ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / SHREE KRISHNA VILLA

Valid until 30 Oct 2027 Residential/Group Housing project

SHREE KRISHNA VILLA

By AKSHAR INFRA

RG-GJ-67580 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA15050/010425/300627 · Last updated on GujRERA portal: 16 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Oct 2027Possession promisedno revision filed
2 of 9Construction stages donefurthest along: Internal walls, 65%
17 of 25Units unsoldnot recorded sold or booked
Jump to the 26 documents Report an error

SHREE KRISHNA VILLA is a Residential/Group Housing project by AKSHAR INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA15050/010425/300627 on 1 Apr 2025. Possession is promised by 30 Oct 2027. 8 of the 25 units on this registration are recorded sold or booked, and 2 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHREE KRISHNA VILLA
  • TypeResidential/Group Housing
  • Location
    • SHREE KRISHNA VILLA- Behind BAPS Mandir
    • Beside Sahjanand Flats
    • Atladara
    • Vadodara 390012
    • ATLADRA
    • Vadodara
    • 390012
  • Pincode390012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA15050/010425/300627
  • ReraGenie IDRG-GJ-67580

Builder

  • NameAKSHAR INFRA
  • Entity typePARTNERSHIP FIRM
  • Other registrations9 more →

Key dates

this monthRegisteredApr 2025PromisedOct 2027

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2027
  • Registered on1 Apr 2025
  • Promised completion30 Oct 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed26 files

Current status

32%8 of 25 units booked
43.4%Of the estimated cost spent so far

Figures as on 16 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
25 Residential Unit---25025

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 65%.

25 Residential Unit: 50% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure49%
Internal walls, internal plaster, floorings, doors and windows within flats65%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%

Progress on shared amenities19

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes30%
Water supplyYes30%
Sewerage (chamber, lines, septic tank, STP)Yes40%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes25%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,172 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 7.00 cr
Cost incurredRs 3.04 cr
Spent of the estimate43.44%
BuildingWingEstimatedIncurred
25 Residential UnitNARs 7.00 crRs 3.04 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNIRAV NARESHBHAI NAKRANI
EngineerMEET MUKESH SHAH

Documents filed26

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA15050/010425/300627 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)16 Jul 2026
Engineer's certificate (Form 2)16 Jul 2026
Engineer's certificate annexure16 Jul 2026
Accountant's certificate (Form 3)16 Jul 2026
Site photograph, 25 Residential Unit16 Jul 2026
RERA registration certificate1 Apr 2025
Proforma agreement for sale-
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-

How this compares with Vadodara

32%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHREE KRISHNA VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near ATLADRA2,900+ in Vadodara

2 kmSHREE KRISHNA VILLAOther 250Dot size: filed unitsN

Filed coordinates, straight-line distance. 250 registered projects within 2 km.

Builder: AKSHAR INFRA

AKSHAR INFRA has 10 registrations on GujRERA, including AKSHAR AFFORD and AKSHAR ICONS. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHREE KRISHNA VILLA is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREE KRISHNA VILLA?

The registered promoter entity is AKSHAR INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREE KRISHNA VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE KRISHNA VILLA?

The professionals named in the filing: Architect: NIRAV NARESHBHAI NAKRANI; Engineer: MEET MUKESH SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE KRISHNA VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE KRISHNA VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE KRISHNA VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.