Home / Browse projects / Dharwad, Karnataka / shree guruji enclave

Registration approved Residential/Group Housing project

shree guruji enclave

By CG PARIVAR CONSTRUCTIONS

RG-KA-72712 · RERA PRM/KA/RERA/1259/410/PR/180208/002195 · Last updated on RERA Karnataka portal: 12 Apr 2021

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2021Possession promisedmoved 18 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 72 documents Report an error

shree guruji enclave is a Residential/Group Housing project by CG PARIVAR CONSTRUCTIONS in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/410/PR/180208/002195 on 8 Feb 2018. Possession is promised by 15 Sep 2021. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • Nameshree guruji enclave
  • TypeResidential/Group Housing
  • Location
    • Dharwad
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1259/410/PR/180208/002195
  • ReraGenie IDRG-KA-72712

Builder

  • NameCG PARIVAR CONSTRUCTIONS
  • Entity typePartnership Firm
  • Authorized SignatorySANDEEP ANGADI
  • OthersSandeep Angadi
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2018First promiseMar 2020Revised toSep 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on8 Feb 2018
  • Promised completion15 Sep 2021
  • Revised completionRevised to 15 Sep 2021 (originally 31 Mar 2020)
  • Buildings1 building record
  • Documents filed72 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shree Guruji Enclave---39039

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Apr 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 12 Apr 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,584 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.71 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR K Group Architects
EngineerMohan.M.Dandin

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2020 → Sep 2020

No reason recorded in the filing

EX/PRM/KA/RERA/1259/410/PR/220711/002195Sep 2020 → Sep 2021

Reason as filed by the promoterForce Majeure

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed72

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/410/PR/180208/002195 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Corrected CA Certificate_Funds Used_Ex3 with one bank accountFile: CA Certificate_Funds used_EX3.pdf12 Apr 2021
Corrected CA Certificate_Funds Required_Ex4 with one bank accountFile: CA Certificate_Pending_Ex4.pdf12 Apr 2021
CA Certificate_Funds Used_Ex3File: CA Certificate_Funds used_EX3.pdf26 Mar 2021
CA Certificate_Funds Required_Ex4File: CA Certificate_Pending_Ex4.pdf26 Mar 2021
CA CertificateFile: CA Certificate_Ex3_Ex4.pdf27 Jan 2021
Commencement CertificateFile: Approval letter 2017.pdf27 Jan 2021
Architect Certificate for Commencement DateFile: Commencement Date.pdf27 Jan 2021
Upload designated bank account statement till date (A/c-915020019478899)File: 8899.pdf1 Dec 2020
Escrow Account deposits consideredFile: 401_CON0.pdf1 Dec 2020
Escrow Account deposits consideredFile: 401.pdf1 Dec 2020
Commencement Certificate to be uploaded issued by the planning authorityFile: Approval letter 2017.pdf1 Dec 2020
Bank Change request letter & AcknowledgementFile: ack1.pdf1 Dec 2020
Old Bank change request letter of 2018 and acknoeldgementFile: Letter.pdf1 Dec 2020
Approved PlanFile: Approval plan 2017.jpg1 Dec 2020
Sold & Unsold UnitsFile: Sold & Unsold.pdf8 Nov 2020
Date ofCommencement of projectFile: Commencement Date.pdf8 Nov 2020
Bank Account ChangeFile: Letter_Bank Change_RERA.pdf8 Nov 2020
CertificateFile: Firm Reg certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect certificate - Status of work.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer certificate - Status of work.pdf-
CA Certificate for Funds UtilizationFile: CA Fund utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect certificate - Pending works.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer certificate - Pending works.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Fund Required.pdf-
AffidavitFile: Form EX - 7.pdf-
Latest Encumbrance CertificateFile: EC.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letter.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold and unsold details.pdf-
NOC DetailsFile: Revised Approval letter.pdf-
Document 1File: Form B.pdf-
10Approved Plan-
20sale deed Format-
12Agreement_for_Sale_of_RERA-
Sale Deed -NAP-
14Approved Plan-
17project report-
NA Conversion-
17project report-
8EC1-
Kahata_new-
13Land Doc&Location-
NA Conversion_06012018-
NA Conversion-
14Approved Plan-
Balance Sheet 2016 - 2017File: balancesheet.pdf-
Balance Sheet 2015 - 2016File: Certificate CG Construction.pdf-
Balance Sheet 2014 - 2015File: Certificate CG Construction.pdf-
Audited Profit and Loss Statement 2016 - 2017File: 2Profit and loss.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Certificate CG Construction.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Certificate CG Construction.pdf-
Director's Report 2015 - 2016File: Certificate CG Construction.pdf-
Director's Report 2014 - 2015File: Certificate CG Construction.pdf-
Cash Flow Statement 2015 - 2016File: Certificate CG Construction.pdf-
Auditor's Report 2016 - 2017File: 53CB_3CD.pdf-
Auditor's Report 2015 - 2016File: Certificate CG Construction.pdf-
Auditor's Report 2014 - 2015File: Certificate CG Construction.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: 6ITR Ack.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Certificate CG Construction.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: Certificate CG Construction.pdf-
Form B-
Prospectus/BrochureFile: PRKN171005002195.pdf-
Advertisement Copy 1File: Paper- Ad. Shree Guruji Englave-15.04.2018.jpeg-
Tower Excel SheetFile: PRM_KA_RERA_1259_410_PR_180208_002195 (1).xlsx-
Stability CertificateFile: Engineer Certificate.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: Completion Certificate.pdf-
NOC issued by the Fire Force department after completion of workFile: Completion Certificate.pdf-
Occupancy CertificateFile: Completion Certificate.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Meter Sanction letter.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4 CC.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit for Project Completion.pdf-
Transformer installation ApprovalFile: Transformer installation Approval.pdf-

How this compares with Dharwad

29%of Dharwad projects moved their completion datethis one moved by 18 months
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep shree guruji enclave on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

Builder: CG PARIVAR CONSTRUCTIONS

CG PARIVAR CONSTRUCTIONS has 2 registrations on RERA Karnataka, including shree guruji enclave and SHRI GURUJI GREEN PARK. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if shree guruji enclave is delayed beyond 15 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of shree guruji enclave?

The registered promoter entity is CG PARIVAR CONSTRUCTIONS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in shree guruji enclave?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at shree guruji enclave?

The professionals named in the filing: Architect: R K Group Architects; Engineer: Mohan.M.Dandin. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in shree guruji enclave?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About shree guruji enclave. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save shree guruji enclave to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.