph, TYPE K21 Feb 2026
Site photograph, TYPE J21 Feb 2026
Site photograph, TYPE M21 Feb 2026
Site photograph, TYPE L21 Feb 2026
Site photograph, TYPE N21 Feb 2026
Site photograph, TYPE A21 Feb 2026
RERA registration certificate24 Jan 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

80%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHREE RANG VATIKA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KARJAN2,900+ in Vadodara

2 kmSHREE RANG VATIKAOther 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: SHREE RANG DEVELOPERS

Shree Rang Developers has 3 registrations on GujRERA, including Shree Rang Nagar & Mall and SHREE RANG VATIKA. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHREE RANG VATIKA is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREE RANG VATIKA?

The registered promoter entity is SHREE RANG DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREE RANG VATIKA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE RANG VATIKA?

The professionals named in the filing: Architect: HARESH B GANDHI; Engineer: DIYA STRUCTURAL CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE RANG VATIKA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE RANG VATIKA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE RANG VATIKA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.