ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / SHREE KAPILESHWAR ARCADE

Valid until 30 Aug 2030 Commercial project

SHREE KAPILESHWAR ARCADE

By SHREE KAPILESHWAR INFRA

RG-GJ-74455 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/CAA16360/200126/300430 · Last updated on GujRERA portal: 27 Apr 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Aug 2030Possession promisedno revision filed
0 of 9Construction stages donefurthest along: Excavation, 80%
188 of 190Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

SHREE KAPILESHWAR ARCADE is a Commercial project by SHREE KAPILESHWAR INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/CAA16360/200126/300430 on 20 Jan 2026. Possession is promised by 30 Aug 2030. 2 of the 190 units on this registration are recorded sold or booked, and 0 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHREE KAPILESHWAR ARCADE
  • TypeCommercial
  • Location
    • RS 607/A/2
    • TP 28/C MOJE SAYAJIPURA
    • VADODARA
    • SAYAJIPURA
    • Vadodara
    • 390019
  • Pincode390019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/CAA16360/200126/300430
  • ReraGenie IDRG-GJ-74455

Builder

  • NameSHREE KAPILESHWAR INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2026PromisedAug 2030

Key facts

Registration and timeline

  • StatusValid until 30 Aug 2030
  • Registered on20 Jan 2026
  • Promised completion30 Aug 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed39 files

Current status

1%2 of 190 units booked
2.3%Of the estimated cost spent so far

Figures as on 27 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower - A---0120190

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 9 construction stages are filed complete. The stage furthest along is Excavation, at 80%.

Tower - A: 9% average across the applicable activities

ActivityProgress
Excavation80%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,700 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 29.40 cr
Cost incurredRs 68.26 lakh
Spent of the estimate2.32%
BuildingWingEstimatedIncurred
Tower - ANARs 29.40 crRs 68.26 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHRENIK RAJENDRAKUMAR SONI
EngineerCHIRAG ASHOKBHAI SHAH

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/CAA16360/200126/300430 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)27 Apr 2026
Engineer's certificate (Form 2)27 Apr 2026
Engineer's certificate annexure27 Apr 2026
Accountant's certificate (Form 3)27 Apr 2026
Site photograph, Tower - A17 Apr 2026
RERA registration certificate20 Jan 2026
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Property card 2-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

1%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHREE KAPILESHWAR ARCADE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near SAYAJIPURA2,900+ in Vadodara

2 kmSHREE KAPILESHWAR ARCADEOther 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: SHREE KAPILESHWAR INFRA

SHREE KAPILESHWAR INFRA has 1 registration on GujRERA, including SHREE KAPILESHWAR ARCADE. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHREE KAPILESHWAR ARCADE is delayed beyond 30 Aug 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREE KAPILESHWAR ARCADE?

The registered promoter entity is SHREE KAPILESHWAR INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREE KAPILESHWAR ARCADE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE KAPILESHWAR ARCADE?

The professionals named in the filing: Architect: SHRENIK RAJENDRAKUMAR SONI; Engineer: CHIRAG ASHOKBHAI SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE KAPILESHWAR ARCADE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE KAPILESHWAR ARCADE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE KAPILESHWAR ARCADE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.